Prepayment Unallocatable Transactions
Preliminary Change Report Issued
Start:
15 Dec 2021Due:
04 Mar 2022Completion:
04 Mar 2022Responsible Committee Decision
Start:
08 Apr 2022Due:
19 Apr 2022Completion:
19 Apr 2022Consultation Period Start
Start:
19 Apr 2022Due:
22 Apr 2022Completion:
22 Apr 2022Consultation Period End
Start:
22 Apr 2022Due:
16 May 2022Completion:
16 May 2022Final Change Report Issued
Start:
16 May 2022Due:
27 May 2022Completion:
27 May 2022Responsible Committee Decision
Start:
27 May 2022Due:
07 Jun 2022Completion:
07 Jun 2022Appeal Window Closure
Start:
07 Jun 2022Due:
22 Jun 2022Completion:
22 Jun 2022Legal Review / Preliminary Change Report Revision
Start:
04 Mar 2022Due:
15 Mar 2022Completion:
15 Mar 2022Revised Preliminary Change Report Issued
Start:
15 Mar 2022Due:
08 Apr 2022Completion:
08 Apr 202230 June 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0014 | Cable Colour Identification |
|
| R0019 | Consequential REC changes for BSC CP1532 |
|
| R0008 | Consequential New and Amended Market Messages for BSC Modification P375 |
|
| R0023 | Prepayment Unallocatable Transactions |
|
| R0035 | Market Stabilisation Charge – Administration |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a PPMIP, I want to receive accurate market share data to allow me to complete the Unallocatable Prepayment Allocation Run in a timely manner.
- As an Energy Supplier, I want the calculation of Unallocatable Transactions to be carried out accurately and efficiently so that I receive payments allocated to my organisation.
Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier
Solution Development
Start:
09 Dec 2021Due:
03 Feb 2022Completion:
19 Apr 2022Party Impact Assessment Issued
Start:
03 Feb 2022Due:
22 Apr 2022Completion:
22 Apr 2022Deadline for Alternative Change Proposal Submission
Start:
22 Apr 2022Due:
27 May 2022Completion:
27 May 2022Preliminary Change Report Issued Interim
Start:
27 May 2022Due:
27 May 2022Completion:
27 May 2022Consultation Issued
Start:
27 May 2022Due:
12 Jul 2022Completion:
12 Jul 2022Final Change Report Issued
Start:
16 Aug 2022Due:
26 Aug 2022Completion:
26 Aug 2022Responsible Committee Decision
Start:
26 Aug 2022Due:
14 Sep 2022Completion:
14 Sep 2022Preliminary Change Report (Updated) Issued
Start:
12 Jul 2022Due:
12 Jul 2022Completion:
12 Jul 2022Consultation closure (extended deadline)
Start:
12 Jul 2022Due:
16 Aug 2022Completion:
16 Aug 202230 June 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0101 | Revision of the Implementation Date and approved solution for R0021 |
|
| R0102 | Revision of the approved solution for R0032 |
|
| R0114 | Housekeeping amendments |
|
| R0015 | Remote communication obligations for electricity Advanced Meters |
|
| R0010 | New Meter Types for Auxiliary Proportional Controllers (APCs) |
|
| R0011 | Reporting of Additional EMR Backing Data to Suppliers |
|
| R0021 | Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier |
|
| R0030 | Erroneous Transfer Cancellations |
|
| R0066 | Inclusion of SMRS Data Items in EES (BSC CP1568 Consequential Change) | |
| R0032 | New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS) |
|
| R0090 | Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a property owner or occupier I want to be to arrange for the installation of equipment for the use of the occupier, such as fitting an isolator, installing on-site generation equipment or electric vehicle charging points. I want the installer to use a Safe Isolator Provider (SIP) who is authorised to undertake the work at my instruction rather than arrange for this work to be completed through the premises’ Registered Suppliers.
- As a REC Accredited Metering Equipment Manager, I want to be able to work as a SIP and de-energise and re-energise a site on the instruction of the homeowner/landlord, so that equipment – such as an isolator, on-site generation or electric vehicle charging points can be fitted without the need to co-ordinate the work with the Registered Suppliers’ MEMs. As a Distribution Network Operator, I want to be assured that the work is only completed by a SIP that has the necessary skills and REC accreditation and has the appropriate permissions to de-energise and re-energise the supply and doesn’t introduce any additional risk to the Distribution Network.
- As the Registered Supplier, I want to know what steps the SIP who attends the site and finds the site in an unsafe situation to re-energise, will take so that my customer is not left off-supply unnecessarily. As the Registered Supplier, I want to be alerted if the SIP finds any evidence of meter tampering at the premises.
ETTOS Report Dissemination
Initial Assessment Report published
Start:
29 Nov 2021Due:
03 Dec 2021Completion:
03 Dec 2021Change Panel review
Start:
03 Dec 2021Due:
07 Dec 2021Completion:
07 Dec 2021Preliminary Change Report issued
Start:
07 Dec 2021Due:
13 Dec 2021Completion:
13 Dec 2021Change Panel review
Start:
13 Dec 2021Due:
21 Dec 2021Completion:
21 Dec 2021Consultation starts
Start:
21 Dec 2021Due:
22 Dec 2021Completion:
21 Dec 2021Consultation ends
Start:
22 Dec 2021Due:
12 Jan 2022Completion:
12 Jan 2022Final Change Report issued
Start:
12 Jan 2022Due:
14 Jan 2022Completion:
14 Jan 2022Change Panel decision
Start:
14 Jan 2022Due:
18 Jan 2022Completion:
18 Jan 202231 January 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0020 | ETTOS Report Dissemination |
|
| R0012 | Housekeeping amendments to REC V2 |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Consumer, I want my Energy Supplier to receive and act upon energy theft tip-offs, to ensure the safety and security of my energy supply.
- As an ETTOS Recipient, I need to be aware of changes to the way I will receive and send tip-off information, so I can engage in the process and plan any required changes to my processes.
- As an ETTOS Recipient, I need to receive my ETTOS Service Data in a timely manner, so that I am able to act on tip-offs, to reduce risks for consumers and my business.
Invalid Requests for Site Technical Details
ANALYSIS AND ENGAGEMENT WITH BSC
Start:
01 Nov 2022Due:
30 Nov 2022Completion:
30 Nov 2022PRESENT UPDATED CHANGE PROPOSAL PLAN TO CHANGE PANEL
Start:
22 Nov 2021Due:
01 Nov 2022Completion:
01 Nov 2022Part Impact Assessment Issued
Start:
30 Nov 2022Due:
13 Jan 2023Completion:
13 Jan 2023Party Impact Assessment Closes
Start:
13 Jan 2023Due:
03 Feb 2023Completion:
03 Feb 2023Present Updated Plan to Change Panel
Start:
03 Feb 2023Due:
07 Feb 2023Completion:
07 Feb 2023Preliminary Change Report issued
Start:
07 Feb 2023Due:
31 Mar 2023Completion:
31 Mar 2023Metering Expert Panel approval of PCR
Start:
31 Mar 2023Due:
12 Apr 2023Completion:
12 Apr 2023Consultation start date (aligned with BSC)
Start:
12 Apr 2023Due:
14 Apr 2023Completion:
14 Apr 2023Consultation end date (aligned with BSC)
Start:
14 Apr 2023Due:
08 May 2023Completion:
08 May 2023Final Change Report issued
Start:
08 May 2023Due:
26 May 2023Completion:
26 May 2023Metering Expert Panel decision
Start:
26 May 2023Due:
07 Jun 2023Completion:
07 Jun 202303 November 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0110 | A review of Supplier access to data on GES | |
| R0138 | Combined progression of Change Proposals R0058, R0104 and R0129 | |
| R0140 | Housekeeping amendments | |
| R0059 | Maintenance of Qualification Schedule Change |
|
| R0088 | Make Shipper NExA values available on the GES portal | |
| R0017 | Invalid Requests for Site Technical Details |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Consumer I want my existing or new meter to be read regularly to ensure I receive accurate bills.
- As a Distribution Network Operator I want to receive appropriate Requests for Site Technical Details. As a Distribution Network Operator I want the difference between my obligations and best practice to be clear in relation to provision of Site Technical Details for sites with and without Measurement Transformers.
- As a Metering Equipment Manager I want to be provided with Site Technical Details for all relevant sites so I can correctly install, commission and maintain the Metering Equipment.
Resolution of Bilateral Erroneous Transfers
Solution Analysis
Start:
18 Nov 2021Due:
21 Mar 2023Completion:
Proposed Approach Presented To Change Panel
Start:
21 Mar 2023Due:
18 Apr 2023Completion:
- As a Consumer, I want issues affecting me or my energy account to be resolved at the earliest opportunity, to minimise impacts to my energy switch or accurate and timely billing.
- As a Consumer, I want industry parties to share my personal data securely so that my data is protected.
- As an Energy Supplier, I want to be able to resolve Bilateral Erroneous Transfers effectively and efficiently, so that I can bill my Consumers accurately and timely.
- As an Energy Supplier, I want to be able to resolve Bilateral Erroneous Transfers effectively and efficiently, so that I supply Consumers with whom I have a valid contract.
Remote communication obligations for electricity Advanced Meters
Initial Assessment Report published
Start:
17 Nov 2021Due:
21 Dec 2021Completion:
21 Dec 2021Analysis and Solution development activity
Start:
21 Dec 2021Due:
27 Feb 2022Completion:
25 Feb 2022Party Impact Assessment completion
Start:
27 Feb 2022Due:
21 Mar 2022Completion:
21 Mar 2022Preliminary Change Report issued
Start:
07 Apr 2022Due:
27 May 2022Completion:
27 May 2022Consultation starts
Start:
27 May 2022Due:
10 Jun 2022Completion:
10 Jun 2022Consultation ends
Start:
10 Jun 2022Due:
01 Jul 2022Completion:
01 Jul 2022Final Change Report issued
Start:
01 Jul 2022Due:
29 Jul 2022Completion:
28 Jul 2022Metering Expert Panel decision
Start:
29 Jul 2022Due:
10 Aug 2022Completion:
10 Aug 2022Service Provider Impact Assessment issued
Start:
21 Mar 2022Due:
07 Apr 2022Completion:
07 Apr 2022Send back solution refinement completed
Start:
10 Aug 2022Due:
13 Jan 2023Completion:
13 Jan 2023Consultation issued
Start:
13 Jan 2023Due:
20 Jan 2023Completion:
20 Jan 2023Update provided to Change Panel
Start:
20 Jan 2023Due:
07 Feb 2023Completion:
07 Feb 2023Final Change Report issued
Start:
07 Feb 2023Due:
14 Feb 2023Completion:
14 Feb 2023Responsible Committee decision
Start:
14 Feb 2023Due:
21 Feb 2023Completion:
21 Feb 2023Authority Determination requested
Start:
21 Feb 2023Due:
28 Feb 2023Completion:
24 Mar 202330 June 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0101 | Revision of the Implementation Date and approved solution for R0021 |
|
| R0102 | Revision of the approved solution for R0032 |
|
| R0114 | Housekeeping amendments |
|
| R0015 | Remote communication obligations for electricity Advanced Meters |
|
| R0010 | New Meter Types for Auxiliary Proportional Controllers (APCs) |
|
| R0011 | Reporting of Additional EMR Backing Data to Suppliers |
|
| R0021 | Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier |
|
| R0030 | Erroneous Transfer Cancellations |
|
| R0066 | Inclusion of SMRS Data Items in EES (BSC CP1568 Consequential Change) | |
| R0032 | New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS) |
|
| R0090 | Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As an electricity consumer with an Advanced Meter, I want my usage data to be accessed remotely from my meter, to reduce the need for on-site visits and ensure that I receive timely and accurate bills.
- As the Market-wide Half Hourly Settlement (MHHS) Programme I want to see an effective, early migration of NHH settled Advanced Meters to HH settled, to reduce the risk of missed migration deadlines and ensuring sufficient time to resolve ‘problem’ sites ahead of the MHHS migration deadline.
- As an Energy Supplier I want to obtain usage remotely, reducing the need for on-site metering reading activity, enabling me to settle and bill accurately. As a Metering Equipment Manager (MEM), I need to understand any changes to obligations that may impact my business, so I can engage in the change process and plan any required changes to my systems, processes and organisation.
Housekeeping amendments to REC V2
Initial Assessment Report published
Start:
04 Oct 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Preliminary Change Report issued
Start:
19 Oct 2021Due:
22 Oct 2021Completion:
22 Oct 2021Change Panel review
Start:
22 Oct 2021Due:
16 Nov 2021Completion:
16 Nov 2021Consultation starts
Start:
16 Nov 2021Due:
17 Nov 2021Completion:
17 Nov 2021Consultation ends
Start:
17 Nov 2021Due:
08 Dec 2021Completion:
08 Dec 2021Final Change Report issued
Start:
08 Dec 2021Due:
10 Dec 2021Completion:
10 Dec 2021Change Panel decision
Start:
10 Dec 2021Due:
21 Dec 2021Completion:
21 Dec 202131 January 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0020 | ETTOS Report Dissemination |
|
| R0012 | Housekeeping amendments to REC V2 |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As an Energy Consumer, I need Energy Companies to operate consistent processes, to ensure my energy supply is managed efficiently and to retain my trust in the functioning of the energy market.
- As a REC Party, I need the REC to provide a consistent baseline, so I can operate in an interoperable way with other Market Participants.
Reporting of Additional EMR Backing Data to Suppliers
Initial Assessment Report published
Start:
08 Sep 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Preliminary Change Report issued
Start:
19 Oct 2021Due:
12 Nov 2021Completion:
12 Nov 2021Technical Expert Panel review
Start:
12 Nov 2021Due:
24 Nov 2021Completion:
24 Nov 2021Consultation starts
Start:
24 Nov 2021Due:
30 Nov 2021Completion:
29 Nov 2021Consultation ends
Start:
30 Nov 2021Due:
21 Dec 2021Completion:
21 Jan 2022Final Change Report issued
Start:
21 Dec 2021Due:
14 Jan 2022Completion:
14 Jan 2022Technical Expert Panel decision
Start:
14 Jan 2022Due:
26 Jan 2022Completion:
26 Jan 202230 June 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0101 | Revision of the Implementation Date and approved solution for R0021 |
|
| R0102 | Revision of the approved solution for R0032 |
|
| R0114 | Housekeeping amendments |
|
| R0015 | Remote communication obligations for electricity Advanced Meters |
|
| R0010 | New Meter Types for Auxiliary Proportional Controllers (APCs) |
|
| R0011 | Reporting of Additional EMR Backing Data to Suppliers |
|
| R0021 | Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier |
|
| R0030 | Erroneous Transfer Cancellations |
|
| R0066 | Inclusion of SMRS Data Items in EES (BSC CP1568 Consequential Change) | |
| R0032 | New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS) |
|
| R0090 | Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Market Participant, I need to be able to validate EMRS invoices and credits without having to request additional supporting data.
- As EMR Settlement Ltd, I need to have an efficient mechanism in place that enables me to provide Market Participants with all the relevant data that they need to validate their invoices and credit notes, to reduce/remove the need for Market Participants to contact the service desk for additional information.
Introduction of SDEP and EES User Maintenance API
Initial Assessment Report published
Start:
08 Sep 2021Due:
25 Oct 2021Completion:
25 Oct 2021Analysis and Solution Development activity
Start:
25 Oct 2021Due:
15 Feb 2022Completion:
15 Feb 2022Service Provider Impact Assessment completion
Start:
15 Feb 2022Due:
04 Apr 2022Completion:
04 Apr 2022Preliminary Change Report issued
Start:
13 May 2022Due:
16 Dec 2022Completion:
16 Dec 2022Technical Expert Panel review
Start:
16 Dec 2022Due:
21 Dec 2022Completion:
21 Dec 2022Consultation Starts
Start:
21 Dec 2022Due:
23 Dec 2022Completion:
23 Dec 2022Consultation Ends
Start:
23 Dec 2022Due:
27 Jan 2023Completion:
27 Jan 2023Final Change Report issued
Start:
27 Jan 2023Due:
10 Feb 2023Completion:
10 Feb 2023Appeal Window Closure
Start:
22 Feb 2023Due:
15 Mar 2023Completion:
15 Mar 2023Party Impact Assessment Issued
Start:
04 Apr 2022Due:
13 May 2022Completion:
13 May 2022Technical Expert Panel review
Start:
10 Feb 2023Due:
22 Feb 2023Completion:
22 Feb 2023- As a consumer, I want to ensure the data held by my supplier and other industry parties is correct so that I receive accurate and timely bills so that I understand what I need to pay and by when with no surprises.
- As a consumer, I want to be able to switch my energy supply without experiencing significant delays whilst my new and old supplier resolve any issues. So that I can see the benefits of switching at the earliest opportunity.
- As an SDEP User, I want to be able to automate processes that use the SDEP, so I can meet my obligations as efficiently and effectively as possible. As an EES or SDES User, I want to be able to automate certain user maintenance requests, so I can manage user maintenance activities as efficiently as possible.
Changes to message ownership in SDEP
Initial Assessment Report published
Start:
08 Sep 2021Due:
25 Oct 2021Completion:
25 Oct 2021Change Panel review
Start:
25 Oct 2021Due:
02 Nov 2021Completion:
02 Nov 2021Analysis and Solution Development activity
Start:
02 Nov 2021Due:
21 Dec 2021Completion:
Service Provider Impact Assessment completion
Start:
21 Dec 2021Due:
02 Feb 2022Completion:
REC Party Impact Assessment completion
Start:
02 Feb 2022Due:
18 Mar 2022Completion:
Preliminary Change Report issued
Start:
18 Mar 2022Due:
16 May 2022Completion:
Technical Expert Panel review
Start:
15 Jul 2022Due:
27 Jul 2022Completion:
Consultation Starts
Start:
16 May 2022Due:
26 May 2022Completion:
Consultation ends
Start:
26 May 2022Due:
20 Jun 2022Completion:
Final Change Report issued
Start:
20 Jun 2022Due:
15 Jul 2022Completion:
Technical Expert Panel decision
Start:
27 Jul 2022Due:
27 Jul 2022Completion:
Appeal Window Closure
Start:
27 Jul 2022Due:
17 Aug 2022Completion:
- As a consumer, I want issues affecting me or my energy account to be resolved at the earliest opportunity, to minimise impacts to my energy switch or accurate and timely billing.
- As a SDEP Authorised Person with the responsibility for message allocation, I want to efficiently assign multiple messages in one transaction to an Authorised Person, to remove the need to manual assign them one by one.
- As a SDEP Authorised Person with the responsibility for message allocation, I want to be able to filter messages to identify messages requiring action. This will ensure messages are picked up promptly and resolved within the agreed Service Level Agreement (SLA).