Catering for Registration Events where the Incumbent Supplier deactivates prior to a Switch becoming effective

Date of latest update
Type
Change
ID
R0153
Change Category
Change Path
Priority
Urgent
No
Latest Update
04/06/24 - This change has been withdrawn by the proposer and is being incorporated as part of R0178 - Improvements to CSS Business Process Logic. 03/05/2024 - An investigation was held into the requirements of this change and into other issues identified with the CSS Business Process and Logic. Landmark have provided data relating to the number of incidents for three different scenarios which had been identified. A discussion as held between the Code Manager, DCC and Landmark, and agreed that they will look to combine all identified issues into a new REC Change Proposal.
Summary
This change looks to resolve the issue for Registration Events where the incumbent Supplier deactivates prior to a Switch becoming effective. In some instances, the incumbent Supplier is withdrawing prior to the ‘Supply Effective from Date’ which causes the accepted Switch to fail at Gate Closure (17:00hrs) . An effective solution is to allow the consumer to Switch with the original effective date. There are a number of solution options to enable this to happen.
Proposer
David Addison
Impacted Consumers
Impacted REC Services
Status
Implementation Status
Date Raised
Fuel
Lead Analyst
James Hardy
Solution Development
Problem Statement
In some instances, the incumbent Supplier is withdrawing prior to the ‘Supply Effective from Date’ which causes the accepted Switch to fail at Gate Closure (17:00hrs).
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
caroline.milner@capgemini.com
Catering for Registration of Events CP Form 24.11.2023
Company Name
Xoserve
Review status
Review required

Implementation of Online Certificate Standard Protocol (OCSP) in addition to Certificate Revocation List (CRL).

Date of latest update
Type
Change
ID
R0151
Change Category
Change Path
Priority
Urgent
No
Latest Update
14/05/2024 - At the request of the proposer, this Change Proposal has now been withdrawn. The rationale for withdrawing the proposal was that the benefits afforded by this change will not be fully realised until 2026 (renew of digital certificates), and the risk profile around revoked certificates remains unchanged during this period. DCC recommend this change is revisited in 12 months, to allow sufficient time for review and resubmission ahead of any certificate renewal activities.
Summary
This Change seeks to make improvements to the Microsoft Azure Application Gateway module. A defect has been identified which requires the implementation of a manual/ customer workaround when checking the Certificate Revocation Lists (CRLs) systems within the Central Switching Service (CSS) to ensure certificates are revoked. This change seeks to remove the need to complete a manual workaround and implement a real-time certification validation capability.
Proposer
Stuart Pitcher
Change Plan

Solution Analysis and Development

Completed

Start:

30 Oct 2023

Due:

26 Jan 2024

Completion:

26 Jan 2024
Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
James Hardy
Solution Development
Proposed solution summary
  1. The proposed solution is to roll out support for Online Certificate Standard Protocol (OCSP) in addition to Certificate Revocation List (CRL). The scope of the change will be: - Implementation of a central OCSP server and the update of the associated PKI processes to manage the Certificate Revocation. This will cover the TLS and JWS Certificate Revocation. - CSS implementation of Application Gateway will be reconfigured to include the OCSP functionality and server. - CSS change to implement the OCSP checking for the JWS certificates. - All new certificates that are issued will include the detail of the OCSP Server, as part of the migration approach all new certificates will have this information embedded. - All parties connecting to CSS have the relevant information for them to exploit the advanced features that OCSP introduces. The CRL checking functionality will be maintained so this change is an optional upgrade for any Systems that operate using Switching Key Infrastructure.
Problem Statement
There is currently a Microsoft Azure Application Gateway module defect against the checking of Certificate Revocation Lists (CRLs), with Microsoft stating that the CRL related defect will not be fixed. Consequently, any system within the CSS ecosystem, systems that use Switching Key Infrastructure (SWIKI), that have incorporated the Azure Application Gateway module to manage the TLS connection will have been required to implement a manual/custom workaround to ensure that certificates that are revoked are not allowed to establish a connection.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
caroline.milner@capgemini.com
R0151 - Implementation of OCSP in addition to CRL
R0151 - Initial Assessment Report V2.0 (Approved) 06.02.2024
Company Name
Smart DCC
Review status
Review required

Introduction of classification-based access model

Date of latest update
Type
Change
ID
R0148
Change Category
Change Path
Priority
Urgent
No
Latest Update
21/11/2025 - Following a review of the impact assessments received for the technical solution required to deliver R0148, taking into account the timelines, costs and the pending decision on the Evolution of the Enquiry Services, a positive business case cannot be demonstrated at this time. RECCo have, therefore, made the decision to withdraw R0148 and look at how the technical objectives can be met through the Evolution of the Enquiry Services. The adoption window has closed.
Summary
Currently Enquiry Services Data is only available to users whose roles and purposes for access are detailed within the Data Access Matrix (DAM). RECCo has undertaken a project to look at REC controlled data sources and created a Metadata Catalogue based on a Data Classification Model. This details the data items along with descriptions, identification of the associated data, roles, responsibilities, and classification. The output of this work will be utilised to improve access to Enquiry Services Data by making certain data items (defined as Always Open) easily available to everyone and simplifying the approval process for data items which can be made available if certain conditions have been met.
Proposer
Tracy Hardy
Change Plan

Service Provider Impact Assessment

In Progress

Start:

13 Oct 2023

Due:

31 Dec 2024

Completion:

Party Impact Assessment

Not Started

Start:

31 Dec 2024

Due:

31 Dec 2024

Completion:

Consultation

Not Started

Start:

31 Dec 2024

Due:

28 Feb 2025

Completion:

Responsible Committee Decision

Not Started

Start:

28 Feb 2025

Due:

04 Mar 2025

Completion:

Impacted Consumers
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I want Market Participants to have appropriate data access so that I can benefit from improved product and service offerings.
  2. As a Market Participant, I want the processes that grant data access to be simplified and adaptable so that valid data use cases are addressed quickly.
Proposed Solution Document
Document title
Wiki Article - R0148 and the Metadata Catalogue
Archive
Off
Problem Statement
Currently the REC has a focus on role-based access to data items within the Enquiry Services as detailed in Schedule 12 – Data Access. However, a system and process where data items are released by virtue of the data item is needed.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
caroline.milner@capgemini.com
R0148 - Open Data Change Proposal Form V1.0.docx
Rebaseline of Change Proposal Plan v2.0
Metadata Catalogue V2.2 Published - EES GES Sources.
R0148 - Change Proposal Plan V1.0 (Approved)
R0148 - Initial Assessment Report v1.0 (Approved)
R0148 - Rebaseline of Change Proposal Plan (20.09.2024)
Company Name
Code Manager
Review status
Review required

Service Termination Issue Reporting (Change to Category 2 document)

Date of latest update
Type
Change
ID
R0145
Change Category
Change Path
Priority
Urgent
Yes
Latest Update
22/02/2024 At the Metering Expert Panel meeting on 14 February 2024, the Panel voted to reject the Code Manager's recommendation to approve R0145 - Service Termination Issue Reporting (Change to Category 2 Document). Under REC Schedule 5 - Change Management, when a Responsible Committee rejects the recommendation of the Code Manager with respect to a Self-Governance Change Proposal, the Change Proposal is automatically referred to Ofgem (as the Authority) for its determination, unless the Code Manager changes its recommendation based on the reasons provided by the relevant sub committee. Following consideration of the decision made by the Metering Expert Panel and the reasons for its rejection, the Code Manager has decided to amend its recommendation, and is now recommending the rejection of R0145. The Code Manager maintains that the business case for R0145 was made, and the solution does address the identified problem statement, and this was reflected in the comments of a majority of group members as the R0145 was progressed and during the vote. However, it is clear that some RECMEP members are supportive of a change to the governance of this document that would remove it from the REC completely. Although this was outside of the scope of the original change, it was a consistent theme throughout the development of R0145. Consequently, R0145 has been rejected for implementation and the decision will not be referred to Ofgem.
Summary
This Change Proposal updates the Categorisation of this REC document to a Category 2 document. It is currently classified as a Category 3 document – which are used for guidance documents that have no material impacts on REC Parties. The REC obligates compliance with this document through Schedule 14 – Meter Operations and the Consolidated Metering Codes of Practice
Proposer
Colette Baldwin
Change Plan

Impact Assessment

Completed

Start:

21 Aug 2023

Due:

25 Aug 2023

Completion:

25 Aug 2023

Preliminary Change Report Issued

Completed

Start:

25 Aug 2023

Due:

08 Sep 2023

Completion:

08 Sep 2023

Preliminary Change Report Review by Metering Expert Panel (ex-committee)

Completed

Start:

08 Sep 2023

Due:

15 Sep 2023

Completion:

15 Sep 2023

Consultation - 15 Working Days

Completed

Start:

15 Sep 2023

Due:

22 Sep 2023

Completion:

13 Oct 2023

Final Change Report Issued

Completed

Start:

08 Dec 2023

Due:

22 Dec 2023

Completion:

06 Feb 2024

Metering Export Panel Decision

Completed

Start:

10 Nov 2023

Due:

24 Nov 2023

Completion:

24 Nov 2023

Second Preliminary Change Report

Completed

Start:

22 Sep 2023

Due:

10 Nov 2023

Completion:

10 Nov 2023

Consultation on 2nd Preliminary Change Report

Completed

Start:

24 Nov 2023

Due:

27 Nov 2023

Completion:

24 Nov 2023

Preliminary Change Report Consultation Closes

Completed

Start:

27 Nov 2023

Due:

08 Dec 2023

Completion:

08 Dec 2023

Final Decision of Metering Expert Panel

Not Started

Start:

22 Dec 2023

Due:

12 Jan 2024

Completion:

Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
colette.baldwin
Solution Development
Proposed solution summary
  1. As a DNO I want to ensure that the MEMs who work on my network have the requisite skills and experience and that they will follow the instructions relating to reporting incidents of danger, damage, or interference with the DNO Equipment, as set out in the Service Termination Issue Reporting document.
  2. As a Supplier I want any MEM I employ to have clear instructions on how to report incidents of danger, damage, or interference with the DNO Equipment.
  3. As a MEM I want information on what actions I need to take where there is danger, damage, or interference with the DNO Equipment at site, so that issues can be safely addressed in the appropriate timescales.
  4. As the Code Manager, I want clarity on the governance and for change processes of the document to be appropriate, for the subject matter and relevant affected parties.
Problem Statement
Compliance with the CoMCoP and the Metering Operations Schedule includes obligations on the MEMs to report incidents of danger, damage, or interference with the DNO Equipment in accordance with the requirements set out in the document. Failure to comply with these requirements will leave the MEM subject to permission to work on the DNO’s equipment being revoked, which will have consequences on their ability to work as a REC MEM more widely.
Stages Selection
R0145 - Downloadable Change Proposal Form
R0145 - Service Termination Issue Reporting CPP v1.0 Approved 05.09.2023
R0145 IAR - Service Termination Issue Reporting Approved by Change Panel 05.09.2023
08.09.2023 - R0145 REC Service Termination Issue Reporting v1.0 Draft Legal Text for PCR
R0145 - Preliminary Change Report (Approved by Panel) 15.09.23
R0145 - Change Proposal Re-Plan v2.0 20/11/2023
R0145 - Consolidated Consultation Responses v1.1 Public
R0145 FCR -STIR Document (Change to Cat 2) (Post-Vote) V1.0 14.02.2024
Company Name
Gemserv
Review status
Review required

Allowing different Metering Equipment Managers (MEMs) to be appointed to Import and Export Metering Points

Date of latest update
Type
Change
ID
R0144
Change Category
Priority
Urgent
No
Latest Update
17/02/2025 - R0144 has been withdrawn by the Proposer, alongside it's joint BSC Change P459, as they cannot be progressed prior to MHHS. The Proposer will look to re-raise both changes in the future. The adoption window for this withdrawal has closed.
Summary
The Export Supplier needs to be able to appoint different MEMs to that of the Import Supplier
Proposer
Kit Dixon
Impacted Consumers
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I want a competitive Export market so I can get the best rates for the energy I generate. I want clear metering equipment ownership so I can be confident my meter is functional and safe. I want accurate billing from my Export Supplier.
  2. As an Export Supplier, I want to be able to appoint the MEM that ties in with my commercial strategy.
  3. As a MEM, I want clear guidance on the responsibilities I have for any metering equipment I am appointed to.
Problem Statement
Export Suppliers may become non-compliant with industry regulations if they are unable to appoint the same MEM as the Import Supplier, for example when the Consumer switches Import Supplier or when the Import Supplier changes the appointed MEM.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
Change Proposal Form
R0144 Change Proposal Plan Withdrawal v1.0 (Pre Approval)
R0144 Change Proposal Plan v1.0 (16.04.2024) Approved
R0144 Initial Assessment Report v1.0 (16.04.2024) Approved
Company Name
REC Code Manager
Review status
Review required

New value for Site Visit Check Code (J0024)

Date of latest update
Type
Change
ID
R0143
Change Category
Change Path
Priority
Urgent
Yes
Latest Update
12/10/2023 - Change Proposal has been rejected, as the change needs to be raised under the Balancing & Settlement Code - as the impacted Data Item is a BSC owned Data Item, and is not able to be amended by a REC Change.
Summary
The Change introduces a change to the MM00036/(D0139), to introduce a new Site Visit Check Code to reflect site specific capacity charges being levied by the Distribution Network Operators (DNOs) on Suppliers for their Consumers.
Proposer
Peter Waymont
Change Plan

Impact Assessment Report Published

Completed

Start:

14 Aug 2023

Due:

25 Aug 2023

Completion:

25 Aug 2023
Impacted Consumers
Impacted REC Documents
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
colette.baldwin
Solution Development
Proposed solution summary
  1. As a Consumer, I need my Supplier to be aware of any charges that will be applied by the DNO for the provision of the connection while the site is De-energised.
  2. As a Supplier I need to know if charges are expected to be levied by the DNO for retained capacity for De-energised Metering Points, so that I can pass the costs on to my Consumer.
Problem Statement
DNOs need to be able to communicate to Suppliers that they will charge site-specific DUoS for de-energised sites where there is an ongoing need for the connection to be maintained.
Stages Selection
R0143 - Change Proposal Form
R0143 - Change Proposal Plan v1.0 2 Approved by Change Panel 05.09.2023
R0143 - IAR - New Site Visit Check Code v1.0 Approved by Change Panel 25.09.2023
Company Name
UK Power Networks
Review status
Review required

Recommended Data Access Matrix changes due to Data Permission Matrix changes

Date of latest update
Type
Change
ID
R0141
Urgent
No
Latest Update
04/09/2023 - R0141 has been withdrawn. The Proposer is confident that, if accepted, R0118 – Review of Schedule 12 and processes to manage access to data would provide a more appropriate route to reflect the Data Access Matrix changes required.
Summary
Empty
Proposer
admin
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
Recommeded DAM changes.xlsx
Change Proposal Form External
Company Name
Xoserve
Review status
Review required

Introducing Third Party Intermediary (energy broker) assurance and accreditation

Date of latest update
Type
Change
ID
R0137
Change Category
Urgent
No
Latest Update
16/05/2025 - The Authority has published their decision to reject R0137 and R0137A.
Summary
This change seeks to expand the obligation for Energy Suppliers to only work with TPIs who are adhering to principles as set out in the REC TPI Code of Practice to all Non-Domestic Consumers. It also looks to reduce the burden on Energy Suppliers having to perform their own audits by introducing a REC Services Accreditation Scheme and allowing companies to qualify as an Industry-Recognised Accreditation Body.
Proposer
Jon Dixon
Change Plan

Service Provider Impact Assessment opens

Completed

Start:

20 Jul 2023

Due:

05 Jul 2024

Completion:

05 Jul 2024

Service Provider Impact Assessment closes

Completed

Start:

05 Jul 2024

Due:

09 Aug 2024

Completion:

06 Aug 2024

Party Impact Assessment opens

Completed

Start:

09 Aug 2024

Due:

16 Aug 2024

Completion:

15 Aug 2024

Party Impact Assessment closes

Completed

Start:

16 Aug 2024

Due:

09 Sep 2024

Completion:

09 Sep 2024

Preliminary Change Report Issued

Completed

Start:

09 Sep 2024

Due:

08 Oct 2024

Completion:

08 Oct 2024

Responsible Committee Review

Completed

Start:

08 Oct 2024

Due:

15 Oct 2024

Completion:

15 Oct 2024

Consultation opens

Completed

Start:

15 Oct 2024

Due:

18 Oct 2024

Completion:

17 Oct 2024

Consultation closes

Not Started

Start:

18 Oct 2024

Due:

08 Nov 2024

Completion:

Responsible Committee Decision

Not Started

Start:

10 Dec 2024

Due:

17 Dec 2024

Completion:

Final Change Report issued

Not Started

Start:

08 Nov 2024

Due:

10 Dec 2024

Completion:

Sent to Authority for Determination

Not Started

Start:

17 Dec 2024

Due:

18 Dec 2024

Completion:

Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Non-Domestic Consumer, I want to work with TPIs who are demonstrating best practice standards within the market.
  2. As a Non-Domestic Energy Supplier, I want clear obligations around my use of TPIs so I can demonstrate best practice standards within the market and ensure my audit obligations are met.
  3. As RECCo, I want to provide an assurance and accreditation scheme to register TPIs to remove the burden of Suppliers having to individually audit TPIs.
  4. As a Third Party Intermediary, I want clear obligations so I can become accredited and assure that Suppliers and Non-Domestic Consumers are receiving best practice standards within the market.
Proposed Solution Document
Document title
Legal Text for Party IA.zip
Upload document
Legal Text for Party IA.zip
Archive
Off
Document title
R0137 Legal Text for Consultation
Upload document
R0137 Legal Text for Consultation.zip
Archive
Off
Document title
R0137 Legal Text - Final
Upload document
R0137 Final Legal Text (1).zip
Archive
Off
Problem Statement
Non-Domestic Consumers have more limited protections than Domestic and Microbusiness Consumers in the energy market, and so may not always experience best practice from all parties they interact with. The aim is to expand these protections while limiting the audit burdens on Suppliers and TPIs.
Stages Selection
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
R0137 - Change Proposal Form External
R0137 Change Proposal Plan v1.0 (Approved)
R0137 Initial Assessment Report v1.1 (Approved)
R0137 Consolidated Impact Assessment Responses PUBLIC
R0137 and R0137A Change Report (For Consultation) V1.0
R0137 &R0137A Consolidated Consultation Responses PUBLIC v1.0
R0137 and R0137A Change Report (Post Vote) V1.0
Authority decision on REC modification proposal R0137 and R0137A
Company Name
RECCo
Review status
Review required

Add DESNZ to Schedule 12

Date of latest update
Type
Change
ID
R0135
Change Category
Change Path
Priority
Urgent
No
Latest Update
22/03/2024 - Withdrawn.
Summary
Empty
Proposer
Elise Handy
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Stages Selection
R0135 - Change Proposal Form
Company Name
BEIS (Department for Business, Energy and Industrial Strategy)
Review status
Review required

VLP data access requirements

Date of latest update
Type
Change
ID
R0134
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
22/03/2024 - Withdrawn.
Summary
Empty
Proposer
Elise Handy
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Stages Selection
ESS data items requirements.xlsx
R0134 - Change Proposal Form
R0054 Draft DAM changes.xlsx
Company Name
Levelise Limited
Review status
Review required