Related Meter Point RMP status rules
Date of latest update
Type
Change
ID
R0190
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
The drafting in Schedule 28 – Related Metering Points has been updated for Market-wide Half Hourly Settlement (MHHS), allowing related Metering Points to be in a Status of Operational or Created in MPRS, as long as all Related Metering Points are in the same Status. This Change Proposal suggests allowing Secondary Metering Points with a Status of Created to be linked to Primary Metering Points with a Status of Operational, for MHHS migrated Metering Points only.
Change Plan
Presented at Change Issues Group
Completed
Start:
Due:
Completion:
07 Aug 2025Proposal Plan approved by Change Panel
Completed
Start:
Due:
Completion:
19 Aug 2025Change Report (For Consultation) approved by Change Panel
Completed
Start:
Due:
Completion:
18 Nov 2025Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Date
27 February 2026
| Included changes | Affected REC Items | |
|---|---|---|
| R0179 | Proposal for Limiting Queries in EES API Calls (Single Query per API Call) | |
| R0190 | Related Meter Point RMP status rules |
|
| R0198 | Metering Asset Manager (MAM) Communication Method Register | |
| R0242 | Missing Scenario Variant from R0043 |
|
| R0244 | C21 to be introduced into STIRG Document |
|
| R0235A | Missing Scenario Variants in D0179 Alternate Solution | |
| R0256 | MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101 |
|
| R0270 | Clarification of SIP Qualification Requirements |
|
| R0271 | Clarification of ASP, AMI, and EMO Accession Requirements |
|
| R0272 | Enabling transparency of the CRS Provider’s REC service level performance |
|
| R0277 | Data Latency SLA Alignment for Gas Enquiry Service |
|
| R0280 | CSS Certificate Authority audit clarification |
|
| R0283 | Annual Address Management Plan Updates |
|
| R0287 | Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations |
|
| R0293 | Housekeeping February 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0190 - Draft Schedule 28 changes for IA
Upload document
I0190 - Draft Schedule 28 changes V0.2.docx
Archive
Off
Problem Statement
By not allowing Primary Metering Points with a Status of Operational to be linked to Secondary Metering Points with a Status of Created, where the Metering Points have migrated into the MHHS arrangements, full advantage is not being taken of the MHHS functionality of automatically appointing agents to Secondary Metering Points.
Stages Selection
SME
SME Role
Lead Assurance Analyst
SME User
awaghorn@deloitte.co.uk
I0190 - Related Meter Point RMP status rules
I0190 Change Report (Proposal Plan) V1.0
I0190 Consolidated Information Request Responses v1.0
I0190 Consolidated Impact Assessment Responses v1.0
I0190 Extension to Plan V1.0 approved 30.10.25
R0190 Change Report (For Consultation) V1.0 approved 18.11.25
R0190 Consolidated Consultation Responses v1.0
R0190 Change Report (Final Recommendation) V1.0 post vote
Company Name
Code Body/ Administrator
Review status
Review required
Voice of the Consumer
Date of latest update
Type
Issue
ID
I0189
Change Category
Priority
Urgent
No
Latest Update
25/02/2026 - an Issue Closure Report has been published and this Issue moved to resolved.
Summary
There is currently a gap in the understanding of the effectiveness of the retail systems and processes in delivering positive outcomes for Consumers. While Consumer surveys are conducted on certain areas to some aspects of Consumer satisfaction, it may be necessary to expand the evaluation methods used by the Code Manager to gain a more comprehensive understanding.
Change Plan
Working Group 1
Completed
Start:
Due:
Completion:
12 Dec 2024Working Group 2
Completed
Start:
Due:
Completion:
10 Feb 2025Working Group 3
Completed
Start:
Due:
Completion:
18 Mar 2025Working Group 4
Completed
Start:
Due:
Completion:
30 Apr 2025Extension to Plan approved by Change Panel
Completed
Start:
Due:
Completion:
20 May 2025Working Group 5
Completed
Start:
Due:
Completion:
12 Jun 2025Working Group 6
Completed
Start:
Due:
Completion:
28 Jul 2025Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0189 proposed legal text - draft 1
Upload document
I0189 proposed legal text - draft 1.zip
Archive
Off
Problem Statement
RECCo’s mission is to facilitate the efficient and effective running of the retail energy market, including its systems and processes through promoting innovation, competition, and delivering positive Consumer outcomes. However, the Code Manager receives limited feedback directly from Consumers to determine if this mission is being fulfilled.
Stages Selection
Stages Selection
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0189- Voice of the Consumer
I0189 Change Report (Proposal Plan) v1.0 20.11.2024
I0189 Extension to Plan V1.0 Approved 20.05.2025
I0189 Extension to Plan V2.0 Approved 23.09.2025
I0189 Issue Closure Report V1.1
Company Name
Code Administrator
Review status
Review required
Housekeeping Amendments
Date of latest update
Type
Change
ID
R0192
Change Category
Change Path
Priority
Urgent
No
Latest Update
06/08/24 - Change Proposal approved for implementation on 06 September 2024.
Summary
The Code Manager has identified a number of typographical and formatting errors, as well as opportunities to provide clarity, improve consistency and accuracy across the REC Services and products. These changes have been assessed as meeting the criteria to be progressed via a Housekeeping Change Proposal.
Change report - Final Change Report
Change Plan
Housekeeping Report Published
Completed
Start:
25 Jul 2024Due:
26 Jul 2024Completion:
26 Jul 2024Responsible Committee Decision
Completed
Start:
26 Jul 2024Due:
06 Aug 2024Completion:
Status
Implementation Date
06 September 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0177 | Change Smart Meter Installation Consumer Survey Specification survey questions to a REC Category 2 document | |
| R0188 | Changes to Terms of reference following acceptance of R0167 | |
| R0192 | Housekeeping Amendments |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 |
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
API GES Supply Point Switching Technical Specification v1.1
Upload document
API GES Supply Point Switching Technical Specification v1.1.docx
Archive
Off
Document title
Housekeeping legal text changes
Upload document
Sept Housekeeping Log.xlsx
Archive
Off
Problem Statement
This is a Housekeeping Change Proposal subject to the Housekeeping Change Proposal process, rather than the standard change process. The nature of the change is that it makes non-material changes to the REC Products to correct typographical and consistency errors. It also provides an opportunity to introduce necessary clarifications.
Stages Selection
Company Name
-
Review status
Review required
Changes to Terms of reference following acceptance of R0167
Date of latest update
Type
Change
ID
R0188
Change Path
Urgent
No
Latest Update
20/08/2024 - Approved for implementation on 06/09/2024.
Summary
This Housekeeping Change Proposal seeks to update the Terms of Reference of the REC Change Panel and the Performance Assurance Board, following the acceptance of R0167, to reflect Issues.
Status
Implementation Date
06 September 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0177 | Change Smart Meter Installation Consumer Survey Specification survey questions to a REC Category 2 document | |
| R0188 | Changes to Terms of reference following acceptance of R0167 | |
| R0192 | Housekeeping Amendments |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 |
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
REC Change Panel - Terms of Reference
Upload document
REC Change Panel - Terms of Reference.docx
Archive
Off
Document title
REC Performance Assurance Board (PAB) - Terms of Reference
Upload document
REC Performance Assurance Board (PAB) - Terms of Reference.docx
Archive
Off
Problem Statement
This Housekeeping Change Proposal seeks to update the Change Panel and Performance Assurance Board, Terms of Reference to reflect that these Committees consider change Issues as well as Change Proposals.
Stages Selection
R0188 - Change Proposal Form
R0188 - Housekeeping Change Report (Post Approval)
Company Name
Rec Manager
Review status
Review required
Schedule 8 Review and Best Practice Guidance Development
Date of latest update
Type
Issue
ID
I0187
Change Category
Change Path
Priority
Urgent
No
Latest Update
18/11/2026 The REC Change Panel has approved the Update to Plan as part of the Bulk Update presented at their meeting on 17/11/2026
Summary
Schedule 8 - Unbilled Energy Code of Practice has not been reviewed since its development for REC go-live. This Issue seeks to understand if there are any conflicts in the Schedule with best practice and identify any gaps or duplication. Alongside this, a best practice guidance document will be developed which is relevant, complete and aligned to current processes and obligations.
Change Plan
Proposal Plan Approved at Change Panel
Completed
Start:
26 Sep 2024Due:
31 Mar 2027Completion:
21 Jan 2025Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
Schedule 8 - Unbilled Energy Code of Practice has not been reviewed since its development for REC go-live. The Schedule needs to be reviewed to ensure it is up to date, understand if there are any conflicts with best practice and identify any gaps or duplication.
Stages Selection
Stages Selection
Workgroup
Workgroup(s)
I0187 - Change Proposal Form
I0187 - Change Report (Proposal Plan) V1.0 (Approved) 21.01.2025
I0187 - Change Report (Extension to Plan) Approved 17.06.2025
I0187 - Change Report (Extension to Plan) 02.09.2025
I0187 - Change Report (Extension to Plan) 13.01.2025 (Pre-Approval)
I0187 - Change Report (Extension to Plan) V1.0 Approved 25.06.2026
I0187 - Change Report (Extension to Plan) 13.01.2025
I0187 - Change Report (Extension to Plan) V5.0 (Approved)
Company Name
Code Manager
Review status
Review required
Non dual-fuel Gas PSR Consumer
Date of latest update
Type
Issue
ID
I0186
Change Category
Change Path
Priority
Urgent
No
Latest Update
02/09/2025 - the Change Panel approved placing this Issue on hold while the proposer progresses a sandbox trial
Summary
Non dual-fuel Consumers who register upon the PSR, will have their PSR data flow across energy industry data flows to mean that all parties are aware of any PSR Needs Codes, allowing us all to provide equal access to our services and support. This will be achieved via the utilisation of existing processes and systems. Initially a pilot will take place for a minimum of 3 months between participating companies before extending this to the whole industry”.
Change Report - Initial Assessment and Change Plan Report
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
The majority of domestic customers in the UK are what are called in the industry ‘dual-fuel’ - this means that with two types of energy (electricity & gas) a domestic dwelling has a single supplier ie they pay their bill to one organisation. This ‘dual-fuel’ position has supported the industry improvements to Priority Services Register (PSR) data flows by allowing previous divides to be overstepped in terms of data flows between energy types. There is however a problem which this RECC request aims to resolve. That is, where a customer who has both fuel types, also has two suppliers and they want to register upon the PSR. This was always a ‘known’ gap shared with our regulator when the many improvements were implemented across the PSR and considered to be something that would be addressed at a later date. This ‘gap’ means that without the dual-fuel link, currently data flows do not complete across energy types via the supplier data flow triggers.
Stages Selection
Stages Selection
Change Proposal Form - Non dual-fuel Gas PSR Customer
I0186 - Change Report (Proposal Plan) V1.0 (Approved) 18.02.2025
Company Name
British Gas
Review status
Review required
Levelisation Reconciliation Electricity Single-rate/Multi-register Split
Date of latest update
Type
Change
ID
R0182
Change Category
Priority
Urgent
Yes
Latest Update
18/11/24 - The Authority has approved R0182 for Implementation. R0182 will now be targeted for an extraordinary release on 08/12/24.
Summary
This Change Proposal seeks to introduce the necessary governance and charging amendments to existing Payment Method Levelisation (PML) Reconciliation arrangements (introduced in R0147) to allow for multi-register reconciliation. The amendments will allow for an ongoing reconciliation that accounts for split in both single-rate and multi-register Metering Assets. Additionally, it will also allow for a one-off retrospective recalculation for the period dating from the proposed effective implementation date of 01 January 2025 back to the implementation of the original reconciliation mechanism on 01 April 2024.
Change Plan
Party Impact Assessment
Completed
Start:
20 Jun 2024Due:
09 Aug 2024Completion:
09 Aug 2024Consultation
Completed
Start:
09 Aug 2024Due:
20 Sep 2024Completion:
20 Sep 2024Responsible Committee Decision
Completed
Start:
20 Sep 2024Due:
15 Oct 2024Completion:
15 Oct 2024Authority Determination Sent
Completed
Start:
15 Oct 2024Due:
16 Oct 2024Completion:
16 Oct 2024Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- N/A – No identifiable Consumer impact.
- M1 - As a Domestic Supplier, I want my PML Reconciliation payments to be as reflective of my portfolio as possible, by differentiating between single rate and multi register Metering Assets, so that my engagement with the reconciliation is as accurate as possible. M2 - As a Domestic Supplier, I want my PML Reconciliation obligations regarding the retrospective recalculation to be well defined within the REC, so that I am able to engage as efficiently as possible. M3 - As RECCo, I want the PML Reconciliation mechanism to be reflective of REC Parties true costs (based on their single-rate vs multi-register split in their portfolio), so that I am able to deliver the most optimised outcome for PML Reconciliation participants.
Proposed Solution Document
Document title
R0182 Solution & Legal Text 08.10.24
Upload document
R0182 Solution and legal text 08.10.14.zip
Archive
Off
Document title
R0182 Solution & Legal Text 08.10.24
Upload document
R0182 Solution and legal text 08.10.14 (1).zip
Archive
Off
Problem Statement
PML Reconciliation currently does not distinguish between single-rate and multi-register electricity Metering Assets. This represents a discrepancy, as Price Cap methodology currently does make this distinction. As a result, PML Reconciliation calculation methodology must be updated to distinguish between single-rate and multi-register Metering Assets. This will be effective for all reconciliations going forward from the date of implementation, as well as retrospectively from the start of the PML Reconciliation in April 2024, to the date of implementation.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
R0182 - CP Form
Consolidated Consultation Responses
Ofgem Letter on Upcoming PPM Levelisation Single and Multi-Metering Arrangements RFI
R0182 Change Proposal Plan (Approved) V1.0 16.07.24
R0182 Initial Assessment Report V1.0 (Approved) 16.07.24
R0182 Consolidated Impact Assessment Responses V1.0 30.08.24
R0182 Change Report (Post-Vote) V3.0 15.10.24
Authority Decision on REC Modification Proposal R0182
Company Name
RECCo
Review status
Review required
Schedule 14 - Metering Operations Footnote Review
Date of latest update
Type
Change
ID
R0181
Change Category
Change Path
Priority
Urgent
No
Latest Update
23/08/2024 - This change was successfully implemented as part of the August 2024 Extraordinary REC Release on 23 August 2024.
Summary
The footnotes within Schedule 14 - Metering Operations are not in the correct place, are missing or no longer relevant. This Change Proposal looks to correct issues within the footnotes and move them into the legal text to prevent this from happening when future Change Proposals impacting this schedule are implemented.
Change Plan
Change Proposal Plan and Impact Assessment Report issued
Completed
Start:
06 Jun 2024Due:
18 Jun 2024Completion:
18 Jun 2024Preliminary Change Report issued
Completed
Start:
18 Jun 2024Due:
19 Jun 2024Completion:
19 Jun 2024Consultation issued
Completed
Start:
19 Jun 2024Due:
19 Jun 2024Completion:
19 Jun 2024Consultation Close
Completed
Start:
19 Jun 2024Due:
10 Jul 2024Completion:
10 Jul 2024Final Change Report Issued
Completed
Start:
10 Jul 2024Due:
11 Jul 2024Completion:
11 Jul 2024Responsible Committee Decision
Completed
Start:
11 Jul 2024Due:
19 Jul 2024Completion:
19 Jul 2024Appeal Window Closure
Not Started
Start:
19 Jul 2024Due:
02 Aug 2024Completion:
Status
Implementation Date
23 August 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0121 | SDEP Review Improvements (1) - Process Types |
|
| R0146 | Data Specification Update for Refresh Functionality | |
| R0164 | Removing the Enumerations from Communications Method Data Item (J0386) to align with BSC CP 1594 | |
| R0166 | Removal of the Green Deal Panel | |
| R0181 | Schedule 14 - Metering Operations Footnote Review |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Metering Operations v4.1 footnote review legal drafting for PCR
Upload document
Metering Operations v4.1 footnote review - PCR.docx
Archive
Off
Document title
Metering Operations v4.1 footnote review legal drafting for FCR
Upload document
Metering Operations v4.1 footnote review - FCR (2).docx
Archive
Off
Problem Statement
REC parties are unable to ensure their processes and procedures correctly reflect their obligations as the footnotes within Schedule 14 - Metering Operations are not in the correct place, are missing or no longer relevant.
Stages Selection
R0181 Change Proposal Plan (Approved) 18.06.2024
R0181 Initial Assessment Report (Approved) 18.06.2024
R0181 Preliminary Change Report
Consolidated Consultation Responses
R0181 Final Change Report - approved 22.07.24
Company Name
Code Manager
Review status
Review required
Clarity on use of on hold for switching issues, including the obligations of CSS Users
Date of latest update
Type
Change
ID
R0180
Change Category
Change Path
Priority
Urgent
No
Latest Update
06/11/26 - This Change Proposal has been implemented as part of the 6 November 2026 REC Release.
Summary
Many Switching Incidents are on hold waiting for resolution. The Switching Operator puts these tickets on hold, which is an approved business process from the Switching Programme. This is not reflected in the obligations on SDSPs or other REC Service Providers, where there is no on hold concept. Further there are no obligations on CSS Users to respond in a timely basis. This means that the REC obligations do not reflect current practice, and many tickets remain open much longer than necessary.
Change Plan
Change Issue Group
Completed
Start:
03 Jun 2024Due:
01 Aug 2024Completion:
01 Aug 2024Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
06 November 2026
| Included changes | Affected REC Items | |
|---|---|---|
| R0180 | Clarity on use of on hold for switching issues, including the obligations of CSS Users |
|
| R0207 | Import / Export MOA Charging Clarification |
|
| R0253 | Theft - DNO/Networks not providing photos |
|
| R0261 | Addition of Export flag in D0303 flows | |
| R0266 | REC Data Specification Clarifications |
|
| R0317 | Number of Displayed Register Digits Data Item linkage | |
| R0328 | Removal of D0383 & D0384 requirements from Sharing MTDs process |
|
| R0336 | Legal text to support REC Change R0180 |
|
| R0343 | MSC - Amending Statement Production Timescales | |
| R0345 | Housekeeping November 2026 |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 11 Nov 2026 | ||
| 1.0 | 11 Nov 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Option 1
Upload document
Option 1.zip
Archive
Off
Document title
Solution Development Report
Upload document
Solution Development Report.pdf
Archive
Off
Document title
Option 2
Upload document
Option 2.zip
Archive
Off
Document title
Option 3
Upload document
Option 3.zip
Archive
Off
Problem Statement
A lack of obligations is causing issues with open tickets relating to missing messages. Tickets placed on hold also require significant additional work for the Switching Operator, which could either be released as a cost saving or it could result in time freed up for improvement activities.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
Issue Form
Change Report - Proposal Plan V1.0
I0180 Extension to Plan V1.0 approved 09.07.25
I0180 Consolidated Party Impact Assessment Responses v1.0
I0180 Update to Plan V1.0 approved 10.12.25
R0180 Change Report (For Consultation) V1.0
R0180 Consolidated consultation responses V1.0
R0180 Change Report (Final Recommendation) V1.0 approved 25.03.26
Company Name
REC Code Manager
Review status
Review required
Proposal for Limiting Queries in EES API Calls (Single Query per API Call)
Date of latest update
Type
Change
ID
R0179
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
This issue has been raised proposing to establish a limit on the number of queries permitted within a single Application Programming Interface (API) call. As there is potential for performance degradation and system instability that can occur when a large number of queries are made in a single API call to the Electricity Enquiry Services (EES) API. The aim would be to prevent overwhelming the system and ensure consistent response times and reliability. Therefore, this proposes implementing a limit of 1000 queries per single API call.
Change Plan
Request for Information
Completed
Start:
03 Jun 2024Due:
05 Jul 2024Completion:
05 Jul 2024Change Issue Group
Completed
Start:
05 Jul 2024Due:
01 Aug 2024Completion:
01 Aug 2024Impacted REC Parties and Market Participants
Status
Implementation Date
27 February 2026
| Included changes | Affected REC Items | |
|---|---|---|
| R0179 | Proposal for Limiting Queries in EES API Calls (Single Query per API Call) | |
| R0190 | Related Meter Point RMP status rules |
|
| R0198 | Metering Asset Manager (MAM) Communication Method Register | |
| R0242 | Missing Scenario Variant from R0043 |
|
| R0244 | C21 to be introduced into STIRG Document |
|
| R0235A | Missing Scenario Variants in D0179 Alternate Solution | |
| R0256 | MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101 |
|
| R0270 | Clarification of SIP Qualification Requirements |
|
| R0271 | Clarification of ASP, AMI, and EMO Accession Requirements |
|
| R0272 | Enabling transparency of the CRS Provider’s REC service level performance |
|
| R0277 | Data Latency SLA Alignment for Gas Enquiry Service |
|
| R0280 | CSS Certificate Authority audit clarification |
|
| R0283 | Annual Address Management Plan Updates |
|
| R0287 | Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations |
|
| R0293 | Housekeeping February 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Request For Information (RFI)
Archive
Off
Problem Statement
The absence of a limit on the number of queries (batch processing) within a single API call could cause performance issues and system instability. As a result, system responsiveness may degrade when a large number of queries are made in a single call, impacting user experience and hindering the ability of the EES API to consistently meet user demands.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
Issue Form
EES API Interface Specification REDLINE DRAFT for R0179
R0179 - Change Report - Final Recommendation Approved
R0179 Change Report (Consultation)
R0179 Consolidated consultation responses (non- confidential)
Re-baseline Change Plan 15.07.25
Consolidated IA responses (non-confidential)
I0179 Change Report (Impact Assessment)
Service Provider - Impacts Data
I0179 - Consolidated RFI Responses
Change Report (Proposal Plan)
Consultation on implementation date response
Change Report - Final Recommendation (new implementation date)
Company Name
RECCo
Review status
Review required