MHHS D0300 Issue

Date of latest update
Type
Issue
ID
I0295
Urgent
No
Latest Update
09/04/2026 - The Proposer has withdrawn the Issue following conversations with the Code Manager. The Proposer concluded that it would be more appropriate for MHHS migration to complete before undertaking a comprehensive review of the overall process.
Summary
D0300s for MHHS do not include register reads. Block 60C says: “For MHHS Metering Points, this Data Item should be populated with details of the cumulative register for Smart Metering Assets”. If a smart meter is non-comms, and we receive a cumulative only in the D0300, but are billing to register reads, we don't know whether the disputed read is valid based on our read history. Furthermore, a cumulative will not always equal the sum of the register reads for smart meters.
Proposer
David Morley
Status
Implementation Status
Date Raised
Lead Analyst
florentina.monea
Solution Development
Stages Selection
Stages Selection
I0295 Submission Form
Company Name
OVO
Review status
Review required

Implementation of IF-051 Data Refresh in EES for BSC CP1607

Date of latest update
Type
Change
ID
R0294
Change Category
Change Path
Priority
Urgent
No
Latest Update
28/10/2026 On 28 October 2026, the Technical Expert Panel voted, in line with the Code Manager’s recommendation, to approve the extension to plan for R0294. The Code Manager is working with the BSC on stakeholder workshops on a complete end-to-end solution, including the required market message specification, governance arrangements and operational processes. Stakeholder workshops will be held to run through the new ‘Data Refresh’ message, discuss the proposed change and gather stakeholder views on the full solution. The Code Manager will be attending these workshops to provide input on the new BSC CP, as well as impacts on the REC and REC services (primarily the Electricity Enquiry Services).
Summary
The IF-051 provides a refresh of data from Supplier Meter Registration Service (SMRS) to the Electricity Enquiry Service (EES) (REC) and Market Data Service (BSC). Currently the REC does not hold any detail regarding the DIP Market Messages that the EES is required to receive and process. Due to the nature of the IF-051, the EES Provider obligations need to be clear to ensure the interface can be received and processed appropriately.
Proposer
Harriet Truss
Change Plan

Proposal Plan approved at REC Change Panel

Completed

Start:

Due:

16 Dec 2025

Completion:

16 Dec 2025

Consultation published

Completed

Start:

Due:

12 Feb 2026

Completion:

12 Feb 2026

Consultation closed

Completed

Start:

Due:

27 Feb 2026

Completion:

27 Feb 2026

Proposal Plan update approved by Technical Expert Panel

Completed

Start:

Due:

25 Mar 2026

Completion:

25 Mar 2026

Proposal Plan update approved by Technical Expert Panel

Completed

Start:

Due:

Completion:

28 Oct 2026
Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
EES Service Definition v4.1 - redlined for IF-051
Upload document
EES Service Definition v4.1 - redlined for IF-051.pdf
Archive
Off
Document title
366_05B CP1607 IF-0XX_Proposed Data Refresh Flow v0.1
Upload document
366_05B CP1607 IF-0XX_Proposed Data Refresh Flow v0.1.pdf
Archive
Off
Document title
R0294 EES Service Definition REDLINED for Consultation
Upload document
R0294 EES Service Definition REDLINED for Consultation.pdf
Archive
Off
Document title
CP1629 Attachment C IF-051 Refresh Flow v2.0 REDLINED
Upload document
Attachment C IF-051 Refresh Flow v2.0 REDLINED.pdf
Archive
Off
Document title
R0294 Solution Development Report v1.0
Upload document
R0294 Solution Development Report v1.0.pdf
Archive
Off
Problem Statement
BSC CP 1607 will implement a new DIP Market Message, the IF-051 ‘Data Refresh’ on 26 March 2026. EES will be a recipient of that change. If EES is not able to receive and process instances of the IF-051, data in EES will be misaligned with other industry systems (SMRS, DIP and MDS) meaning that it will not maintain its role as the accurate reference point for industry participants. This could lead to potential disruption of industry processes.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
R0294 Submission Form
R0294 Change Report (Proposal Plan) Approved v1.1 16.12.2025
R0294 Change Report (Consultation) Approved v1.0 04.02.2026
R0294 Consolidated Consultation Responses v1.0
R0294 - Change Proposal Re-Plan v1.0 (Approved) 25.03.2026
R0294 Change Report (Update to Plan) v1.0 Approved 07.07.26
R0294 Change Report (Update to Plan) v2.0 Approved 28.10.26
Company Name
REC Code Manager
Review status
Review required

Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations (Alternate)

Date of latest update
Type
Change
ID
R0287A
Change Category
Priority
Urgent
No
Latest Update
20/02/2026 The Authority has published their decision to reject R0287A and approve the R0287, in line with the Code Manager and the Change Panel's recommendation. The Authority's decision has been published below.
Summary
Inconsistent interpretations of the Annulment definition in Schedule 23 are leading to disputes between suppliers. We are, therefore, seeking to further clarify the use of annulments to ensure that the customer is placed firmly at the heart of this process.
Proposer
Komal Brown
Change Plan

Proposal Plan approved at Change Panel

Completed

Start:

Due:

Completion:

02 Dec 2025
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0287A Draft Legal Changes - For Consultation
Upload document
I0287A (Alternate) Proposed Solution For Consultation.docx
Archive
Off
Problem Statement
The current wording of the Annulment definition in the REC Schedule 23 – Registration Services is insufficiently aligned with the obligations set out in Ofgem’s Electricity Supply Standard Licence Conditions (SLC). This has led to inconsistent interpretations of the usage of the Annulment process.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
R0287A submission form
R0287 and R0287A Change Report (Proposal Plan and Consultation) v1.0 approved 02.12.25
R0287 and R0287A Consolidated Consultation Responses PUBLIC
R0287 and R0287A Change Report (Final Recommendation) Post Vote 20.01.2026 v1.0
Ofgem decision to reject R0287A
Company Name
ScottishPower
Review status
Review required

Rationalisation of reports produced by CSS - CRS improvements project

Date of latest update
Type
Issue
ID
I0289
Change Path
Urgent
No
Latest Update
15/01/2026 The Code Manager has rejected this Change Proposal as it does not impact any REC products. Further feedback, and any information on the CRS Improvements project as a whole, can be provided via the usual channels, including the Switching Operator Forum, your OAM teams and the Change Management team.
Summary
Ensuring the reports generated from CSS (Into ServiceNow) are being utilised and where they are not utilised reducing cadence or potentially removing completely.
Proposer
Leo Brown
Status
Implementation Status
Date Raised
Fuel
Solution Development
Proposed Solution Document
Document title
I0289 submission form
Upload document
I0289 submission form.pdf
Archive
Off
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Issue Proposal Form
I0289 Information Request Consolidated Responses
Company Name
DCC
Review status
Review required

Schedule 14 review – DNOs do not remove Metering Assets

Date of latest update
Type
Issue
ID
I0288
Urgent
No
Latest Update
18/12/2025 - the Code Manager has withdrawn this Issue following discussions at the Metering Expert Panel on 10 December 2025, where Panel members advised there were a small number of niche scenarios where a DNO may remove a Metering Asset (e.g. emergencies). On this basis, the Code Manager believes it appropriate this remains within Schedule 14. If you wish to adopt this REC Issue, please contact the Code Manager by COB 07 January 2026.
Summary
As part of the REC Code drafting for MHHS, an issue has been identified with the current drafting of Metering Operations Schedule. This sets out the processes for the removal of a meter (and metering assets) by the DNOs. DNOs would only remove CTs and VTs and not the actual meters. The text should be reviewed and revised to reflect what happens and what activity DNOs complete.
Proposer
Caroline Freimuller
Change Plan

Change Proposal approved

Completed

Start:

28 Oct 2025

Due:

24 Jan 2026

Completion:

24 Jan 2026

Test

In Progress

Start:

24 Jan 2026

Due:

24 Mar 2026

Completion:

Status
Implementation Status
Date Raised
Solution Development
Stages Selection
Stages Selection
I0288 submission form
Company Name
REC Code Manager
Review status
Review required

Organisations with multiple role types EES and SDEP access

Date of latest update
Type
Issue
ID
I0285
Change Category
Change Path
Priority
Urgent
No
Latest Update
On 22 October 2026, the Code Manager published the I0285 Closure Report. Following a review of the responses to the Party impact assessment, the Code Manager has determined that this REC Issu can be moved to Resolved as there has been a lack of Parties indicating they would use the proposed solution under I0285. The enduring solution of one individual assigned to two company groups to use two separate email addresses for each company group will be sustained. RECCo will consider the requirement for a single login across multiple roles as part of the Enquiry Services Evolution project development.
Summary
It is currently not possible for organisations with multiple role types to have the same person be able to access all assigned role types within the Secure Data Exchange Portal (SDEP) without having a unique email address for each role type.
Proposer
Caroline Freimuller
Change Plan

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

04 Nov 2025

Discussed at Technical Expert Panel

Completed

Start:

Due:

Completion:

17 Dec 2025

Discussed at Technical Expert Panel

Completed

Start:

Due:

Completion:

28 Jan 2026

Extension to Plan approved by Technical Expert Panel

Completed

Start:

Due:

Completion:

25 Feb 2026

Discussed at Change Issues Group

Completed

Start:

Due:

Completion:

06 Aug 2026
Impacted Consumers
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Zip file with I0285 legal text
Upload document
Legal text for Party IA (2).zip
Archive
Off
Document title
I0285 Solution Development Report V1.0
Upload document
I0285 Solution Development Report V1.0.pdf
Archive
Off
Problem Statement
Organisations with more than one role type are required to have unique email addresses for staff who require access to multiple role types, leading to inefficiencies, unnecessary administrative burdens and a poor user experience.
SME
SME Role
Lead Technical Analyst
I0285 submission form
I0285 Change Report (Proposal Plan) V1.0 approved 04.11.25
I0285 Extension to Plan V1.0 approved 25.02.26
I0285 Extension to Plan V2.0 approved 24.06.26
I0285 Consolidated Impact Assessment Responses v1.0
I0285_Closure Report
Company Name
REC Code Manager
Review status
Review required

Return of Legacy Meters

Date of latest update
Type
Issue
ID
I0282
Change Path
Priority
Urgent
No
Latest Update
08/04/2026 - The Closure Report was presented to the REC Metering Expert Panel at their meeting on 08 April 2026. The Issue has now been classed as resolved.
Summary
The issue identified is that current arrangements require or assume that legacy Meter Asset Providers (MAPs) take back old, non Smart Meters once they are removed from Consumers’ Premises, even though many of these meters are obsolete, cannot be reused, and ultimately require disposal. This has resulted in large volumes of legacy meters being transported across the country between storage providers and legacy MAPs, creating unnecessary cost, administrative burden, and environmental impact. Storage providers are issuing extensive lists of Meter Serial Numbers (MSN) to try to establish meter ownership, and legacy MAPs must manually verify these details. This process has been made more difficult by historical changes in company names and ownership structures. Once ownership is confirmed, the meters are frequently transported to the legacy MAP only for them to arrange disposal, which provides no net value and simply adds further transportation and handling costs.
Proposer
Bryan Heap
Change Report - Initial Assessment and Change Plan Report
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
The process for handling removed legacy non Smart Meters is inefficient and environmentally costly, with unclear ownership, unnecessary transport, and no established recycling route. A consistent, sustainable disposal solution is needed to reduce waste, simplify operations, and clarify the management of any scrap value.
I0282 submission form
I0282_Closure Report_v1.0 (26 March 2026)
Company Name
SP Electricity North West
Review status
Review required

Extending R0067 Refresh Functionality

Date of latest update
Type
Issue
ID
I0281
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/09/2026 - The update to plan has been approved by the Technical Expert Panel on 30 September 2026.
Summary
CSS Market Messages sent by the Central Switching Service (CSS) to Switching Data Service Providers (SDSPs) are either not being received, being received after Gate Closure, or are being received out of the order that they were originally sent in. This Issue originally aimed to extend the Refresh functionality, implemented for the Gas Retail Data Agent (GRDA).to the Electricity Retail Data Agent (ERDA). Following solution development for I0281, it was agreed that the Refresh functionality would be made available for all Market Participants in receipt of the in-scope messages.
Proposer
Finn Deacon
Change Report - Initial Assessment and Change Plan Report
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
Francine Peyroux-Sissoko
Solution Development
Proposed Solution Document
Document title
I0281_Proposed_Legal text_PIA_V1.0.
Upload document
I0281_Proposed_Legal text_PIA_V1.0.zip
Archive
Off
Problem Statement
CSS messages are not received by the SDSPs in the order in which they were originally sent, or after Gate Closure, so it can be difficult to detect and often requires significant manual effort to resolve. This issue can directly impact Consumer switching experiences, causing disruption and possible delays in a switch.
Workgroup
Workgroup(s)
I0281_Change Report (Update to Plan) v1.0 (Pre-approval)
I0281_Change Report (Update to Plan) v2.0 Approved
I0281_Change Report (Update to Plan) v2.0 (Pre-approval)
I0281_Change Report (Update to Plan) v1.0 Approved 20.05.2026
I0281_Change Report (Proposal Plan) v1.0_Approved 04.11.2025
Company Name
REC Technical Services
Review status
Review required

Establishing the Safe Isolation Provider (SIP) as a Standalone REC Party

Date of latest update
Type
Issue
ID
I0278
Change Category
Change Path
Priority
Urgent
No
Latest Update
21/07/2026 - An Update to Plan has been approved by the Change Panel on 21 July 2026.
Summary
This proposal recommends the formal recognition of the Safe Isolation Provider (SIP) as a standalone Party under the Retail Energy Code (REC). This aligns with the direction set out in Ofgem’s recently published Strategic Direction Statement (SDS), which explicitly calls for the establishment of SIPs as a standalone Party role. The aim is to address the growing scale of unregulated SIP activity, mitigate associated consumer safety risks, and ensure the metering industry is equipped to support the UK’s Net Zero ambitions. By enabling easier access to certified SIPs, this change will enhance consumer protection, accelerate low-carbon technology deployment, and improve operational efficiency across the energy sector.
Proposer
Rebecca Griffiths
Change Report - Initial Assessment and Change Plan Report
Impacted Consumers
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Problem Statement
The current SIP framework poses several risks: - Consumers, MEMs and unaccredited practitioners’ safety. Unaccredited and unregulated isolation work increases the risk of unsafe installations and potential harm to Consumers. NAPIT highlighted to RECCo and DESNZ that 17 and 13 unregulated practitioners respectively died in 2023 and in 2024 due to unsafe isolation. With the right Party undertaking this work, there would also be less safety issues for the Consumer at their premises; - Inequity. Independent Installers face longer wait times compared to supplier-led installations, creating a two-tier system; - Low competitive market. Currently prospective Parties can be put off from applying to be a SIP as it appears they would need full MEM Accreditation which is often too far outside their current business operating model. Providing SIPs with their own pathway and requirements could result in more Parties becoming SIPs and therefore giving Consumers more choice in their provider; and - Decarbonisation delays. The inability to scale SIP capacity undermines the timely deployment of LZCTs, threatening Net Zero targets.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0278 submission form
I0278 Change Report (Proposal Plan) V1.0 (Pre-Approval) 09.10.2025
I0278_Change Report (Extension to Plan) v1.0 (Pre-Approval) 12.01.2026
I0278_Change Report (Extension to Plan) v2.0 (Pre-Approval) 13.07.2026
I0278_Change Report (Extension to Plan) v2.1 (Approved) 21.07.26
I0278_Consolidated Information Request DNO Responses
I0278_Consolidated Information Request MEM-SIP Responses PUBLIC
I0278_Consolidated Information Request RPA Responses
Company Name
RECCo
Review status
Review required

MHHS Related Metering Points across Market Segments

Date of latest update
Type
Issue
ID
I0275
Change Category
Change Path
Priority
Urgent
No
Latest Update
17/09/2026 - The Code Manager has published a guidance document that acts as the solution for this Issue. A Closure Report has now been published, and this Issue has now been classed as resolved.
Summary
It has been identified by the MHHS Data Cleanse Working Group (DCWG) that around 9,000 existing Metering Point Relationships include Metering Points that would migrate into different Market-wide Half Hourly Settlement (MHHS) Market Segments. The majority of these are where one Metering Point has a Traditional meter installed (Smart Segment) and a Related Metering Point has an Advanced meter (Advanced Segment). This situation is currently valid but in MHHS would cause two problems. - SMRS would not be able to align the agent appointments, leaving secondary MPANs without agents and MHHS Migrations unable to fully complete.
Proposer
jonny.moore_42
Impacted Consumers
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0275 - Related Metering Points Guidance Document_V1.0.pdf
Upload document
I0275 - Related Metering Points Guidance Document_V1.0 (1).pdf
Archive
Off
Document title
I0275 - Closure Report_V1.0
Upload document
I0275_Closure Report_v1.0 (2).pdf
Archive
Off
Problem Statement
Without considering this Issue, there will be a risk to the MHHS migration. Indeed, a Metering Point installed which does not match its Related Metering Point (for example a Relationship between a Traditional meter with an Advanced Meter) will not be able to fully migrate to MHHS arrangements.
I0275 submission form
Company Name
RECCo
Review status
Review required