MSC Scheme Non-Domestic Exclusions – Process Clarification

Date of latest update
Type
Issue
ID
I0349
Urgent
No
Latest Update
15/10/2026 REC Issue accepted in by the Code Manager.
Summary
The MSC Scheme applies only to domestic Switches; however, identifying eligible Switches currently relies on the Domestic Premises Indicator (DPI), which may not be applied consistently or reliably. This can result in unnecessary processing where an Energy Supplier, or an entire MPID/SSC within its portfolio, supplies only non-domestic Consumers.
Proposer
Jenny Bridges
Status
Implementation Status
Date Raised
Solution Development
I0349 Submission Form
Company Name
RECCo
Review status
Review required

Energy Code Reform - consequential changes to the REC

Date of latest update
Type
Change
ID
R0348
Change Category
Change Path
Priority
Urgent
No
Latest Update
The Final Recommendation has been published for determination by the REC Change Panel on 17 November 2026.
Summary
On 04 September 2026, Ofgem published a Statutory consultation to seek views on proposed amendments to the Retail Energy Code and affected licences required to implement the new governance framework. The proposals address the principal changes required to introduce the new code governance arrangements, including the revised Code Modification process, the Stakeholder Advisory Forum (SAF), changes to existing governance arrangements and transitional provisions. A review of the wider REC baseline has identified that implementation of those changes has consequential impacts on other REC Schedules and subsidiary REC products which are not, or are not fully, addressed by Ofgem’s proposed statutory modifications. Ofgem's statutory Code Reform process will itself introduce amendments to the REC, including amendments to a number of REC Schedules. Those amendments are outside the scope of R0348 and are not being proposed, assessed or approved through this Change Proposal. Where a REC Schedule is being amended both by Ofgem and by R0348, the two sets of amendments will need to be read together and, on implementation, consolidated to form the complete revised Schedule
Proposer
Ann Perry
Change report - Final Change Report

Comments deadline
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Holly Law
Solution Development
Problem Statement
Without corresponding consequential amendments, parts of the REC baseline could retain references, responsibilities, governance arrangements or processes that are inconsistent with reformed REC arrangements. This could create ambiguity over which governance arrangements apply, where responsibilities sit and which process should be followed. It would also mean that different REC products could describe the same arrangements inconsistently.
Workgroup
Workgroup(s)
Energy Code Reform - consequential changes to the REC submission form
Legal Drafting - consultation
Legal Drafting - Final
R0348 Consolidated consultation responses
Change Report - Final Recommendation
Company Name
-
Review status
Review required

REC change to align with BSC IF-045 notification for Import/Export MPAN meter type misalignment

Date of latest update
Type
Change
ID
R0347
Change Category
Change Path
Urgent
No
Latest Update
05/11/2026 The Party impact assessment was published on 05 November 2026 and will remain open to responses until 27 November 2026. The Issue progressed to a Change Proposal on 05 November 2026.
Summary
Elexon are raising a CP that would introduce additional SMRS validation controls and a new IF-045 notification scenario to identify and manage metering misalignment across associated Import and Export MPANs. As this places obligations on MOAs, an impact to REC Schedule 14 has been identified.
Proposer
Caroline Freimuller
Impacted REC Documents
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Poppy Mullins
Solution Development
Proposed Solution Document
Document title
R0347 Legal Text Draft for Party impact assessment
Upload document
R0347 - Legal Text for Party IA.zip
Archive
Off
Problem Statement
The BSC CP CP1652 – Introduction of IF-045 notification from Registration Service for meter type misalignment was raised at the Supplier Volume Allocation Group on 06 October 2026. Following MHHS migration activity, Distribution Network Operators (DNOs) have identified and removed a population of Import and Export MPAN associations that contained inconsistent metering characteristics, including instances where one MPAN was configured with Smart Metering and the other with Advanced Metering. BSC CP1652 is seeking to create a new IF-045 notification scenario for the Supplier and the MOA to identify and manage misalignment issues. As BSC CP1652 relies on a new obligation on MOAs to agree on an approach to resolve the issue with the Electricity Supplier, a REC Issue is required to update Schedule 14 – Metering Operations.
I0347 Change Report (Proposal Plan) Approved
Company Name
Code Manager
Review status
Review required

REC Changes for the Gas Enquiry Service Evolution

Date of latest update
Type
Issue
ID
I0346
Priority
Urgent
No
Latest Update
03/09/2026 - Issue accepted in by Code Manager
Summary
"As part of the evolution of the Gas Enquiry Service (GES), the service is intended to transition to a new Service Provider with an updated service provided for both the API and Portal. To recognise the new service, a number of changes may be required to REC documentation. These changes will need to be discussed with industry and approved via the REC change process prior to implementation of the new service."
Proposer
Jonny Moore
Status
Implementation Status
Date Raised
Lead Analyst
florentina.monea
Solution Development
I0346 submission form
Company Name
RECCo
Review status
Review required

Housekeeping November 2026

Date of latest update
Type
Change
ID
R0345
Change Category
Change Path
Priority
Urgent
No
Latest Update
06/11/26 - This Change Proposal has been implemented as part of the 6 November 2026 REC Release.
Summary
The Code Manager has identified a number of non-material clarifications, typographical errors and changes needed to REC products.
Proposer
Caroline Freimuller
Change report - Final Change Report

Comments deadline
Status
Implementation Date
Status Live
EMAR Version 4.4.0
Included changes Affected REC Items
R0180 Clarity on use of on hold for switching issues, including the obligations of CSS Users
  • Schedule 26 - Switching Service Management
R0207 Import / Export MOA Charging Clarification
  • Schedule 14 - Metering Operations
R0253 Theft - DNO/Networks not providing photos
  • Schedule 8 - Unbilled Energy Code of Practice
R0261 Addition of Export flag in D0303 flows
R0266 REC Data Specification Clarifications
  • Schedule 14 - Metering Operations
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Data Item Catalogue
  • Market Message Catalogue
R0317 Number of Displayed Register Digits Data Item linkage
R0328 Removal of D0383 & D0384 requirements from Sharing MTDs process
  • Schedule 14 - Metering Operations
R0336 Legal text to support REC Change R0180
  • Schedule 26 - Switching Service Management
R0343 MSC - Amending Statement Production Timescales
R0345 Housekeeping November 2026

Documents

Name Version Last updated Actions
331.85 KB
Version 1.0 - 11 Nov 2026 PDF - 331.85 KB
1.0 11 Nov 2026
1.0 11 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
holly.law
Solution Development
Proposed solution summary
  1. This Housekeeping Change Proposal seeks to make typographical and formatting corrections that have been identified and improve consistency across the REC.
Nov 2026 Housekeeping Summary
November 2026 Housekeeping legal text
Company Name
REC Code Manager
Review status
Review required

Explore use of CHECK as a Meter Type option on J0483 DI-059

Date of latest update
Type
Issue
ID
I0344
Other Industry Codes impacted
Priority
Urgent
No
Latest Update
Change Report (Proposal Plan) has been published for REC Change Panel approval on 17 November 2026.
Summary
It has been suggested that CHECK meters should not be sent within industry messages so the presence of this value within the valid set may not be required. This Issue has been raised to explore whether this assumption is correct, look at the existing/historic use cases industry have used the CHECK option for, if they are no longer valid and if so why not.
Proposer
Holly Law
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Lead Analyst
Ian Chalfon
Solution Development
Problem Statement
The DI-059 / J0483 Meter Type Data Item is shared between the Balancing and Settlement Code’s Data Integration Platform (DIP) and the REC’s Data Catalogue. The CHECK Meter Type does not have a valid MHHS Market Segment combination and is not a valid enumeration under the DIP version of DI-059 / J0483. Having an enumeration that is valid in one version of the Data Item and not valid in another causes confusion as to what enumerations are valid for this Data Item. As part of this Issue, we will also explore whether use of the LAG_, LEAD_, and MAIN_ meter types are still necessary to be kept within D-Flows, even though they are valid meter types for MHHS arrangements.
Workgroup
Workgroup(s)
I0344 submission form
Change Report - Proposal Plan
Company Name
-
Review status
Review required

MSC - Amending Statement Production Timescales

Date of latest update
Type
Change
ID
R0343
Change Category
Change Path
Urgent
Yes
Latest Update
06/11/26 - This Change Proposal has been implemented as part of the 6 November 2026 REC Release.
Summary
RECCo is implementing the MSC solution in two phases to enable a swift restart of the MSC scheme, should a decision be made to recommence it. Phase one will enable data collection and the tracking of Supplier liabilities, allowing the scheme to commence before the full solution is available. Phase two will introduce the calculation and financial components.
Proposer
Jenny Bridges
Change Plan

Proposal Plan approved at Change Panel

Completed

Start:

Due:

Completion:

15 Sep 2026

Final Recommendation approved at Change Panel

Completed

Start:

Due:

Completion:

20 Oct 2026
Status
Implementation Date
Status Live
EMAR Version 4.4.0
Included changes Affected REC Items
R0180 Clarity on use of on hold for switching issues, including the obligations of CSS Users
  • Schedule 26 - Switching Service Management
R0207 Import / Export MOA Charging Clarification
  • Schedule 14 - Metering Operations
R0253 Theft - DNO/Networks not providing photos
  • Schedule 8 - Unbilled Energy Code of Practice
R0261 Addition of Export flag in D0303 flows
R0266 REC Data Specification Clarifications
  • Schedule 14 - Metering Operations
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Data Item Catalogue
  • Market Message Catalogue
R0317 Number of Displayed Register Digits Data Item linkage
R0328 Removal of D0383 & D0384 requirements from Sharing MTDs process
  • Schedule 14 - Metering Operations
R0336 Legal text to support REC Change R0180
  • Schedule 26 - Switching Service Management
R0343 MSC - Amending Statement Production Timescales
R0345 Housekeeping November 2026

Documents

Name Version Last updated Actions
331.85 KB
Version 1.0 - 11 Nov 2026 PDF - 331.85 KB
1.0 11 Nov 2026
1.0 11 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0343 Draft Schedule 22 Market Stabilisation Charge v1.0
Upload document
I0343 Draft Schedule 22 Market Stabilisation Charge v1.0.docx
Archive
Off
Problem Statement
The REC currently requires statements relating to MSC to be provided to Energy Suppliers within 15 working days of the relevant MSC cycle. However, during the phased implementation of the MSC scheme, this timeframe may not provide sufficient time to reconcile the data collection while the calculation functionality is still under development.
I0343 submission form
R0343 Change Report (Consultation) v1.0 Approved 15.09.26
R0343 Consolidated Consultation Responses v1.0
R0343 Change Report (Final Recommendation) V1.0 Approved 20.10.26
Company Name
RECCo
Review status
Review required

Enabling Dual MSA & MSS (SVA MOA) appointments for WC connection types

Date of latest update
Type
Change
ID
R0342
Change Path
Priority
Urgent
No
Latest Update
26/10/2026 - The Consultation has closed. The Code Manager is assessing the responses.
Summary
Under the legacy/pre-MHHS arrangements the market is segmented by Measurement Class (MC) for settlement purposes which is not sensitive to the Meter type that is installed or is to be installed, meaning that the replacement of Traditional meters to either smart or Advanced metering equipment can be arranged without the need for the Change of Measurement Class (CoMC) process to be conducted concurrent with the meter exchange (MEX). Under MHHS, when a WC connection goes through a MEX from Traditional to Advanced, or from Advanced to Smart in the MHHS arrangements a new complexity is placed on suppliers because the CoSeg process must be tightly co-ordinated to a specified planned MEX date and processed through the MPRS within 3 Working Days of that date.
Proposer
Lee Stone
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
florentina.monea
Solution Development
Proposed Solution Document
Document title
R0342 Legal Drafting
Upload document
R0342 Legal Drafting V1.0 (1).docx
Archive
Off
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
R0342 submission form
R0342 Change Report (Proposal Plan and Consultation) v1.1 Approved
R0342 Consolidated Non-Confidential Consultation Responses
Company Name
Npower Commercial Gas Limited
Review status
Review required

Improved Validation for DI51599 - Electricity Smart Meter Equipment (ESME ID)

Date of latest update
Type
Issue
ID
I0341
Priority
Urgent
No
Latest Update
18/11/2026 - The Change Report (Proposal Plan) was approved by the REC Change Panel
Summary
A DNO has raised an issue with the ESME ID data stored in MPRS. Some of the ESMEs are passing MPRS basic validation but are being rejected by the proposed Metering Service preventing a change of service.
Proposer
Daniel Tadecicco
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Lead Analyst
Harry Firth
Solution Development
Problem Statement
A DNO has raised an issue with the ESME ID data stored in MPRS. Some of the ESMEs are passing MPRS basic validation but are being rejected by the proposed Metering Service preventing a change of service (Rejection of IF-033 with IF-035 Response R). Basic REC R032 Validation on IF-005/D0312: XX-XX-XX-XX-XX-XX-XX-XX (0-9, A-Z)
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Workgroup
Workgroup(s)
I0341 submission form
Change Report - Proposal Plan
Company Name
-
Review status
Review required

Amendments to the PARC relating to Address Management

Date of latest update
Type
Change
ID
R0340
Change Category
Change Path
Priority
Urgent
No
Latest Update
The Final Recommendation has been published for determination by the REC Performance Assurance Board on 24 November 2026.
Summary
While undertaking the CRS Improvements Project, RECCo, the Code Manager and DCC completed a review of current reporting that is generated as part of REC Obligations. As part of this review, Address Management-related reports were identified that are not fit for purpose. These reports are produced only for DCC internal consumption. The identified reports are captured in the Performance Assurance Report Catalogue (PARC). As such, DCC proposed raising a REC change to have these removed from the PARC (they will still be available on an ad-hoc on request basis).
Proposer
Bradley Baker
Change Report - Initial Assessment and Change Plan Report
Change report - Final Change Report

Comments deadline

Comments deadline
Impacted REC Services
Status
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0340 - Legal Drafting
Upload document
I0340 draft legal text v0.3.xlsx
Archive
Off
Document title
I0340 Legal Text Changes
Upload document
R0340 draft legal text v0.4.xlsx
Archive
Off
Problem Statement
As part of the Centralised Registration Service (CRS) Improvements Plan some Address Management-related reports included in the Performance Assurance Reporting Catalogue (PARC) were identified as not fit for purpose. These reports are produced only for DCC's internal consumption and are operationally burdensome to produce and store, but the PARC obligates their generation even where the data included in reports is available elsewhere.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Workgroup
Workgroup(s)
I0340 submission form
Company Name
-
Review status
Review required