Legacy Data Item API Service
Date of latest update
Type
Change
ID
R0290
Change Category
Change Path
Priority
Urgent
No
Latest Update
02/06/2026 - the REC Change Panel voted to reject the implementation of this Change Proposal, in line with the Code Manager recommendation. The appeal window closed on 17 June 2026.
Summary
MHHS removes certain Data Items (e.g. Profile Class, Measurement Class, Standard Settlement Configuration, Time Pattern Regime etc.) that are important to wider processes and products offered to consumers. This proposal is seeking a mechanism for electricity Market Participants to look up the previous entries for these legacy Data Items held before MHHS Migration begins.
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Date
26 June 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0290 New Schedule Legacy Data Item API V0.4
Upload document
I0290 Legacy Data Item API V0.4.docx
Archive
Off
Document title
R0290 Schedule 1 Defined Terms V0.2
Upload document
I0290 Schedule 1 Defined Terms V0.2.docx
Archive
Off
Document title
R0290 Schedule 9 Qualification and Maintenance v0.1
Upload document
I0290 Scheudle 9 Qualification and Maintenance v0.1.docx
Archive
Off
Problem Statement
The risk of loss of certain Data Items for MHHS Migrated Metering Points may impact Parties in their ability to carry out and support industry processes, or in what products they are able to offer Consumers, in both the MHHS Market and following a Reverse Migration.
Stages Selection
SME
SME Role
Lead Technical Analyst
I0290 submission form
I0290 Change Report (Proposal Plan) V1.0
I0290 Extension to Plan V1.0 approved 27.03.26
I0290 Extension to Plan V2.0 approved 27.04.26
R0290 Change Report (For Consultation) v1.0
R0290 Consolidated Consultation Responses V1.0
Energy Consultants Association - letter on Change Report (Final Recommendation)
R0290 Change Report (Final Recommendation) v1.1 post vote 02.06.2026
Company Name
Stark
Review status
Review required
Clarification on Detailed Impact Assessment Activities
Date of latest update
Type
Change
ID
R0286
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
The first complex technical change R0067 (Introduction of CSS Refresh Functionality) encountered a number of challenges within the design and implementation process, the change was scheduled for implementation on the 6th December 2023, however, the change was deployed with defects and was not fully operational until February 2024. Following that session, the Code Manager held discussions, and a formal Lessons Learned session with all Service Providers and identified a number of challenges with the technical change process. Some of these challenges can be attributed to the timing of the detailed design, Detailed Impact Assessments (DIA) and party impact assessments
Impacted Consumers
Impacted REC Documents
Status
Status
Implementation Date
26 June 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- An update to the REC Schedule 5 - Change Management.
Proposed Solution Document
Document title
R0286 Proposed legal text v1.1
Upload document
R0286_Draft legal text_v1.1.docx
Archive
Off
Problem Statement
The technical change process currently creates five challenges which can be attributed to the timing of the detailed design, PIA and DIAs. These are as follows: Lack of Clarity, Limited Feedback, Misalignment, High Contingency Costs and Inaccurate Timelines.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Change Management v3.5 RedLine for IA Clarifications
I0286 submission form
R0286_Consolidated Consultation responses V1.0
Company Name
REC Technical Services
Review status
Review required
Organisations with multiple role types EES and SDEP access
Date of latest update
Type
Issue
ID
I0285
Change Category
Change Path
Priority
Urgent
No
Latest Update
On 22 October 2026, the Code Manager published the I0285 Closure Report. Following a review of the responses to the Party impact assessment, the Code Manager has determined that this REC Issu can be moved to Resolved as there has been a lack of Parties indicating they would use the proposed solution under I0285. The enduring solution of one individual assigned to two company groups to use two separate email addresses for each company group will be sustained. RECCo will consider the requirement for a single login across multiple roles as part of the Enquiry Services Evolution project development.
Summary
It is currently not possible for organisations with multiple role types to have the same person be able to access all assigned role types within the Secure Data Exchange Portal (SDEP) without having a unique email address for each role type.
Change Plan
Change Report (Proposal Plan) approved by Change Panel
Completed
Start:
Due:
Completion:
04 Nov 2025Discussed at Technical Expert Panel
Completed
Start:
Due:
Completion:
17 Dec 2025Discussed at Technical Expert Panel
Completed
Start:
Due:
Completion:
28 Jan 2026Extension to Plan approved by Technical Expert Panel
Completed
Start:
Due:
Completion:
25 Feb 2026Discussed at Change Issues Group
Completed
Start:
Due:
Completion:
06 Aug 2026Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Zip file with I0285 legal text
Upload document
Legal text for Party IA (2).zip
Archive
Off
Document title
I0285 Solution Development Report V1.0
Upload document
I0285 Solution Development Report V1.0.pdf
Archive
Off
Problem Statement
Organisations with more than one role type are required to have unique email addresses for staff who require access to multiple role types, leading to inefficiencies, unnecessary administrative burdens and a poor user experience.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
I0285 submission form
I0285 Change Report (Proposal Plan) V1.0 approved 04.11.25
I0285 Extension to Plan V1.0 approved 25.02.26
I0285 Extension to Plan V2.0 approved 24.06.26
I0285 Consolidated Impact Assessment Responses v1.0
I0285_Closure Report
Company Name
REC Code Manager
Review status
Review required
Updates to Schedule 14 Measurement Transformers Commissioning Timescales
Date of latest update
Type
Change
ID
R0284
Change Category
Change Path
Priority
Urgent
No
Latest Update
12/08/2026 - the Metering Expert Panel approved the Change Report (Final Recommendation) V1.2. This Change Proposal will be implemented on 26 June 2027. If you wish to appeal this decision, this must be received by COB 28 August 2026.
Summary
The current timetables in REC Schedule 14 Metering Operations sections 15.6 and 30.6, where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 and the Measurement Transformers are owned by the DNO, or in 15.7 and 30.7 where the Measurement Transformers are not owned by the DNO, may no longer be fit for purpose post the implementation of MHHS Milestone M16, where the Settlement timetable reduces the RF run to 4 months.
Change Plan
Change Report (Proposal Plan) approved by Change Panel
Completed
Start:
Due:
Completion:
03 Feb 2026Presented at Change Issues Group
Completed
Start:
Due:
Completion:
05 Feb 2026Change Report (For Consultation) approved by Metering Expert Panel
Completed
Start:
Due:
Completion:
08 Apr 2026Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Date
25 June 2027
| Included changes | Affected REC Items | |
|---|---|---|
| R0122 | SDEP Review Improvements (2) - Usability | |
| R0178 | Improvements to CSS Business Process Logic | |
| R0284 | Updates to Schedule 14 Measurement Transformers Commissioning Timescales |
|
| R0321 | DNOs Create Export MPANs after approving G98/99 commissioning documents |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0284 Schedule 14 Metering Operations draft V0.2
Upload document
I0284 Schedule 14 Metering Operations draft V0.2.pdf
Archive
Off
Document title
R0284 Schedule 14 Metering Operations draft V0.3
Upload document
I0284 Schedule 14 Metering Operations draft V0.3.pdf
Archive
Off
Document title
R0284 Schedule 14 Metering Operations final version
Upload document
I0284 Schedule 14 Metering Operations final version.pdf
Archive
Off
Problem Statement
The current timetables in REC Schedule 14 Metering Operations sections 15.6 and 30.6, where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 and the Measurement Transformers are owned by the DNO, or in 15.7 and 30.7 where the Measurement Transformers are not owned by the DNO, may no longer be fit for purpose post the implementation of MHHS Milestone M16, where the Settlement timetable reduces the RF run to 4 months.
Stages Selection
I0284 submission form
I0284 Change Report (Proposal Plan) V1.0 approved 03.02.26
I0284 Change Issue Group paper v1.0
I0284 Consolidated Impact Assessment Responses PUBLIC v1.0
R0284 Change Report (For Consultation) V1.0 approved 08.04.26
R0284 Consolidated Consultation Responses PUBLIC v1.0
R0284 Change Report (Final Recommendation) V1.2 approved 12.08.26
Company Name
REC Code Manager
Review status
Review required
Return of Legacy Meters
Date of latest update
Type
Issue
ID
I0282
Change Path
Priority
Urgent
No
Latest Update
08/04/2026 - The Closure Report was presented to the REC Metering Expert Panel at their meeting on 08 April 2026. The Issue has now been classed as resolved.
Summary
The issue identified is that current arrangements require or assume that legacy Meter Asset Providers (MAPs) take back old, non Smart Meters once they are removed from Consumers’ Premises, even though many of these meters are obsolete, cannot be reused, and ultimately require disposal. This has resulted in large volumes of legacy meters being transported across the country between storage providers and legacy MAPs, creating unnecessary cost, administrative burden, and environmental impact. Storage providers are issuing extensive lists of Meter Serial Numbers (MSN) to try to establish meter ownership, and legacy MAPs must manually verify these details. This process has been made more difficult by historical changes in company names and ownership structures. Once ownership is confirmed, the meters are frequently transported to the legacy MAP only for them to arrange disposal, which provides no net value and simply adds further transportation and handling costs.
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
The process for handling removed legacy non Smart Meters is inefficient and environmentally costly, with unclear ownership, unnecessary transport, and no established recycling route. A consistent, sustainable disposal solution is needed to reduce waste, simplify operations, and clarify the management of any scrap value.
Stages Selection
Stages Selection
I0282 submission form
I0282_Closure Report_v1.0 (26 March 2026)
Company Name
SP Electricity North West
Review status
Review required
Extending R0067 Refresh Functionality
Date of latest update
Type
Issue
ID
I0281
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/09/2026 - The update to plan has been approved by the Technical Expert Panel on 30 September 2026.
Summary
CSS Market Messages sent by the Central Switching Service (CSS) to Switching Data Service Providers (SDSPs) are either not being received, being received after Gate Closure, or are being received out of the order that they were originally sent in. This Issue originally aimed to extend the Refresh functionality, implemented for the Gas Retail Data Agent (GRDA).to the Electricity Retail Data Agent (ERDA). Following solution development for I0281, it was agreed that the Refresh functionality would be made available for all Market Participants in receipt of the in-scope messages.
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0281_Proposed_Legal text_PIA_V1.0.
Upload document
I0281_Proposed_Legal text_PIA_V1.0.zip
Archive
Off
Problem Statement
CSS messages are not received by the SDSPs in the order in which they were originally sent, or after Gate Closure, so it can be difficult to detect and often requires significant manual effort to resolve. This issue can directly impact Consumer switching experiences, causing disruption and possible delays in a switch.
Stages Selection
Stages Selection
Workgroup
Workgroup(s)
I0281_Change Report (Update to Plan) v1.0 (Pre-approval)
I0281_Change Report (Update to Plan) v2.0 Approved
I0281_Change Report (Update to Plan) v2.0 (Pre-approval)
I0281_Change Report (Update to Plan) v1.0 Approved 20.05.2026
I0281_Change Report (Proposal Plan) v1.0_Approved 04.11.2025
Company Name
REC Technical Services
Review status
Review required
CSS Certificate Authority audit clarification
Date of latest update
Type
Change
ID
R0280
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
CSS Certificate Authority Service Definition clause 9.1 states that the CSS CA Service will be audited each year by a third party against an approved compliance standard and or methodology. The clause however does not state who initiates the audit (i.e. RECCo, the Code Manager, Switching Operator etc.) and engages with the third party.
Change Plan
Proposal Plan approved at Change Panel
Completed
Start:
Due:
Completion:
21 Oct 2025Final Recommendation vote at PAB
Completed
Start:
Due:
Completion:
16 Dec 2025Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
27 February 2026
| Included changes | Affected REC Items | |
|---|---|---|
| R0179 | Proposal for Limiting Queries in EES API Calls (Single Query per API Call) | |
| R0190 | Related Meter Point RMP status rules |
|
| R0198 | Metering Asset Manager (MAM) Communication Method Register | |
| R0242 | Missing Scenario Variant from R0043 |
|
| R0244 | C21 to be introduced into STIRG Document |
|
| R0235A | Missing Scenario Variants in D0179 Alternate Solution | |
| R0256 | MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101 |
|
| R0270 | Clarification of SIP Qualification Requirements |
|
| R0271 | Clarification of ASP, AMI, and EMO Accession Requirements |
|
| R0272 | Enabling transparency of the CRS Provider’s REC service level performance |
|
| R0277 | Data Latency SLA Alignment for Gas Enquiry Service |
|
| R0280 | CSS Certificate Authority audit clarification |
|
| R0283 | Annual Address Management Plan Updates |
|
| R0287 | Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations |
|
| R0293 | Housekeeping February 2026 |
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0280 Legal Text approved 16.12.2025 v1.0
Upload document
R0280 - CSS Certificate Authority Service Definition approved 16.12.2025.docx
Archive
Off
Problem Statement
Section 9 of the CSS Certificate Authority Service Definition document mandates an annual third-party audit of the CSS Certificate Authority Service against an approved compliance standard or methodology. However, it does not specify the audit technique or methodology to be used, nor does it specify who is responsible for initiating the audit and engaging with the third-party.
Stages Selection
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
R0280 submission form
R0280 Change Report (Proposal Plan) v1.0 approved 21/10/2025
R0280 Change Report (For Consultation) v1.0
R0280 Consolidated Consultation Responses v1.0
R0280 Change Report (Final Recommendation) Approved 16.12.25 v1.0
Company Name
Smart DCC
Review status
Review required
Housekeeping November 2025
Date of latest update
Type
Change
ID
R0279
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
The Code Manager has identified a number of non-material clarifications, typographical errors and changes needed to REC products.
Change Plan
Approved at Change Panel
Completed
Start:
Due:
Completion:
21 Oct 2025Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Date
07 November 2025
| Included changes | Affected REC Items | |
|---|---|---|
| R0152 | Revision to the Consolidated Metering Code of Practice (CoMCoP) |
|
| R0157 | Removal of Facsimile as a Method of Code Communication |
|
| R0191 | Introduction of SLA for Supplier De-Registration on Disconnected Meters |
|
| R0205 | Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches | |
| R0212 | Protecting Crimestoppers and their Contacts | |
| R0215 | Schedule 30 Switch Meter Reading Problems - Rejections and Timings |
|
| R0060 | ERDS Service Definition timezone correction |
|
| R0232 | Non-Domestic Change of Occupier SDEP Screens (R0155 Solution) | |
| R0243 | Transfer of Standard Settlement Configuration and Time Pattern Regime Data Item Ownership |
|
| R0248 | REC Changes to tie in with DCP451 - Suspending Registrations |
|
| R0254 | Non-Domestic Change of Occupier Reporting (R0155 Solution) | |
| R0255 | Terms of Reference Updates | |
| R0257 | Change to REC for Data processing outside of EEA | |
| R0263 | Sharing Confirmed Energy Theft Data with the BSCCo |
|
| R0269 | Schedule 5 – Change Management: Clarity and Typographical Review |
|
| R0279 | Housekeeping November 2025 |
|
| R0227 | Domestic Elective HH Switching |
|
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
This Housekeeping Change Proposal seeks to make typographical and formatting corrections that have been identified and improve consistency across the REC.
Stages Selection
November 2025 Housekeeping summary spreadsheet V1.0
November Housekeeping legal text (zip file) V1.0
R0279 Housekeeping Change Report V1.0 approved 21.10.25
Company Name
Code Manager
Review status
Review required
Data Latency SLA Alignment for Gas Enquiry Service
Date of latest update
Type
Change
ID
R0277
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
The current performance level for the processing of Data from CDSP is no longer fit for purpose and does not reflect the operational capability of the service. The performance level was originally conceived as part of the CSS programme in 2022 and operational reality has shown it is not required by industry. A revision of the performance level will align service performance metrics with system performance and deliver economic benefit.
Change Plan
Proposal Plan approved at Change Panel
Completed
Start:
Due:
Completion:
07 Oct 2025Final Recommendation approved at TEP
Completed
Start:
Due:
Completion:
26 Nov 2025Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
27 February 2026
| Included changes | Affected REC Items | |
|---|---|---|
| R0179 | Proposal for Limiting Queries in EES API Calls (Single Query per API Call) | |
| R0190 | Related Meter Point RMP status rules |
|
| R0198 | Metering Asset Manager (MAM) Communication Method Register | |
| R0242 | Missing Scenario Variant from R0043 |
|
| R0244 | C21 to be introduced into STIRG Document |
|
| R0235A | Missing Scenario Variants in D0179 Alternate Solution | |
| R0256 | MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101 |
|
| R0270 | Clarification of SIP Qualification Requirements |
|
| R0271 | Clarification of ASP, AMI, and EMO Accession Requirements |
|
| R0272 | Enabling transparency of the CRS Provider’s REC service level performance |
|
| R0277 | Data Latency SLA Alignment for Gas Enquiry Service |
|
| R0280 | CSS Certificate Authority audit clarification |
|
| R0283 | Annual Address Management Plan Updates |
|
| R0287 | Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations |
|
| R0293 | Housekeeping February 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0277 Legal Text For Consultation
Upload document
R0277 Legal Text For Consultation.zip
Archive
Off
Problem Statement
The current performance levels for the processing of data from CDSP is no longer fit for purpose and does not align with system or service performance. The CSDP is also not meeting these performance levels on a monthly basis. While there are no known issues on data latency raised by users, this change to clarify performance levels is needed for the GES reinstated contract and to ensure ongoing service delivery.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0277 submission form
I0277 Change Report (Proposal Plan) approved 07/10/2025
R0277 Change Report (For Consultation) v1.0
R0277 Change Report (Final Recommendation) Approved 26.11.25 v1.0
Company Name
RECCo
Review status
Review required
SFIC to CMRM - missing Scenario Variant in D0126 / MM00016
Date of latest update
Type
Change
ID
R0276
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
It has been raised to the Code Manager by a Party that the Scenario Variant of Supply Fault Information Centre (SFIC) to Crowded Meter Room MEM (CMRM) is missing from the D0126 / MM00016 (Asset Condition Report Response / Clearance) Market Message. This should have been introduced as part of REC Change R0043 which introduced the role of the CMRM.
Change Plan
Change Report (Proposal Plan) approved by Change Panel
Completed
Start:
Due:
Completion:
16 Sep 2025Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Date
26 June 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
SFIC to CMRM - missing Scenario Variant in D0126 red-lining (IA)
Upload document
SFIC to CMRM - missing Scenario Variant in D0126 MM00016 legal text.docx
Archive
Off
Document title
SFIC to CMRM - missing Scenario Variant in D0126 red-lining (consultation)
Upload document
SFIC to CMRM - missing Scenario Variant in D0126 V2.0.docx
Archive
Off
Problem Statement
CMRMs can send the D0135 / MM00023 Asset Condition Report Market Message to the SFIC, but the SFIC cannot send a response on the D0126 / MM00016 Asset Condition Report Response / Clearance Market Message to confirm the outcome of their investigation.
Stages Selection
R0276 submission form
R0276 Change Report (Proposal Plan) V1.0 approved 16.09.25
R0276 Consolidated Impact Assessment Responses PUBLIC v1.0
R0276 Change Report (For Consultation) V1.0
R0276 Consolidated Consultation Responses v1.0
R0276 Change Report (Final Recommendation) V1.0 approved 17.12.25
Company Name
REC Code Manager
Review status
Review required