Amendment to Multiplication Factor Enumerations to Support Hydrogen Trials

Date of latest update
Type
Change
ID
R0142
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
28/06/2024 - Change implemented as part of the June 2024 REC Release
Summary
The H100 hydrogen gas trial involves the supply of hydrogen gas to households in place of natural gas. The quantity of gas supplies needs to be billed in a way that is comparable to standard gas supply. To facilitate the trial, a multiplication factor enumeration value must be established within the Data Specification that can replicate hydrogen’s calorific value, therefore allowing accurate billing.
Proposer
David Addison
Change Plan

SERVICE PROVIDER IMPACT ASSESSMENT ISSUED

Completed

Start:

11 Aug 2023

Due:

27 Nov 2023

Completion:

27 Nov 2023

PARTY IMPACT ASSESSMENT ISSUED

Completed

Start:

27 Nov 2023

Due:

01 Dec 2023

Completion:

01 Dec 2023

PRELIMINARY CHANGE REPORT PUBLISHED

Completed

Start:

01 Dec 2023

Due:

19 Jan 2024

Completion:

19 Jan 2024

CONSULTATION ISSUED

Completed

Start:

19 Jan 2024

Due:

19 Jan 2024

Completion:

19 Jan 2024

FINAL CHANGE REPORT PUBLISHED

Completed

Start:

19 Jan 2024

Due:

20 Feb 2024

Completion:

16 Feb 2024

RESPONSIBLE COMMITTEE DECISION

Completed

Start:

20 Feb 2024

Due:

28 Feb 2024

Completion:

28 Feb 2024
Impacted Consumers
Impacted REC Documents
Status
Implementation Date
Status Superseded
EMAR Version 3.11.0_Superseded
Included changes Affected REC Items
R0043 Commissioning of Works by the Crowded Meter Room Coordinator (CMRC) to Resolve Issues In Crowded Meter Rooms
  • MOCoPA (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 12 - Data Access
  • Data Access Matrix (Electricity)
  • Data Item Catalogue
  • Market Message Catalogue
R0158 Amendment to the ‘Supplier Registration Report (MAP)’ report methodology
R0160 Electricity Supply to Hydrogen Electrolysers
  • Schedule 1 - Interpretations and Definitions
R0064 Creating a Meter Operator Agent and MOCoP Installer
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 9 - Qualification and Maintenance
R0070 Provision of Enduring Test Environments
  • Schedule 1 - Interpretations and Definitions
  • Schedule 5 - Change Management
  • Schedule 26 - Switching Service Management
  • Schedule 25 - Central Switching Service

Documents

Name Version Last updated Actions
159.49 KB
Version 1.0 - 16 Nov 2026 PDF - 159.49 KB
1.0 16 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
Lydia Bentley
Solution Development
Proposed solution summary
  1. As a Consumer taking part in the H100 trial, I want to be charged based on the amount of gas I consume, such that I am not charged more than I would have been, had I consumed the equivalent energy from natural gas.
  2. As a Gas Supplier, I want to ensure H100 trial Consumers, are not charged more than they would have been, had they consumed the equivalent energy from natural gas. 2- As a Gas Transporter, I want to accurately know how much hydrogen gas is being offtaken, so that I can support Suppliers. 3- As the Central Data Service Provider (CDSP), I want Market Messages relating to meter asset information to be accurate, so that I am better able to support dependant REC Parties. 4- As a Meter Equipment Manager (MEM), I want my metering assets compatible with the H100 trial to be underpinned by accurate Market Messages, so that I able to manage these meters correctly.
Proposed Solution Document
Document title
R0142 Solution - DI40145 - A0120 - Multiplication Factor Change v2.0
Upload document
R0142 Solution-DI40145-A0120-Multiplication Factor Change v2.0.pdf
Archive
Off
Document title
R0142 Solution-DI40145-A0120-Multiplication Factor Change v2.1
Upload document
R0142 Solution-DI40145-A0120-Multiplication Factor Change v2.1.pdf
Archive
Off
Problem Statement
In order for the H100 gas trial to be successful, a billable value for hydrogen gas needs to be accurately calculated from supplied physical volumes. To do this, relevant Data Items (relating to the calculation of billable gas volumes) within the Data Specification need to be updated to allow a new value for the multiplication factor. This change seeks to introduce a new enumeration value for the multiplication factor needed to facilitate the addition of this new value.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
SME Role
Lead Assurance Analyst
DI40145 Multiplication Factor - 23.06.2023
R0142 - Change Proposal Form.pdf
R0142 - Change Proposal Form
R0142 Change Proposal Plan v1.0 (Approved) - 05.12.2023
R0142 Initial Assessment Report v1.0 (Approved) - 05.12.23
R0142 Consolidated Impact Assessment Responses V1.0 16.01.24
R0142 Preliminary Change Report (Published for Consultation) V1.0 19.01.24
R0142 Consolidated Consultation Responses v1.0 16.02.24
R0142 Final Change Report (Post-Vote) v1.0 - 28.02.24
Company Name
Xoserve
Review status
Review required

Housekeeping amendments

Date of latest update
Type
Change
ID
R0140
Change Category
Change Path
Priority
Urgent
No
Latest Update
03/11/23 - This change was implemented on 03 November 2023 as part of the November 2023 REC Release
Summary
The Code Manager has identified a number of typographical and formatting errors, as well as opportunities to provide clarity, improve consistency and accuracy across the REC Services and products. These changes have been assessed as meeting the criteria to be progressed via a Housekeeping Change Proposal. Schedule 27 – RMP Lifecycle Schedule 1 – Interpretations and Definitions Schedule 5 – Change Management Schedule 9 – Qualification and Maintenance
Proposer
Holly Law
Change Plan

Publish House Keeping Change Report

Completed

Start:

11 Aug 2023

Due:

08 Sep 2023

Completion:

08 Sep 2023

Responsible Committee decision

Completed

Start:

08 Sep 2023

Due:

19 Sep 2023

Completion:

19 Sep 2023

Implemented

Completed

Start:

19 Sep 2023

Due:

03 Nov 2023

Completion:

03 Nov 2023
Status
Implementation Date
Status Superseded
EMAR Version 3.6.0_Superseded
Included changes Affected REC Items
R0110 A review of Supplier access to data on GES
R0138 Combined progression of Change Proposals R0058, R0104 and R0129
R0140 Housekeeping amendments
R0059 Maintenance of Qualification Schedule Change
  • Schedule 1 - Interpretations and Definitions
  • Schedule 9 - Qualification and Maintenance
R0088 Make Shipper NExA values available on the GES portal
R0017 Invalid Requests for Site Technical Details
  • Schedule 14 - Metering Operations
  • Data Item Catalogue
  • Market Message Catalogue

Documents

Name Version Last updated Actions
222.91 KB
Version 1.0 - 02 Nov 2026 PDF - 222.91 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
holly.law
Solution Development
Proposed Solution Document
Document title
R0140 Final Draft Legal text
Upload document
R0140 Final Draft Legal text.zip
Archive
Off
Problem Statement
This is a Housekeeping Change Proposal subject to the Housekeeping Change Proposal process, rather than the standard change process. The nature of the change is that it makes non-material changes to the REC Products to correct typographical and consistency errors. It also provides an opportunity to introduce necessary clarifications.
R0140 - Housekeeping Change Report v1.0 (Approved) 19.09.23
Company Name
Gemserv
Review status
Review required

Alignment of Market Message D0225 ‘consent to share flag’ to support PSR data sharing

Date of latest update
Type
Change
ID
R0139
Change Category
Change Path
Priority
Urgent
Yes
Latest Update
This change was implemented on the 12th April 2024.
Summary
Ofgem have been in with discussion with Energy Suppliers this year, requesting them to voluntarily change how they use the consent option within the Priority Services Register (PSR) flow. This Change Proposal (CP) has been raised to make sure the Market Message mirrors the process agreed between Ofgem and Energy Suppliers by re-naming the Priority Services Register (PSR) Data Item DI51497 (J2208) as “Lawful basis for sharing” and to amend the relevant clauses in REC Schedule 13 if needed.
Proposer
Katie Stanyard
Change Plan

Party Impact Assessment

Completed

Start:

11 Aug 2023

Due:

05 Jan 2024

Completion:

05 Jan 2024

Preliminary Change Report Issued

Completed

Start:

05 Jan 2024

Due:

26 Jan 2024

Completion:

26 Jan 2024

Consultation

Completed

Start:

26 Jan 2024

Due:

09 Feb 2024

Completion:

09 Feb 2024

Final Change Report Issued

Completed

Start:

09 Feb 2024

Due:

16 Feb 2024

Completion:

16 Feb 2024

Responsible Committee Decision

Not Started

Start:

16 Feb 2024

Due:

28 Feb 2024

Completion:

Appeal Window Closure

Not Started

Start:

28 Feb 2024

Due:

13 Mar 2024

Completion:

Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 3.10.0_Superseded
Included changes Affected REC Items
R0062 Removal of ERDA meteringPointEnergyFlow change restriction
  • Schedule 27 - RMP Lifecycle
R0063 Addition of key information to all Service Now tickets
R0093 Uplift to CSS Maximum Demand Volumes during MHHS Migration Period
  • Schedule 1 - Interpretations and Definitions

Documents

Name Version Last updated Actions
172.63 KB
Version 1.0 - 16 Nov 2026 PDF - 172.63 KB
1.0 16 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
holly.law
Solution Development
Proposed Solution Document
Document title
Redlining - DI51497 - J2208 - Consent to share data obtained
Upload document
D0139 redlining - DI51497 - J2208 - Consent to share data obtained v0.2 (1).pdf
Archive
Off
Problem Statement
The current PSR Data Item DI51497(J2208) ‘Consent to share data obtained’ does not mirror the legal basis for sharing data that DNOs rely on, or the process that Suppliers have planned to have in place by early 2024.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0139 - Change Proposal Form
Consolidated Impact Assessment Responses
Consolidated Consultation Responses R0139
R0139 Change Proposal Plan v1.0 Approved
R0139 Initial Assessment Report v1.1 Approved
R0139 - Extension to Change Plan v1.0
R0139 Preliminary Change Report v1.0
R0139 Final Change Report v1.0 approved
ICO letter to Ofgem
R0139 redlining - DI51497 - J2208 - Consent to share data obtained
Company Name
Energy Networks Association
Review status
Review required

Combined progression of Change Proposals R0058, R0104 and R0129

Date of latest update
Type
Change
ID
R0138
Change Category
Change Path
Priority
Urgent
No
Latest Update
03/11/23 - This change was implemented on 03 November 2023 as part of the November 2023 REC Release
Summary
This change seeks to efficiently address the issues raised under the following Change Proposals. R0058 – REC Services Procurement Clarification R0104 – Clarifying Requirement for Continuous Billing Following an Erroneous Switch R0129 – Clarifying Event of Default Requirements These Change Proposals have been identified by the Code Manager as requiring non-contentious, clarificatory and non-material alterations to the REC Legal Text only.
Proposer
Elise Handy
Change Plan

Preliminary Change Report published

Completed

Start:

04 Aug 2023

Due:

01 Sep 2023

Completion:

01 Sep 2023

Consultation close

Completed

Start:

01 Sep 2023

Due:

15 Sep 2023

Completion:

15 Sep 2023

Final Change Report published

Completed

Start:

15 Sep 2023

Due:

22 Sep 2023

Completion:

22 Sep 2023

Responsible Committee decision

Not Started

Start:

22 Sep 2023

Due:

03 Oct 2023

Completion:

Status
Implementation Date
Status Superseded
EMAR Version 3.6.0_Superseded
Included changes Affected REC Items
R0110 A review of Supplier access to data on GES
R0138 Combined progression of Change Proposals R0058, R0104 and R0129
R0140 Housekeeping amendments
R0059 Maintenance of Qualification Schedule Change
  • Schedule 1 - Interpretations and Definitions
  • Schedule 9 - Qualification and Maintenance
R0088 Make Shipper NExA values available on the GES portal
R0017 Invalid Requests for Site Technical Details
  • Schedule 14 - Metering Operations
  • Data Item Catalogue
  • Market Message Catalogue

Documents

Name Version Last updated Actions
222.91 KB
Version 1.0 - 02 Nov 2026 PDF - 222.91 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Market Participant, I need the REC drafting to be accurate, so I can rely on it to ensure my processes and procedures correctly reflect my obligations. If there are mistakes or omissions, then it could cause issues with the effective operation and assurance of the retail energy market.
Proposed Solution Document
Document title
R0138 - Draft Legal Text
Upload document
R0138 - Draft Legal Text.zip
Archive
Off
Problem Statement
Three Change Proposals have been placed on hold due to having a low priority status. These proposals have been identified as having fully formed solutions, which are non-contentious and can be quickly implemented. This change seeks to address these Change Proposals so that they can be addressed, and their benefits realised.
DRAFT Change Proposal Form - Umbrella 2 CP.docx
R0138 - Initial Assessment Report (Approved) 15.08.2023
R0138 - Change Proposal Plan (Approved) 15.08.2023
R0138 - Consolidated Consultation Responses
R0138 - Preliminary Change Report v1.0 (01.09.2023) published for Consultation
R0138 - Final Change Report (Post-Vote) 03.10.2023
Company Name
REC Code Manager
Review status
Review required

Change to REC Schedule 22 Market Stabilisation Charge (MSC)

Date of latest update
Type
Change
ID
R0136
Change Category
Change Path
Priority
Urgent
Yes
Latest Update
06/12/2023- This Change was implemented as part of the 6 December 2023 Extraordinary Release
Summary
This Change Proposal seeks to deliver two changes to REC Schedule 22 – Market Stabilisation Charge. The first change will update the statement timescales in Schedule 22 to ensure that this is appropriately aligned with the statement Schedule. The second change seeks to update the disputes Section (section 7) of Schedule 22 to include reference to Credit Advice Notes.
Proposer
Lynne Fallon
Change Plan

Impact Assessment and Change Proposal Plan Published

Completed

Start:

17 Jul 2023

Due:

25 Aug 2023

Completion:

25 Aug 2023

Preliminary Change Report Issued

Completed

Start:

25 Aug 2023

Due:

22 Sep 2023

Completion:

22 Sep 2023

Review of PCR by Change Panel

Completed

Start:

22 Sep 2023

Due:

03 Oct 2023

Completion:

03 Oct 2023

Consultation Started

Completed

Start:

03 Oct 2023

Due:

06 Oct 2023

Completion:

06 Oct 2023

Consultation Closes

Completed

Start:

06 Oct 2023

Due:

26 Oct 2023

Completion:

26 Oct 2023

Final Change Report Issued

Completed

Start:

26 Oct 2023

Due:

10 Nov 2023

Completion:

10 Nov 2023

Change Panel Decision

Completed

Start:

10 Nov 2023

Due:

21 Nov 2023

Completion:

21 Nov 2023
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 3.7.0_Live

Documents

Name Version Last updated Actions
160.82 KB
Version 1.0 - 02 Nov 2026 PDF - 160.82 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
Samantha Briggs
Solution Development
Proposed solution summary
  1. As RECCo, I want the Retail Energy Code to specify my obligations, governance and charging mechanisms, so that I can effectively discharge obligations imposed by the Authority through the Licence Condition modification.
  2. As a Domestic Supplier, I want to understand how RECCo will calculate my credits and liabilities and when they will send statements, so that I can plan to review my invoices/credit notes prior to the receipt of monies owed or payments I need to make to RECCo or at an appropriate time for my organisation.
  3. As a Domestic Supplier, I want to understand how I can dispute a Credit Advice which I do not believe is accurate, so that I am able to raise a dispute/challenge compliantly.
Proposed Solution Document
Document title
R0136 - Draft Legal Text (10.11.2023)
Upload document
R0136 - Draft Legal Text v1.0 (1).doc
Archive
Off
Problem Statement
Schedule 22 says that within 10 Working Days after the end of each MSC-4-Week Cycle, RECCo shall send each Energy Supplier a statement in respect of that MSC-4-Week Cycle. This contradicts the 15 days set out in the Process Maps shared with Parties during the development of the administration arrangements of the Market Stabilisation Charge. Additionally, suppliers are querying how they may raise a dispute when they believe they are not entitled to the monies stated on Credit Advice Notices as this process is not set out in the Schedule.
R0136 - Change Proposal Form
R0136 - Changes to Sche 22 - CPP v1.0 (Approved) 05.09.2023
R0136 - Changes to Sch 22 MSC IAR (Approved) v1.0 05.09.2023
R0136 - Preliminary Change Report - (Approved) 03.10.23
R0136 - Consolidated Consultation Response 10/11/2023
R0136 - Final Change Report v2.0 (Post-Vote) 21.11.2023
Company Name
RECCo
Review status
Review required

Add DESNZ to Schedule 12

Date of latest update
Type
Change
ID
R0135
Change Category
Change Path
Priority
Urgent
No
Latest Update
22/03/2024 - Withdrawn.
Summary
Empty
Proposer
Elise Handy
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Stages Selection
R0135 - Change Proposal Form
Company Name
BEIS (Department for Business, Energy and Industrial Strategy)
Review status
Review required

VLP data access requirements

Date of latest update
Type
Change
ID
R0134
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
22/03/2024 - Withdrawn.
Summary
Empty
Proposer
Elise Handy
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Stages Selection
ESS data items requirements.xlsx
R0134 - Change Proposal Form
R0054 Draft DAM changes.xlsx
Company Name
Levelise Limited
Review status
Review required

Consequential Cross-Code Change for BSC P441 - Complex Site Classes Creation

Date of latest update
Type
Change
ID
R0133
Change Category
Change Path
Priority
Urgent
No
Latest Update
22/03/2024 - Withdrawn.
Summary
A Balancing & Settlement Code (BSC) Modification P441 is looking to introduce additional Complex Site classes which would categorise the types of Complex Site, with each having clearly defined criteria within the BSC, whilst also facilitating a new "type" of Complex Site (referred to as a Class 6 Complex Site) to allow approval of "non-standard" complex sites. It will also clarify when the netting of Imports from Exports for multiple Metering Systems registered in Supplier Volume Allocation (SVA) is permitted.
Proposer
Elise Handy
Change Plan

Solution Development

Completed

Start:

04 Jul 2023

Due:

14 Aug 2023

Completion:

14 Aug 2023

Party Impact Assessment

Completed

Start:

14 Aug 2023

Due:

14 Aug 2023

Completion:

04 Sep 2023

Preliminary change report

Completed

Start:

14 Aug 2023

Due:

22 Sep 2023

Completion:

22 Sep 2023
Impacted Consumers
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a consumer, I want more choice to take up low-carbon technology and more flexible energy solutions through local energy schemes, such as the Ofgem BEIS Smart System Flexibility Plan and any other future flexibility service provisions that may be developed.
  2. For MEMs, l want to remove ambiguity around the current Complex Site arrangements and will facilitate the advancement of community energy schemes.
  3. For Suppliers, I want to encourage more innovation that will lead to the better use of local energy schemes.
Problem Statement
The introduction of new Complex Site classes is needed into the REC to make the solutions under P441 and DCP 424 work. Meter Equipment Managers (MEMs) will need to understand what their new obligations are in respect of metering requirements, as well as impacts on any of the metering processes associated with a Complex Site.
Stages Selection
Change Proposal Form 04.07.2023
R0133 - Change Proposal Plan v1.0 approved 18/07/2023
R0133 Initial Assessment Report v1.0 Approved 18/07/2023
R0133 - Change Proposal Plan v2.0 (Approved) 13/09/2023
R1033 - Draft Legal Text Schedule 14 - Metering Operations for PCR 22.09.23
R0133 - Consolidated Impact Assessment Responses
R0133 Preliminary Change Report V1.0
Company Name
Code Manager
Review status
Review required

Change the Logical Format of the J0001 (DI50001) ‘Market Participant Role Code’ data item to Char(2)

Date of latest update
Type
Change
ID
R0132
Change Category
Change Path
Urgent
Yes
Latest Update
20/10/2023 - Change Proposal Withdrawn. This change will be progressed through the BSC.
Summary
This Change Proposal looks to implement changes to REC Market Messages impacted by the change in the logical format of the J0001 (DI50001) ‘Market Participant Role Code’ from a character length of one to a character length of two.
Proposer
admin
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a new Market Participant, I want to be able to implement Electricity industry solutions and initiatives utilising industry systems that require me to be assigned a MPRC
  2. As an existing Market Participant, I want to be able to define my interactions with other Market Participants using unique Market Role code identifiers As the BSC, I want to be able to assign new MPRCs so that we can fulfil requests as part of new market solutions
  3. As a new or existing Market Participant, I want to be able to continue sending and receiving Market Messages which include the MPRC within the file
Problem Statement
Under the current logical format there are only 36 possible MPRCs available for the Electricity industry, and they have all been allocated. The BSC are therefore currently unable to allocate new MPRCs and propose to update the logical format of the J0001 (DI50001) ‘Market Participant Role Code’. REC owned Market Messages will need to be updated to accommodate the new logical format.
Stages Selection
REC Change Proposal for J0001 Logical Format_Attachment 1_proposed amendment.docx
R0132 Change Proposal Form
R0132 Change Proposal Plan v1.0 (Approved) 19.09.2023
R0132 Initial Assessment Report v1.0 (Approved) 19.09.2023
Company Name
BSCCo
Review status
Review required

Creation of new Enquiry Service User Category

Date of latest update
Type
Change
ID
R0131
Change Category
Change Path
Priority
Urgent
No
Latest Update
17/06/2024 - this Change Proposal has been withdrawn at the request of the Proposer. The adoption window is closed.
Summary
Empty
Proposer
Tony SARKIS
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
R0131 - Change Proposal Form (downloadable version) 22.06.2023
Company Name
-
Review status
Review required