Market Role Code
ES
Harmonised context
ES

Clarification of Supplier of Last Resort Obligations under the REC

Date of latest update
Type
Change
ID
R0057
Change Category
Change Path
Priority
Urgent
No
Latest Update
04/08/2023 - Change Proposal has been withdrawn as agreed with the Proposer. The Problem Statement was addressed through C3-0047 - Updates to PAB Procedures.
Summary
Within Schedule 19 – Market Exit and Supplier of Last Resort there is currently no consideration of circumstances where the Replacement Supplier is unable to fulfil its REC obligations in respect of Consumers transferred to them, due to them having little or no control over the processes of the failed supplier or it’s administrator. This change seeks to define when the Replacement Supplier is responsible for obligations relating to the Consumers gained through a Supplier of Last Resort (SoLR) Process.
Proposer
admin
Impacted Consumers
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer when my Energy Supplier goes out of business and I am transferred to a Replacement Supplier, I want my supply transfer to be handled quickly and have confidence that my new Supplier has all the necessary data to set up my account and bill me correctly from the transfer date, and if the Replacement Supplier fails to provide the expected level of service they will be appropriately held accountable.
  2. As a Replacement Supplier, I want the limitations affecting my ability to meet my REC obligations to be understood by the REC Code Manager and the Performance Assurance Board, so that any breaches of obligations are considered fairly and any limitations are taken into consideration.
  3. As the Code Manager I want to apply appropriate and proportionate Performance Assurance Techniques, taking in to account the ability of a Replacement Supplier to meet their obligations under the REC.
Proposed Solution Document
Document title
R0057 Draft Legal Text
Upload document
R0057 Draft Legal Text.zip
Archive
Off
Problem Statement
Currently, Replacement Suppliers are responsible for all obligations of the failed supplier from the date and time set out in the Last Resort Supply Direction, this includes a period of time prior to Consumer accounts transferring to the Replacement Supplier’s systems, limiting their ability to fulfil these obligations. This means that a Replacement Supplier may experience issues with the Performance Assurance obligations for which they are responsible, but do not have direct control over. Any breaches of obligations by a Replacement Supplier need to be considered fairly and any limitations the Replacement Supplier may face are taken into consideration.
Stages Selection
R0057 - Change Proposal Form
R0057 - Solution Options
R0057 - Consolidated Impact Assessment Responses
R0057 - Change Proposal Plan v1.0
R0057 - Initial Assessment Report v1.0 (Approved)
R0057 - Preliminary Change Report V1.0 (Approved)
Company Name
EDF
Review status
Review required

24/7 Emergency Metering Service

Date of latest update
Type
Change
ID
R0053
Change Category
Priority
Urgent
No
Latest Update
01/05/25 - Proposal withdrawn at proposers request.
Summary
This change has been raised to address the issue that Suppliers currently are not required to provide a 24/7 emergency metering service that enables a Consumer to speak to an agent and/or receive a visit from a field operative outside normal business hours when faced with power loss situation relating to a metering issue. This Change Proposal has been raised to assess and consider the options to address this issue.
Proposer
Bryan Heap
Change Plan

Solution Analysis and Development

In Progress

Start:

17 Jun 2022

Due:

26 May 2023

Completion:

Impacted Consumers
Impacted REC Documents
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As an Energy Consumer, I want my metering fault to be identified and fixed as soon as possible, so that I am not left in a situation where I have no electricity for an extended period. I want to be able to contact the correct Party to fix my metering fault. I want my personal circumstances to be taken in to account when arranging for a fault to be fixed out of standard working hours.
  2. As a DNO, where there is a meter fault identified I want to be able to contact the Energy Supplier to rectify this, no matter what day or time this is identified, so that Consumers are not left without power for extended periods, during which time they may require ongoing help, support and communication. As an Energy Supplier, I want to provide my Customers with accurate and relevant Emergency contact information. As an Energy Supplier, I want to be able to respond to meter faults in a timely manner and not leave Consumers without power for an extended period.
  3. As a MEM, I want to be notified, in a timely manner, of faults that occur on Metering assets I am responsible for, so that I am able to rectify these without undue detriment being experienced by Consumers
Problem Statement
In situations where an Electricity Consumer experiences a loss of power, the DNOs who attend site to investigate and resolve the issues, are unable to do so when there is a meter issue, which is the responsibility of the Energy Supplier and it’s Appointed agents. When an issue occurs out of hours, or when an Energy Supplier does not have an out of hours metering service in operation, Consumers can be left without power for an extended period, this can create a safety or health concern, particularly for vulnerable Consumers or vulnerable members of their household.
Stages Selection
R0053 - Downloadable Change Proposal Form
R0053 - Change Proposal Plan v1.0 (pre-approval) 27/02/2023
R0053 - Initial Assessment Report v1.1 (Pre-Approval) 06.03.23
R0053 - Initial Assessment Report v2.0 (Approved) 07.03.2023
R0053 - Change Proposal Plan v2.0 (Approved) 07.03.2023
Company Name
Electricity North West Limited
Review status
Review required

Switch Request Objections (Change of Occupier)

Date of latest update
Type
Change
ID
R0051
Change Category
Change Path
Priority
Urgent
No
Latest Update
26/01/2024 - Withdrawn following adoption window closure.
Summary
This Change Proposal looks to clarity obligations regarding the losing suppliers' rights to object and the circumstances surrounding registrations by gaining suppliers, following the migration from the MRA to the REC.
Proposer
admin
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Stages Selection
R0051 - Downloadable CP form
Company Name
Business Energy Direct
Review status
Review required

Clarification of REC Maintenance of Qualification Schedule

Date of latest update
Type
Change
ID
R0050
Urgent
No
Latest Update
Change withdrawn following agreement to combine with R0059
Summary
-
Proposer
Bryan Heap
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
R0050 - Downloadable Change Proposal form
Company Name
-
Review status
Review required

REC V3.0

Date of latest update
Type
Change
ID
R0041
Change Category
Urgent
Yes
Latest Update
-
Summary
-
Proposer
Alasdair MacMillan
Change Plan

Legal text baselined

Completed

Start:

10 Apr 2022

Due:

13 May 2022

Completion:

13 May 2022

Final Change Report Issued

Completed

Start:

13 May 2022

Due:

20 May 2022

Completion:

20 May 2022

Responsible Committee Decision

Completed

Start:

20 May 2022

Due:

07 Jun 2022

Completion:

07 Jun 2022

Authority Determination (Original)

Completed

Start:

07 Jun 2022

Due:

20 Jun 2022

Completion:

17 Jun 2022

Authority Determination (revoked and re-issued)

Completed

Start:

20 Jun 2022

Due:

29 Jun 2022

Completion:

29 Jun 2022
Impacted Consumers
Status
Implementation Date
Status Superseded
EMAR Version 3.0.0_Superseded
Included changes Affected REC Items
R0038 Performance Assurance Report Catalogue Changes as a consequence of REC V3.0
R0041 REC V3.0
  • REC Main Body
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 19 - Market Exit and Supplier of Last Resort
  • Schedule 5 - Change Management
  • Schedule 27 - RMP Lifecycle
  • ASPCoP (since removed)
  • Schedule 28 - Related Metering Points
  • Schedule 29 - Address Management
  • Schedule 9 - Qualification and Maintenance
  • Schedule 2 - REC Transition Schedule
  • Schedule 26 - Switching Service Management
  • Schedule 12 - Data Access
  • Schedule 10 - Charging Methodology
  • Schedule 23 - Registration Services
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Schedule 25 - Central Switching Service
  • Standards Definition Document
  • Data Access Matrix (Electricity)
  • Data Access Matrix (Gas)
  • Data Item Catalogue
  • Market Message Catalogue
R0042 Performance Assurance Board Terms of Reference
  • Performance Assurance Board - Terms of Reference
R0045 Changes to SDEP Messages and Schedule numbering for REC V3.0
  • Market Message Catalogue

Documents

Name Version Last updated Actions
258.97 KB
Version 1.0 - 02 Nov 2026 PDF - 258.97 KB
1.0 02 Nov 2026
257.76 KB
Version 1.0 - 02 Nov 2026 DOCX - 257.76 KB
1.0 02 Nov 2026
219.4 KB
Version 1.0 - 16 Nov 2026 PDF - 219.4 KB
1.0 16 Nov 2026
1.65 MB
Version 1.0 - 02 Nov 2026 PPTX - 1.65 MB
1.0 02 Nov 2026
6.74 MB
Version 1.0 - 02 Nov 2026 PPTX - 6.74 MB
1.0 02 Nov 2026
9.01 MB
Version 1.0 - 02 Nov 2026 PPTX - 9.01 MB
1.0 02 Nov 2026
3.89 MB
Version 1.0 - 02 Nov 2026 PPTX - 3.89 MB
1.0 02 Nov 2026
1.0 02 Nov 2026
16.78 KB
Version 1.0 - 02 Nov 2026 XLSX - 16.78 KB
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I want to be able to successfully switch my Energy Supplier with minimal delay or hassle, so that I can start to receive the service and tariff from my chosen Energy Supplier at the earliest opportunity.
  2. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the obligations, processes and provisions for the new switching arrangements, to enable the successful transition to enduring governance and operational arrangements.
  3. As a REC Party, I want to be clear on the obligations I need to meet and the processes I need to follow post CSS go live, to ensure my organisation is ready for the introduction of the new switching arrangements.
  4. As a REC Service Provider, I want to be clear on the obligations, processes and service standards that I need to meet, to ensure my organisation is ready for the introduction of the new switching arrangements.
Proposed Solution Document
Document title
REC V3.0 Baselined documents
Upload document
R0041 Legal Text.zip
Archive
Off
Document title
REC v3.0 Baselined documents (REC Portal)
Archive
Off
Problem Statement
Changes are required to the REC, to ensure the appropriate obligations, processes and provisions are defined within the REC at CSS go-live, enabling successful transition to enduring governance and operational arrangements developed as part of Ofgem’s Switching Programme.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0041 - Change Proposal Form
Letter from the Authority to the REC Code Manager - REC V3.0 Authority Change Proposal
R0041 - Change Proposal Plan v1.0 (Approved)
R0041 - Initial Assessment Report v2.0 (Approved)
R0041 - Final Change Report v3.0 (Post-Vote)
R0041 Authority Decision
Company Name
Ofgem
Review status
Review required

Revised Implementation Date for R0011

Date of latest update
Type
Change
ID
R0039
Change Category
Change Path
Priority
Urgent
Yes
Latest Update
-
Summary
-
Proposer
patrick.bibby
Change Plan

Party Impact Assessment Issued

Completed

Start:

25 Mar 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Preliminary Change Report Issued

Completed

Start:

08 Apr 2022

Due:

29 Apr 2022

Completion:

29 Apr 2022

Consultation Issued

Completed

Start:

29 Apr 2022

Due:

29 Apr 2022

Completion:

29 Apr 2022

Final Change Report Issued

Completed

Start:

29 Apr 2022

Due:

13 May 2022

Completion:

13 May 2022

Responsible Committee Decision

Completed

Start:

13 May 2022

Due:

17 May 2022

Completion:

17 May 2022
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 01.06.2022_live
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Market Participant, I need the industry Market Message/Data Specification to be implemented by all Parties at the same time so that I am able to validate EMRS invoices and credits without having to request additional supporting data or without my Market Messages failing.
  2. As LCCC I need to delay the implementation of R0011 so that changes to industry Market Message/Data Specification can be implemented by all Parties at the same time so that industry Market Messages don’t fail validation between Parties.
Problem Statement
Following a review of its delivery pipeline, the LCCC has determined it is unable to deploy the changes required in time for the current approved implementation date of 04 November 2022. In order to communicate a revised date and to limit the impacts to industry parties and delivery partners, this change needs to be assessed as a matter of urgency.
R0039 Change Proposal Form
R0039 - Change Proposal Plan v1.0 (Approved)
R0039 Initial Assessment Report v1.0
R0039 Preliminary Change Report v1.0
R0039 - Final Change Report v2.0
Company Name
Low Carbon Contracts Company
Review status
Review required

Prepayment Credit Balance Transfer Process

Date of latest update
Type
Change
ID
R0037
Change Category
Priority
Urgent
No
Latest Update
04/08/2026 - On 04 August 2026, the REC Change Panel approved this Proposal Plan.
Summary
This Change Proposal seeks to develop an agile, efficient, Consumer-centric solution for the transfer of credit balance as part of a smart prepayment Switch.
Proposer
Simon Bevis
Change Plan

Initial Analysis

Completed

Start:

10 Mar 2022

Due:

30 Jun 2022

Completion:

Present updated Change Proposal Plan to Change Panel

Completed

Start:

30 Jun 2022

Due:

19 Jul 2022

Completion:

Solution Development Complete

Completed

Start:

30 Jan 2023

Due:

29 Feb 2024

Completion:

29 Feb 2024

Present Updated Change Proposal Plan to Change Panel

Completed

Start:

19 Jul 2022

Due:

08 Nov 2022

Completion:

Present Updated Plan to Change Panel

Completed

Start:

08 Nov 2022

Due:

17 Jan 2023

Completion:

17 Jan 2023

Service Provider Impact Assessment

Completed

Start:

17 Jan 2023

Due:

30 Jan 2023

Completion:

30 Jan 2023
Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
florentina.monea
Solution Development
Proposed Solution Document
Document title
R0037 - Draft Legal Text v1.0
Upload document
R0037 Party IA Legal Drafts.zip
Archive
Off
Document title
R0037 - Solution Document v2.0
Upload document
R0037 - Solution Document v2.0.pdf
Archive
Off
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
R0037 - CP Form (Downloadable version)
R0037 Consolidated Party IA Responses PUBLIC v1.0
R0037 - Change Proposal Plan V6.0 (Approved) 05.03.24
R0037 - Initial Assessment Report v1.0 (Approved) 06.04.22
R0037 Consolidated RFI Responses PUBLIC v1.0
R0037 Change Report (Proposal Plan) Approved
Company Name
Utilita Energy Limited
Review status
Review required

Market Stabilisation Charge – Administration

Date of latest update
Type
Change
ID
R0035
Change Category
Priority
Urgent
Yes
Latest Update
-
Summary
-
Proposer
Jon Dixon
Change Plan

Party Impact Assessment initiated

Completed

Start:

22 Feb 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Party Impact Assessment completed

Completed

Start:

08 Apr 2022

Due:

29 Apr 2022

Completion:

29 Apr 2022

Preliminary Change Report issued

Completed

Start:

29 Apr 2022

Due:

06 May 2022

Completion:

06 May 2022

Issued to Responsible Committee for review (ex-Committee)

Completed

Start:

06 May 2022

Due:

10 May 2022

Completion:

10 May 2022

Consultation initiated

Completed

Start:

10 May 2022

Due:

13 May 2022

Completion:

13 May 2022

Consultation completed

Completed

Start:

13 May 2022

Due:

01 Jun 2022

Completion:

01 Jun 2022

Final Change Report issued

Completed

Start:

01 Jun 2022

Due:

10 Jun 2022

Completion:

10 Jun 2022

Responsible Committee Decision (ex-Committee)

Completed

Start:

10 Jun 2022

Due:

14 Jun 2022

Completion:

14 Jun 2022

Authority Determination

Completed

Start:

14 Jun 2022

Due:

24 Jun 2022

Completion:

27 Jun 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 2.3.0_Live
Included changes Affected REC Items
R0014 Cable Colour Identification
  • MOCoPA (since removed)
R0019 Consequential REC changes for BSC CP1532
  • Schedule 14 - Metering Operations
R0008 Consequential New and Amended Market Messages for BSC Modification P375
  • Standards Definition Document
  • Data Item Catalogue
  • Market Message Catalogue
R0023 Prepayment Unallocatable Transactions
  • Schedule 11 - Prepayment Arrangements
R0035 Market Stabilisation Charge – Administration
  • Schedule 1 - Interpretations and Definitions

Documents

Name Version Last updated Actions
156.64 KB
Version 1.0 - 02 Nov 2026 PDF - 156.64 KB
1.0 02 Nov 2026
256.28 KB
Version 1.0 - 02 Nov 2026 DOCX - 256.28 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Domestic Consumer, I want to be able to choose my Energy Supplier and a tariff from a range of competitive options, so that I can take advantage of cheaper deals as they become available.
  2. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the MSC obligations, so that the new MSC licence obligations on Energy Suppliers can be effectively discharged by RECCo.
  3. As RECCo, I want the Retail Energy Code to specify my obligations, governance and charging mechanisms, so that I can effectively discharge obligations imposed by the Authority through the Licence Condition modification.
  4. As a Domestic Supplier, I want to understand how RECCo will calculate my credits and liabilities and when they will send my invoices/credit notes, so that I can plan to review my invoices/credit notes prior to the receipt of monies owed or payments I make to RECCo or at an appropriate time for my organisation. As a Domestic Supplier, I want to understand how I could dispute an invoice which I do not believe is accurate, so that I am able to raise a dispute/challenge compliantly
Proposed Solution Document
Document title
Legal Text (tracked changes)
Upload document
R0035 Legal Text - Post Consultation.zip
Archive
Off
Document title
EMAR Change Set
Archive
Off
Problem Statement
Following the publication of Ofgem’s decision on potential short-term interventions to address risks to consumers from market volatility, the Market Stabilisation Charge will be introduced via the modified Standard Licence Condition 24A and introduced into the REC by Change Proposal R0034. A change is needed to the REC to set out the charging and payment mechanism, and to introduce the necessary governance arrangements to allow these MSC payments to be administered by RECCo.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0035 - CP Form (Downloadable version)
Ofgem Decision document - Short Term Interventions
MSC calculation guidance
Gas SLC Modified Decision Notice
Elec SLC Modified Decision Notice
R0035 - High level Solution Overview v1.0
R0035 - Change Proposal Plan v2.0 (Approved)
R0035 - Initial Assessment Report v2.0 (Approved)
R0035 - Consolidated IA responses v1.0
R0035 - Proposed Solution v2.0
R0035 - Preliminary Change Report v2.0 (Approved)
R0035 - Consolidated consultation responses v1.0
R0035 - Final Change Report v2.0 (Post-Vote)
Authority Decision for R0035
Company Name
RECCo
Review status
Review required

Market Stabilisation Charge

Date of latest update
Type
Change
ID
R0034
Change Category
Priority
Urgent
Yes
Latest Update
-
Summary
-
Proposer
Henry Kemp
Change Plan

Preliminary Change Report issued

Completed

Start:

21 Feb 2022

Due:

04 Mar 2022

Completion:

04 Mar 2022

Consultation issued (5 WD)

Completed

Start:

04 Mar 2022

Due:

04 Mar 2022

Completion:

04 Mar 2022

Final Change Report issued

Completed

Start:

04 Mar 2022

Due:

18 Mar 2022

Completion:

18 Mar 2022

Responsible Committee decision (ex-Committee)

Completed

Start:

18 Mar 2022

Due:

23 Mar 2022

Completion:

23 Mar 2022

Authority determination

Completed

Start:

23 Mar 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version REC V2.2.2_SUPERSEDED
Included changes Affected REC Items
R0028 Review of Category 3 documents in the REC Baseline Statement
  • Schedule 1 - Interpretations and Definitions
  • Schedule 5 - Change Management
  • Standards Definition Document
R0034 Market Stabilisation Charge
  • Schedule 1 - Interpretations and Definitions

Documents

Name Version Last updated Actions
170.51 KB
Version 1.0 - 02 Nov 2026 PDF - 170.51 KB
1.0 02 Nov 2026
4.09 MB
Version 1.0 - 02 Nov 2026 PPTX - 4.09 MB
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the MSC obligations, so that the new MSC licence obligations on Energy Suppliers can be effectively discharged by RECCo.
Proposed Solution Document
Document title
Legal Text
Upload document
R0034 legal text - Market Stabilisation Charge v2.0 Post Consultation.zip
Archive
Off
Document title
EMAR Change Set
Archive
Off
Problem Statement
Following the publication of Ofgem’s decision on potential short-term interventions to address risks to consumers from market volatility, the Market Stabilisation Charge will be introduced via the modified Standard Licence Condition 24A. A change is needed to the REC to give effect to the Market Stabilisation Charge from 14 April 2022.
Ofgem Decision Document - Short Term Interventions
R0034 - CP Form (Downloadable version)
R0034 - Change Proposal Plan v1.0 (Approved)
R0034 - Initial Assessment Report v1.0 (Approved)
R0034 - Preliminary Change Report v1.0 (Published for Consultation)
R0034 - Consolidated consultation responses v1.0
R0034 - Final Change Report v2.0 (Post-Vote)
Authority Decision for R0034 - Market Stabilisation Charge
Company Name
-
Review status
Review required

Erroneous Transfer Cancellations

Date of latest update
Type
Change
ID
R0030
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/06/2023 - This change was implemented on 30 June 2023 as part of the June 2023 REC Release
Summary
Erroneous Switches (ESs) are currently being cancelled without a defined process or full audit trail. This Change Proposal seeks to introduce a defined process for Energy Suppliers to be able to cancel an ES in specific scenarios.
Proposer
Lorna Mallon
Change Plan

Solution Development

Completed

Start:

13 Jan 2022

Due:

22 Apr 2022

Completion:

22 Apr 2022

Party Impact Assessment Issued

Completed

Start:

22 Apr 2022

Due:

06 May 2022

Completion:

06 May 2022

Preliminary Change Report Issued

Completed

Start:

06 May 2022

Due:

08 Jul 2022

Completion:

08 Jul 2022

Responsible Committee Review

Completed

Start:

08 Jul 2022

Due:

19 Jul 2022

Completion:

19 Jul 2022

Consultation Issued

Completed

Start:

19 Jul 2022

Due:

05 Aug 2022

Completion:

05 Aug 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 3.5.0_Superseded
Included changes Affected REC Items
R0101 Revision of the Implementation Date and approved solution for R0021
  • MOCoPA (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
R0102 Revision of the approved solution for R0032
  • Data Item Catalogue
  • Market Message Catalogue
R0114 Housekeeping amendments
  • REC Main Body
  • Schedule 1 - Interpretations and Definitions
  • Schedule 2 - REC Transition Schedule
  • Data Access Matrix (Electricity)
  • Data Access Matrix (Gas)
R0015 Remote communication obligations for electricity Advanced Meters
  • Schedule 14 - Metering Operations
R0010 New Meter Types for Auxiliary Proportional Controllers (APCs)
  • Data Item Catalogue
  • Market Message Catalogue
R0011 Reporting of Additional EMR Backing Data to Suppliers
  • Data Item Catalogue
  • Market Message Catalogue
R0021 Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier
  • MOCoPA (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
R0030 Erroneous Transfer Cancellations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Data Item Catalogue
  • Market Message Catalogue
R0066 Inclusion of SMRS Data Items in EES (BSC CP1568 Consequential Change)
R0032 New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS)
  • Data Item Catalogue
  • Market Message Catalogue
R0090 Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
4.64 MB
Version 1.0 - 02 Nov 2026 PPTX - 4.64 MB
1.0 02 Nov 2026
199.58 KB
Version 1.0 - 02 Nov 2026 PDF - 199.58 KB
1.0 02 Nov 2026
124.69 KB
Version 1.0 - 02 Nov 2026 PDF - 124.69 KB
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer I want to receive my bills when expected, from the Supplier of my choice without delays caused by being switched incorrectly and not being resolved in a timely manner. As a Consumer, in the event that my Supplier has exited the market and my supply cannot be returned to my original Supplier, I want the Gaining ET Supplier to have the ability to terminate any ET process that has already been initiated so that I am able to choose my preferred Supplier and switch without delay or penalty.
  2. As a Consumer, if Energy Suppliers need to share my data to resolve a switching issue, I want Suppliers to share my personal data securely so that my data is protected.
  3. As an Energy Supplier, where appropriate, I need to be able to cancel an ET effectively and efficiently, so that I can bill my Consumers accurately and timely. As an Energy Supplier, where appropriate, I need to be able to cancel an ET so that I supply Consumers with whom I have a valid contract.
  4. As The Code Manager I need to be able to identify when an ET has been cancelled so that I have a clear audit trail and can monitor performance effectively.
Proposed Solution Document
Document title
R0030 Pre Consultation Solution Documents
Upload document
R0030 - Consultation Solution Documents (1).zip
Archive
Off
Document title
R0030 - Final Solution Documents
Upload document
Final Solution (1).zip
Archive
Off
Document title
R0030 - EMAR Change Set (Final)
Archive
Off
Problem Statement
Erroneous Transfers are being cancelled by Suppliers, which is currently not permitted under the REC. There is no consistent defined process or audit trail. In the event of a Supplier of Last Resort (SoLR) being appointed, or on a Change of Occupier at a premise, the Gaining Supplier currently has no way to formally cancel an ET after it has been initiated. This can cause Switching and/or Billing delays for Consumers whilst Energy Suppliers attempt to resolve an outstanding or open ET. For Energy Suppliers this can mean they are supplying Consumers with whom they have no Valid Contract, resulting in additional Guaranteed Standards of Performance (GSOP) Payments and increased Consumer dissatisfaction. The Performance Assurance Board (PAB) has no way to identify the difference between the process legitimately closing without resolution, and an Energy Supplier not meeting their obligations in the code to properly resolve an ET. As a result, the PAB are unable to differentiate the performance of Energy Suppliers between those that are closed down legitimately or those being closed inappropriately.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
Erroneous Transfer Cancellations - Change Proposal Form
R0030 - Consolidated Impact Assessment Responses
R0030 Change Proposal Plan v1.0 (Approved)
R0030 - Initial Assessment Report v1.0 (Approved)
R0030 - Preliminary Change Report v2.0 (Approved)
Non Confidential Consultation Responses
R0030 Final Change Report v2.0 (Post-Vote)
Company Name
Scottish Power
Review status
Review required