Prepayment Credit Balance Transfer Process
Initial Analysis
Start:
10 Mar 2022Due:
30 Jun 2022Completion:
Present updated Change Proposal Plan to Change Panel
Start:
30 Jun 2022Due:
19 Jul 2022Completion:
Solution Development Complete
Start:
30 Jan 2023Due:
29 Feb 2024Completion:
29 Feb 2024Present Updated Change Proposal Plan to Change Panel
Start:
19 Jul 2022Due:
08 Nov 2022Completion:
Present Updated Plan to Change Panel
Start:
08 Nov 2022Due:
17 Jan 2023Completion:
17 Jan 2023Service Provider Impact Assessment
Start:
17 Jan 2023Due:
30 Jan 2023Completion:
30 Jan 2023Market Stabilisation Charge – Administration
Party Impact Assessment initiated
Start:
22 Feb 2022Due:
08 Apr 2022Completion:
08 Apr 2022Party Impact Assessment completed
Start:
08 Apr 2022Due:
29 Apr 2022Completion:
29 Apr 2022Preliminary Change Report issued
Start:
29 Apr 2022Due:
06 May 2022Completion:
06 May 2022Issued to Responsible Committee for review (ex-Committee)
Start:
06 May 2022Due:
10 May 2022Completion:
10 May 2022Consultation initiated
Start:
10 May 2022Due:
13 May 2022Completion:
13 May 2022Consultation completed
Start:
13 May 2022Due:
01 Jun 2022Completion:
01 Jun 2022Final Change Report issued
Start:
01 Jun 2022Due:
10 Jun 2022Completion:
10 Jun 2022Responsible Committee Decision (ex-Committee)
Start:
10 Jun 2022Due:
14 Jun 2022Completion:
14 Jun 2022Authority Determination
Start:
14 Jun 2022Due:
24 Jun 2022Completion:
27 Jun 202230 June 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0014 | Cable Colour Identification |
|
| R0019 | Consequential REC changes for BSC CP1532 |
|
| R0008 | Consequential New and Amended Market Messages for BSC Modification P375 |
|
| R0023 | Prepayment Unallocatable Transactions |
|
| R0035 | Market Stabilisation Charge – Administration |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Domestic Consumer, I want to be able to choose my Energy Supplier and a tariff from a range of competitive options, so that I can take advantage of cheaper deals as they become available.
- As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the MSC obligations, so that the new MSC licence obligations on Energy Suppliers can be effectively discharged by RECCo.
- As RECCo, I want the Retail Energy Code to specify my obligations, governance and charging mechanisms, so that I can effectively discharge obligations imposed by the Authority through the Licence Condition modification.
- As a Domestic Supplier, I want to understand how RECCo will calculate my credits and liabilities and when they will send my invoices/credit notes, so that I can plan to review my invoices/credit notes prior to the receipt of monies owed or payments I make to RECCo or at an appropriate time for my organisation. As a Domestic Supplier, I want to understand how I could dispute an invoice which I do not believe is accurate, so that I am able to raise a dispute/challenge compliantly
Market Stabilisation Charge
Preliminary Change Report issued
Start:
21 Feb 2022Due:
04 Mar 2022Completion:
04 Mar 2022Consultation issued (5 WD)
Start:
04 Mar 2022Due:
04 Mar 2022Completion:
04 Mar 2022Final Change Report issued
Start:
04 Mar 2022Due:
18 Mar 2022Completion:
18 Mar 2022Responsible Committee decision (ex-Committee)
Start:
18 Mar 2022Due:
23 Mar 2022Completion:
23 Mar 2022Authority determination
Start:
23 Mar 2022Due:
08 Apr 2022Completion:
08 Apr 202214 April 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0028 | Review of Category 3 documents in the REC Baseline Statement |
|
| R0034 | Market Stabilisation Charge |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the MSC obligations, so that the new MSC licence obligations on Energy Suppliers can be effectively discharged by RECCo.
Erroneous Transfer Cancellations
Solution Development
Start:
13 Jan 2022Due:
22 Apr 2022Completion:
22 Apr 2022Party Impact Assessment Issued
Start:
22 Apr 2022Due:
06 May 2022Completion:
06 May 2022Preliminary Change Report Issued
Start:
06 May 2022Due:
08 Jul 2022Completion:
08 Jul 2022Responsible Committee Review
Start:
08 Jul 2022Due:
19 Jul 2022Completion:
19 Jul 2022Consultation Issued
Start:
19 Jul 2022Due:
05 Aug 2022Completion:
05 Aug 202230 June 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0101 | Revision of the Implementation Date and approved solution for R0021 |
|
| R0102 | Revision of the approved solution for R0032 |
|
| R0114 | Housekeeping amendments |
|
| R0015 | Remote communication obligations for electricity Advanced Meters |
|
| R0010 | New Meter Types for Auxiliary Proportional Controllers (APCs) |
|
| R0011 | Reporting of Additional EMR Backing Data to Suppliers |
|
| R0021 | Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier |
|
| R0030 | Erroneous Transfer Cancellations |
|
| R0066 | Inclusion of SMRS Data Items in EES (BSC CP1568 Consequential Change) | |
| R0032 | New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS) |
|
| R0090 | Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Consumer I want to receive my bills when expected, from the Supplier of my choice without delays caused by being switched incorrectly and not being resolved in a timely manner. As a Consumer, in the event that my Supplier has exited the market and my supply cannot be returned to my original Supplier, I want the Gaining ET Supplier to have the ability to terminate any ET process that has already been initiated so that I am able to choose my preferred Supplier and switch without delay or penalty.
- As a Consumer, if Energy Suppliers need to share my data to resolve a switching issue, I want Suppliers to share my personal data securely so that my data is protected.
- As an Energy Supplier, where appropriate, I need to be able to cancel an ET effectively and efficiently, so that I can bill my Consumers accurately and timely. As an Energy Supplier, where appropriate, I need to be able to cancel an ET so that I supply Consumers with whom I have a valid contract.
- As The Code Manager I need to be able to identify when an ET has been cancelled so that I have a clear audit trail and can monitor performance effectively.
Minimum identification requirements in the Meter Operation Code of Practice
- As an electricity Consumer I want to be able to verify the attending agent’s identity so I can feel safe at my Premises whilst work is completed and trust the Energy industry to care about my safety.
- As an electricity Consumer I want to be able to verify the attending agent’s identity so that work can be completed efficiently, without delay or confusion.
- As an Electricity Supplier I want my Appointed Metering Equipment Manager to be identifiable when attending Consumer Sites to retain Consumer confidence, trust and for works to be completed without delay.
- As a Metering Equipment Manager, I want clarity around the requirements regarding identity cards to be clear so that I can assure compliance and easily identify myself to consumers at site.
- As a Metering Scheme Auditor, I want clarity on appropriate identity requirements so I can confidently validate a Metering Equipment Manager’s identity during a site audit.
Whole current (WC)/Current Transformer (CT) certificates
Solution Analysis and Development Start
Start:
07 Jan 2022Due:
31 Oct 2022Completion:
Impact Assessment Period start
Start:
Due:
Completion:
Solution Development completed
Start:
Due:
Completion:
Impact Assessment period ends
Start:
Due:
Completion:
- As an Electricity Consumer I want to be confident that the Meter Operative that completes work on my Metering Equipment is competent to ensure my supply is safe, secure and uninterrupted.
- As a MEM, I want to be confident that my processes and Meter Operatives are compliant with the MOCoP, to ensure minimal disruption to my clients and the safety of my employees.
- As an Electricity Supplier, I want to be confident that my Appointed agents are compliant with the MOCoP to ensure my consumers safety.
EAC information in the EES API
Solution Development and Party Engagement
Start:
29 Aug 2022Due:
07 Sep 2022Completion:
29 Aug 2022Change Proposal Withdrawal
Start:
20 Dec 2021Due:
29 Aug 2022Completion:
29 Aug 2022- As a domestic Electricity Consumer, I want to be quoted accurately for my electricity usage based on my electricity consumption, so that I can make an informed decision to accept/reject the quotation offered.
- As an Electricity Supplier, I want to have access to the most recent Metering Point consumption data to be able to provide accurate prices/quotations to a consumer based on their Electricity usage.
- As a Third-Party Intermediary (TPI), I want to have access to the most recent Metering Point consumption data to be able to provide accurate prices/quotations to a consumer based on their Electricity usage.
Prepayment Unallocatable Transactions
Preliminary Change Report Issued
Start:
15 Dec 2021Due:
04 Mar 2022Completion:
04 Mar 2022Responsible Committee Decision
Start:
08 Apr 2022Due:
19 Apr 2022Completion:
19 Apr 2022Consultation Period Start
Start:
19 Apr 2022Due:
22 Apr 2022Completion:
22 Apr 2022Consultation Period End
Start:
22 Apr 2022Due:
16 May 2022Completion:
16 May 2022Final Change Report Issued
Start:
16 May 2022Due:
27 May 2022Completion:
27 May 2022Responsible Committee Decision
Start:
27 May 2022Due:
07 Jun 2022Completion:
07 Jun 2022Appeal Window Closure
Start:
07 Jun 2022Due:
22 Jun 2022Completion:
22 Jun 2022Legal Review / Preliminary Change Report Revision
Start:
04 Mar 2022Due:
15 Mar 2022Completion:
15 Mar 2022Revised Preliminary Change Report Issued
Start:
15 Mar 2022Due:
08 Apr 2022Completion:
08 Apr 202230 June 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0014 | Cable Colour Identification |
|
| R0019 | Consequential REC changes for BSC CP1532 |
|
| R0008 | Consequential New and Amended Market Messages for BSC Modification P375 |
|
| R0023 | Prepayment Unallocatable Transactions |
|
| R0035 | Market Stabilisation Charge – Administration |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a PPMIP, I want to receive accurate market share data to allow me to complete the Unallocatable Prepayment Allocation Run in a timely manner.
- As an Energy Supplier, I want the calculation of Unallocatable Transactions to be carried out accurately and efficiently so that I receive payments allocated to my organisation.
Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier
Solution Development
Start:
09 Dec 2021Due:
03 Feb 2022Completion:
19 Apr 2022Party Impact Assessment Issued
Start:
03 Feb 2022Due:
22 Apr 2022Completion:
22 Apr 2022Deadline for Alternative Change Proposal Submission
Start:
22 Apr 2022Due:
27 May 2022Completion:
27 May 2022Preliminary Change Report Issued Interim
Start:
27 May 2022Due:
27 May 2022Completion:
27 May 2022Consultation Issued
Start:
27 May 2022Due:
12 Jul 2022Completion:
12 Jul 2022Final Change Report Issued
Start:
16 Aug 2022Due:
26 Aug 2022Completion:
26 Aug 2022Responsible Committee Decision
Start:
26 Aug 2022Due:
14 Sep 2022Completion:
14 Sep 2022Preliminary Change Report (Updated) Issued
Start:
12 Jul 2022Due:
12 Jul 2022Completion:
12 Jul 2022Consultation closure (extended deadline)
Start:
12 Jul 2022Due:
16 Aug 2022Completion:
16 Aug 202230 June 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0101 | Revision of the Implementation Date and approved solution for R0021 |
|
| R0102 | Revision of the approved solution for R0032 |
|
| R0114 | Housekeeping amendments |
|
| R0015 | Remote communication obligations for electricity Advanced Meters |
|
| R0010 | New Meter Types for Auxiliary Proportional Controllers (APCs) |
|
| R0011 | Reporting of Additional EMR Backing Data to Suppliers |
|
| R0021 | Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier |
|
| R0030 | Erroneous Transfer Cancellations |
|
| R0066 | Inclusion of SMRS Data Items in EES (BSC CP1568 Consequential Change) | |
| R0032 | New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS) |
|
| R0090 | Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a property owner or occupier I want to be to arrange for the installation of equipment for the use of the occupier, such as fitting an isolator, installing on-site generation equipment or electric vehicle charging points. I want the installer to use a Safe Isolator Provider (SIP) who is authorised to undertake the work at my instruction rather than arrange for this work to be completed through the premises’ Registered Suppliers.
- As a REC Accredited Metering Equipment Manager, I want to be able to work as a SIP and de-energise and re-energise a site on the instruction of the homeowner/landlord, so that equipment – such as an isolator, on-site generation or electric vehicle charging points can be fitted without the need to co-ordinate the work with the Registered Suppliers’ MEMs. As a Distribution Network Operator, I want to be assured that the work is only completed by a SIP that has the necessary skills and REC accreditation and has the appropriate permissions to de-energise and re-energise the supply and doesn’t introduce any additional risk to the Distribution Network.
- As the Registered Supplier, I want to know what steps the SIP who attends the site and finds the site in an unsafe situation to re-energise, will take so that my customer is not left off-supply unnecessarily. As the Registered Supplier, I want to be alerted if the SIP finds any evidence of meter tampering at the premises.
Resolution of Bilateral Erroneous Transfers
Solution Analysis
Start:
18 Nov 2021Due:
21 Mar 2023Completion:
Proposed Approach Presented To Change Panel
Start:
21 Mar 2023Due:
18 Apr 2023Completion:
- As a Consumer, I want issues affecting me or my energy account to be resolved at the earliest opportunity, to minimise impacts to my energy switch or accurate and timely billing.
- As a Consumer, I want industry parties to share my personal data securely so that my data is protected.
- As an Energy Supplier, I want to be able to resolve Bilateral Erroneous Transfers effectively and efficiently, so that I can bill my Consumers accurately and timely.
- As an Energy Supplier, I want to be able to resolve Bilateral Erroneous Transfers effectively and efficiently, so that I supply Consumers with whom I have a valid contract.