Evolution of the CRS Performance Charge
Date of latest update
Type
Change
ID
R0210
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented on 28 February 2025.
Summary
R0025 established a new performance charge for DCC, which linked its performance against its Service Definition with financial incentives. During the R0025 PAB members noted the need to further develop the methodology, including reviewing it periodically. The RPA has worked with the PAB to develop proposals to enhance the performance charge.
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
28 February 2025
| Included changes | Affected REC Items | |
|---|---|---|
| R0168 | Clarify & Strengthen CRS Providers Requirements |
|
| R0208 | Adding the DIP Rules to the Cross Code Steering Group Terms of Reference | |
| R0210 | Evolution of the CRS Performance Charge | |
| R0239 | Housekeeping February 2025 |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Proposed Solution - Draft Schedule 6 - Performance Assurance
Upload document
R0210 Solution - Draft Schedule 6 V2.4 - 24.09.24.docx
Archive
Off
Document title
R0210 - Legal text for consultation 17.10.24
Upload document
R0210 - Legal text for consultation (1).pdf
Archive
Off
Document title
R0210 - Legal Text - Post-Consultation 18.11.24
Upload document
R0210 Legal Text - 07.11 Amendments Post DCC.pdf
Archive
Off
Stages Selection
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
RECPAB_24_0625_05 - Evolution of CRS Performance Charge.docx
CP form
R0210 Change Report V1.0 01.10.24
R0210 Consolidated Consultation Responses
R0210 Change Report (for Consultation)
R0210 Change Report (Pre-Vote) V1.0 18.11.24
R0210 Change Report (Post-Vote) V1.0 26.11.24
Company Name
REC Code Manager
Review status
Review required
Implementation of Market-wide Half Hourly Settlement (MHHS) Arrangements
Date of latest update
Type
Change
ID
R0209
Change Category
Other Industry Codes impacted
Urgent
No
Latest Update
22/09/25 - This Change Proposal has been implemented as part of the MHHS M8 22 September 2025 REC Release.
Summary
This Authority Change Proposal was raised by Ofgem pursuant to the Electricity Settlement Reform SCR. It will ensure that the appropriate obligations, processes and provisions for the new MHHS arrangements, which have been developed and consulted on as part of the MHHS Programme, are introduced into the REC.
Change Plan
Proposal Plan approved
Completed
Start:
05 Sep 2024Due:
17 Sep 2024Completion:
17 Sep 2024Consultation published
Completed
Start:
17 Sep 2024Due:
18 Sep 2024Completion:
18 Sep 2024Consultation closed
In Progress
Start:
18 Sep 2024Due:
09 Oct 2024Completion:
Final Recommendation Vote
Not Started
Start:
09 Oct 2024Due:
05 Nov 2024Completion:
Issued for Authority Determination
Not Started
Start:
05 Nov 2024Due:
07 Nov 2024Completion:
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
MHHS Programme Milestone M8 (Code changes delivered)
| Included changes | Affected REC Items | |
|---|---|---|
| R0044 | MHHS Programme Changes required to Central Switching Service |
|
| R0173 | Improvements to the Theft Detection Incentive Scheme (TDIS) |
|
| R0209 | Implementation of Market-wide Half Hourly Settlement (MHHS) Arrangements |
|
| R0222 | ESME ID Update Rejections | |
| R0223 | Reconciliation of Unallocatable Transactions Review |
|
| R0241 | MHHS Incremental Changes for go live |
|
| R0259 | Update to R0173 Implementation Date | |
| R0264 | Data Specification Housekeeping | |
| R0083 | Changes to Supply Number Format for MHHS | |
| R0097 | Consequential Change for CSS Smart Meter Data Retriever Appointments |
|
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
EMDS HTML vMHHS 1.2
Upload document
EMDS vMHHS 1.2.zip
Archive
Off
Document title
I0241 MHHS Incremental Changes for go live
Archive
Off
Document title
R0209 - Solution Development Report 24.10.2024
Upload document
R0209 - Solution Development Report 24.10.24.pdf
Archive
Off
Document title
R0209 - Legal Text 24.10.2024
Upload document
R0209 - Legal Text 24.10.24.zip
Archive
Off
Document title
R0209 - Solution Development Report 10.09.24
Upload document
R0209 - Solution Development Report 10.09.24.pdf
Archive
Off
Document title
R0209 - Legal Text 100924
Upload document
R0209 - Legal Text 100924.zip
Archive
Off
Document title
Finalisation of code artefacts - MHHS programme
Archive
Off
Problem Statement
Changes are required to the REC, to ensure that the appropriate obligations, processes and provisions are defined within the REC at MHHS go-live, to enable the successful transition to the enduring governance and operational arrangements developed as part of the MHHS Programme.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
R0209 - Downloadable Submission Form
Authority Led SCR REC Change Proposal on the MHHS arrangements - letter to REC Panel Chair.pdf
R0209 Change Report (Consultation) v2.0 18.09.2024.pdf
R0209 Consolidated Consultation Responses v1.0 24.10.2024
R0209 Change Report (Post-Vote) v2.0 05.11.2024
R0209 Implementation of MHHS Arrangements approval letter 26112024
Company Name
Ofgem
Review status
Review required
CSS Retry Strategy
Date of latest update
Type
Change
ID
R0203
Change Category
Change Path
Priority
Urgent
No
Latest Update
08/11/2024 - This Change Proposal has been implemented as part of the November 2024 REC Release.
Summary
There is currently a mismatch within the Central Switching Service (CSS) system functionality and the legal text within the REC Switching Data Management Schedule. Within the schedule the retry strategy is defined as “retry sending the Market Message at intervals of 10 seconds, 20 seconds and 30 seconds from each attempt to send the Market Message. If these retry Market Messages also fail, then the Market Message shall be retried at intervals of one hour up to a maximum of 12 hours; after which delivery of the Market Message shall be abandoned and a Switching Incident raised in accordance with the Switching Service Management Schedule”. However, in response to an incident in 2022, the CSS Provider updated the retry strategy. This change seeks to amend the legal text in Section 2.4 of the Switching Data Management Schedule to reflect the retry strategy which is currently in operation in the CSS system.
Change Plan
Change Proposal Plan
Completed
Start:
15 Aug 2024Due:
17 Sep 2024Completion:
17 Sep 2024Consultation to be issued
Completed
Start:
17 Sep 2024Due:
20 Sep 2024Completion:
20 Sep 2024Consultation to close
Completed
Start:
20 Sep 2024Due:
04 Oct 2024Completion:
04 Oct 2024Final Recommendation Vote
Completed
Start:
04 Oct 2024Due:
15 Oct 2024Completion:
15 Oct 2024Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
08 November 2024
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- The Switching Data Management Schedule Section 2.4 should be updated to reflect the current retry strategy: 1. a short interval retry sequence of 3 attempts at 20 second intervals 2. a long interval retry sequence of 12 attempts at 1 hour intervals. The CSS Provider has confirmed that there is now a process in place that would prevent any future updates to the retry strategy without a change request being raised in the first instance.
Proposed Solution Document
Document title
CSS Retry Strategy Redlining
Upload document
Switching Data Management v1.2 CSS Retry Strategy Redlining.doc
Archive
Off
Problem Statement
The CSS system is currently out of sync with the REC legal drafting for the retry strategy.
Stages Selection
Switching Data Management v1.2 CSS Retry Strategy Redlining.doc
R0203 - Change Proposal Form
R0203 - Change Report (Consultation) 17.09.2024
R0203 - Non-Confidential Consolidated Consultation Responses V1.0 (03.10.2024)
R0203 - Change Report (Final Recommendation - Approved) 15.10.2024
Company Name
REC Technical Services
Review status
Review required
Review of the REC's Address Management Service
Date of latest update
Type
Issue
ID
I0200
Change Category
Change Path
Priority
Urgent
No
Latest Update
The Change Report (Update to Plan) has been published and is now open for comments until 23:59, 16 November 2026.
Summary
Having the incorrect address can lead to a range of Consumer issues, including switching, billing and meter reading problems. The Meter Point Location (MPL) and Retail Energy Location (REL) have been added to the Code to resolve this issue. Whilst there had been progress resolving address data issues, there is not currently a mechanism to establish Code level targets for address improvement, resulting in around 2.8 million unmatched addresses.
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
There has been progress resolving address data issues, but there is no mechanism to clearly establish Code level targets for address improvement, or overall market performance.
Stages Selection
Stages Selection
Workgroup
I0200 - Improving Address Management Targets (Issue Form)
I0200 - Change Issues Group paper
I0200 - Change Report (Proposal Plan) V1.1 (Approved) 18.02.2025
I0200 - Update to Plan (Pre Approval) 14.04.2026
I0200 Change Report (Update to Plan) V1.0 Approved 17.11.26
Company Name
REC Code Manager
Review status
Review required
Introducing a Process to Provide Updates During Fault Resolutions
Date of latest update
Type
Issue
ID
I0197
Change Category
Priority
Urgent
No
Latest Update
10/06/2026 - The Code Manager, following an approval to an Update to Plan by the REC Metering Expert Panel, has placed I0197 on hold.
Summary
Some customers have had faulty meters for a prolonged period, which impacts billing and settlement, and can prevent customers accessing specific tariffs. Currently the REC only has obligations relating to electricity meter faults, and these do not actually require work to be done to address faults. This issues proposes the introduction a maximum timeframe Fault Resolution deadline to resolve issues around faulty meters.
Change Report - Initial Assessment and Change Plan Report
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
Consumers have had faulty meters for a prolonged period, which impacts billing and settlement, and can prevent customers accessing specific tariffs.
Stages Selection
Stages Selection
SME
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
I0197 - Change Proposal Form
I0197 - Change Report (Proposal Plan) V1.0 (Approved) 03.06.2025
I0197 - Update to Plan V3.0 (On Hold) 03.06.2026
Company Name
-
Review status
Review required
Voice of the Consumer
Date of latest update
Type
Issue
ID
I0189
Change Category
Priority
Urgent
No
Latest Update
25/02/2026 - an Issue Closure Report has been published and this Issue moved to resolved.
Summary
There is currently a gap in the understanding of the effectiveness of the retail systems and processes in delivering positive outcomes for Consumers. While Consumer surveys are conducted on certain areas to some aspects of Consumer satisfaction, it may be necessary to expand the evaluation methods used by the Code Manager to gain a more comprehensive understanding.
Change Plan
Working Group 1
Completed
Start:
Due:
Completion:
12 Dec 2024Working Group 2
Completed
Start:
Due:
Completion:
10 Feb 2025Working Group 3
Completed
Start:
Due:
Completion:
18 Mar 2025Working Group 4
Completed
Start:
Due:
Completion:
30 Apr 2025Extension to Plan approved by Change Panel
Completed
Start:
Due:
Completion:
20 May 2025Working Group 5
Completed
Start:
Due:
Completion:
12 Jun 2025Working Group 6
Completed
Start:
Due:
Completion:
28 Jul 2025Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0189 proposed legal text - draft 1
Upload document
I0189 proposed legal text - draft 1.zip
Archive
Off
Problem Statement
RECCo’s mission is to facilitate the efficient and effective running of the retail energy market, including its systems and processes through promoting innovation, competition, and delivering positive Consumer outcomes. However, the Code Manager receives limited feedback directly from Consumers to determine if this mission is being fulfilled.
Stages Selection
Stages Selection
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0189- Voice of the Consumer
I0189 Change Report (Proposal Plan) v1.0 20.11.2024
I0189 Extension to Plan V1.0 Approved 20.05.2025
I0189 Extension to Plan V2.0 Approved 23.09.2025
I0189 Issue Closure Report V1.1
Company Name
Code Administrator
Review status
Review required
Schedule 8 Review and Best Practice Guidance Development
Date of latest update
Type
Issue
ID
I0187
Change Category
Change Path
Priority
Urgent
No
Latest Update
18/11/2026 The REC Change Panel has approved the Update to Plan as part of the Bulk Update presented at their meeting on 17/11/2026
Summary
Schedule 8 - Unbilled Energy Code of Practice has not been reviewed since its development for REC go-live. This Issue seeks to understand if there are any conflicts in the Schedule with best practice and identify any gaps or duplication. Alongside this, a best practice guidance document will be developed which is relevant, complete and aligned to current processes and obligations.
Change Plan
Proposal Plan Approved at Change Panel
Completed
Start:
26 Sep 2024Due:
31 Mar 2027Completion:
21 Jan 2025Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
Schedule 8 - Unbilled Energy Code of Practice has not been reviewed since its development for REC go-live. The Schedule needs to be reviewed to ensure it is up to date, understand if there are any conflicts with best practice and identify any gaps or duplication.
Stages Selection
Stages Selection
Workgroup
Workgroup(s)
I0187 - Change Proposal Form
I0187 - Change Report (Proposal Plan) V1.0 (Approved) 21.01.2025
I0187 - Change Report (Extension to Plan) Approved 17.06.2025
I0187 - Change Report (Extension to Plan) 02.09.2025
I0187 - Change Report (Extension to Plan) 13.01.2025 (Pre-Approval)
I0187 - Change Report (Extension to Plan) V1.0 Approved 25.06.2026
I0187 - Change Report (Extension to Plan) 13.01.2025
I0187 - Change Report (Extension to Plan) V5.0 (Approved)
Company Name
Code Manager
Review status
Review required
Levelisation Reconciliation Electricity Single-rate/Multi-register Split
Date of latest update
Type
Change
ID
R0182
Change Category
Priority
Urgent
Yes
Latest Update
18/11/24 - The Authority has approved R0182 for Implementation. R0182 will now be targeted for an extraordinary release on 08/12/24.
Summary
This Change Proposal seeks to introduce the necessary governance and charging amendments to existing Payment Method Levelisation (PML) Reconciliation arrangements (introduced in R0147) to allow for multi-register reconciliation. The amendments will allow for an ongoing reconciliation that accounts for split in both single-rate and multi-register Metering Assets. Additionally, it will also allow for a one-off retrospective recalculation for the period dating from the proposed effective implementation date of 01 January 2025 back to the implementation of the original reconciliation mechanism on 01 April 2024.
Change Plan
Party Impact Assessment
Completed
Start:
20 Jun 2024Due:
09 Aug 2024Completion:
09 Aug 2024Consultation
Completed
Start:
09 Aug 2024Due:
20 Sep 2024Completion:
20 Sep 2024Responsible Committee Decision
Completed
Start:
20 Sep 2024Due:
15 Oct 2024Completion:
15 Oct 2024Authority Determination Sent
Completed
Start:
15 Oct 2024Due:
16 Oct 2024Completion:
16 Oct 2024Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- N/A – No identifiable Consumer impact.
- M1 - As a Domestic Supplier, I want my PML Reconciliation payments to be as reflective of my portfolio as possible, by differentiating between single rate and multi register Metering Assets, so that my engagement with the reconciliation is as accurate as possible. M2 - As a Domestic Supplier, I want my PML Reconciliation obligations regarding the retrospective recalculation to be well defined within the REC, so that I am able to engage as efficiently as possible. M3 - As RECCo, I want the PML Reconciliation mechanism to be reflective of REC Parties true costs (based on their single-rate vs multi-register split in their portfolio), so that I am able to deliver the most optimised outcome for PML Reconciliation participants.
Proposed Solution Document
Document title
R0182 Solution & Legal Text 08.10.24
Upload document
R0182 Solution and legal text 08.10.14.zip
Archive
Off
Document title
R0182 Solution & Legal Text 08.10.24
Upload document
R0182 Solution and legal text 08.10.14 (1).zip
Archive
Off
Problem Statement
PML Reconciliation currently does not distinguish between single-rate and multi-register electricity Metering Assets. This represents a discrepancy, as Price Cap methodology currently does make this distinction. As a result, PML Reconciliation calculation methodology must be updated to distinguish between single-rate and multi-register Metering Assets. This will be effective for all reconciliations going forward from the date of implementation, as well as retrospectively from the start of the PML Reconciliation in April 2024, to the date of implementation.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
R0182 - CP Form
Consolidated Consultation Responses
Ofgem Letter on Upcoming PPM Levelisation Single and Multi-Metering Arrangements RFI
R0182 Change Proposal Plan (Approved) V1.0 16.07.24
R0182 Initial Assessment Report V1.0 (Approved) 16.07.24
R0182 Consolidated Impact Assessment Responses V1.0 30.08.24
R0182 Change Report (Post-Vote) V3.0 15.10.24
Authority Decision on REC Modification Proposal R0182
Company Name
RECCo
Review status
Review required
DPI Extract from CSS
Date of latest update
Type
Change
ID
R0183
Change Category
Change Path
Priority
Urgent
No
Latest Update
11/03/2025 - The proposer has withdrawn the request due to the expected delivery of enquiry data in the same anticipated timescales & the continued pursuance of I0224. The adoption window has closed.
Summary
It has emerged that there are data quality issues relating to the Domestic Premises Indicator (DPI) Data Item, where MPxNs have been recorded as having the wrong DPI. This Change has been raised to identify a mechanism by which this issue can be resolved.
Change Plan
Solution Analysis and Development
In Progress
Start:
11 Jun 2024Due:
20 Sep 2024Completion:
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- C1 - As a Consumer, I want industry data relating to my energy supply to be accurate, so that I do not experience any issues when switching or engaging with other consumer facing industry practices.
- M1 - As a CSS User, I want available DPI data to be accurate, so that when I engage with industry processes that require DPI data, I am confident that I am engaging with the right information. M2 - As the CSS, I want to provide accurate data to CSS Users, so that I am able to facilitate successful industry operations for my Users.
Problem Statement
Inaccurate DPI data available within industry data sources can result in less accuracy within REC processes that utilise this data, and poorer consumer outcomes. DPI data accuracy needs to be improved to ensure that industry processes and Consumers are not impacted.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
Change Proposal Form
R0183 Change Report V3.0 02.12.2024
Company Name
-
Review status
Review required
Schedule 14 - Metering Operations Footnote Review
Date of latest update
Type
Change
ID
R0181
Change Category
Change Path
Priority
Urgent
No
Latest Update
23/08/2024 - This change was successfully implemented as part of the August 2024 Extraordinary REC Release on 23 August 2024.
Summary
The footnotes within Schedule 14 - Metering Operations are not in the correct place, are missing or no longer relevant. This Change Proposal looks to correct issues within the footnotes and move them into the legal text to prevent this from happening when future Change Proposals impacting this schedule are implemented.
Change Plan
Change Proposal Plan and Impact Assessment Report issued
Completed
Start:
06 Jun 2024Due:
18 Jun 2024Completion:
18 Jun 2024Preliminary Change Report issued
Completed
Start:
18 Jun 2024Due:
19 Jun 2024Completion:
19 Jun 2024Consultation issued
Completed
Start:
19 Jun 2024Due:
19 Jun 2024Completion:
19 Jun 2024Consultation Close
Completed
Start:
19 Jun 2024Due:
10 Jul 2024Completion:
10 Jul 2024Final Change Report Issued
Completed
Start:
10 Jul 2024Due:
11 Jul 2024Completion:
11 Jul 2024Responsible Committee Decision
Completed
Start:
11 Jul 2024Due:
19 Jul 2024Completion:
19 Jul 2024Appeal Window Closure
Not Started
Start:
19 Jul 2024Due:
02 Aug 2024Completion:
Status
Implementation Date
23 August 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0121 | SDEP Review Improvements (1) - Process Types |
|
| R0146 | Data Specification Update for Refresh Functionality | |
| R0164 | Removing the Enumerations from Communications Method Data Item (J0386) to align with BSC CP 1594 | |
| R0166 | Removal of the Green Deal Panel | |
| R0181 | Schedule 14 - Metering Operations Footnote Review |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Metering Operations v4.1 footnote review legal drafting for PCR
Upload document
Metering Operations v4.1 footnote review - PCR.docx
Archive
Off
Document title
Metering Operations v4.1 footnote review legal drafting for FCR
Upload document
Metering Operations v4.1 footnote review - FCR (2).docx
Archive
Off
Problem Statement
REC parties are unable to ensure their processes and procedures correctly reflect their obligations as the footnotes within Schedule 14 - Metering Operations are not in the correct place, are missing or no longer relevant.
Stages Selection
R0181 Change Proposal Plan (Approved) 18.06.2024
R0181 Initial Assessment Report (Approved) 18.06.2024
R0181 Preliminary Change Report
Consolidated Consultation Responses
R0181 Final Change Report - approved 22.07.24
Company Name
Code Manager
Review status
Review required