Provision of Grid Supply Point Group ID from a Postcode search in EES
Enabling Electricity Enquiry Service searches using a Unique Property Reference Number
Service Provider Impact Assessment window start
Start:
19 Apr 2023Due:
02 Oct 2023Completion:
02 Oct 2023Service Provider Impact Assessment window close
Start:
02 Oct 2023Due:
18 Dec 2023Completion:
18 Dec 2023Party Impact Assessment start
Start:
18 Dec 2023Due:
12 Jan 2024Completion:
12 Jan 2024Preliminary Change Report and Consultation issued
Start:
02 Feb 2024Due:
16 Feb 2024Completion:
16 Feb 2024Party Impact Assessment close
Start:
12 Jan 2024Due:
02 Feb 2024Completion:
02 Feb 2024Consultation close
Start:
16 Feb 2024Due:
08 Mar 2024Completion:
08 Mar 2024Final Change Report issued
Start:
08 Mar 2024Due:
15 Mar 2024Completion:
15 Mar 2024Responsible Committee decision
Start:
15 Mar 2024Due:
27 Mar 2024Completion:
27 Mar 2024Appeal window closure
Start:
27 Mar 2024Due:
12 Apr 2024Completion:
12 Apr 202408 November 2024
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Consumer, I want to be able to switch my electricity easily and efficiently.
- As I Consumer, I want to be able to quote or switch my electricity as part of a packaged search.
- As a Supplier, I want Consumers to be able to search for quotes and switch efficiently.
- As an organisation providing multi-channel switching services, I want Consumers to be able to use one set of data when requesting quotes.
Revision of the approved solution for R0032
Solution Analysis and Development
Start:
23 Mar 2023Due:
31 Mar 2023Completion:
31 Mar 2023Service Provider Impact Assessment Complete
Start:
31 Mar 2023Due:
11 Apr 2023Completion:
11 Apr 2023Party Impact Assessment Completed
Start:
11 Apr 2023Due:
11 Apr 2023Completion:
11 Apr 2023Preliminary Change Report Published for Consultation
Start:
11 Apr 2023Due:
14 Apr 2023Completion:
14 Apr 2023Consultation Start
Start:
14 Apr 2023Due:
14 Apr 2023Completion:
14 Apr 2023Consultation End
Start:
14 Apr 2023Due:
21 Apr 2023Completion:
21 Apr 2023Final Change Report Published
Start:
21 Apr 2023Due:
24 Apr 2023Completion:
24 Apr 2023Responsible Committee Discussion
Start:
24 Apr 2023Due:
26 Apr 2023Completion:
Appeal Window Closure
Start:
26 Apr 2023Due:
12 May 2023Completion:
30 June 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0101 | Revision of the Implementation Date and approved solution for R0021 |
|
| R0102 | Revision of the approved solution for R0032 |
|
| R0114 | Housekeeping amendments |
|
| R0015 | Remote communication obligations for electricity Advanced Meters |
|
| R0010 | New Meter Types for Auxiliary Proportional Controllers (APCs) |
|
| R0011 | Reporting of Additional EMR Backing Data to Suppliers |
|
| R0021 | Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier |
|
| R0030 | Erroneous Transfer Cancellations |
|
| R0066 | Inclusion of SMRS Data Items in EES (BSC CP1568 Consequential Change) | |
| R0032 | New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS) |
|
| R0090 | Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As an impacted Market Participant, I want to have clarity on version of the Market Message and the population of Data Items within the Data Specification, so that my internal systems can be correctly configured to send and receive Data Items within Market Messages.
Optional fuzzy searching in EES
Service Provider Impact Assessment window start
Start:
07 Mar 2023Due:
09 Oct 2023Completion:
09 Oct 2023Service Provider Impact Assessment window close
Start:
09 Oct 2023Due:
27 Dec 2023Completion:
24 Nov 2024Party Impact Assessment start
Start:
27 Dec 2023Due:
12 Jan 2024Completion:
12 Jan 2024Party Impact Assessment close
Start:
12 Jan 2024Due:
02 Feb 2024Completion:
02 Feb 2024Preliminary Change Report and Consultation issued
Start:
02 Feb 2024Due:
16 Feb 2024Completion:
16 Feb 2024Consultation close
Start:
16 Feb 2024Due:
08 Mar 2024Completion:
08 Mar 2024Final Change Report issued
Start:
08 Mar 2024Due:
15 Mar 2024Completion:
15 Mar 2024Responsible Committee decision
Start:
15 Mar 2024Due:
27 Mar 2024Completion:
27 Mar 2024Appeal window closure
Start:
27 Mar 2024Due:
12 Apr 2024Completion:
12 Apr 202408 November 2024
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Consumer, I want to be able to switch my electricity easily and efficiently.
- As an organisation providing switching services, I want Consumers to be able to search addresses efficiently.
ERDS Upload File in the Data Specification and clarification of cancellation code
Formalising the Submission of PPMIP Unallocated Transaction Report (UTR) Files
Solution analysis and development
Start:
28 Nov 2022Due:
12 Jan 2024Completion:
11 Jan 2024Service Provider Impact Assessment start date
Start:
12 Jan 2024Due:
15 Jan 2024Completion:
15 Jan 2024Service Provider Impact Assessment close
Start:
15 Jan 2024Due:
11 Mar 2024Completion:
11 Mar 2024- As a PPMIP, I want to have clear guidance on how and when I should submit my Unallocated Transaction Report files.
- As a Supplier, I want to receive accurate Unallocated Transactions in relation to prepayment meters that are not smart meters.
- As the Code Manager, I want visibility of the Unallocated Transaction Report.
- As the EES Provider, I want to be able to efficiently upload the Unallocated Transaction Reports.
DCC access to EES and GES
Service Provider Impact Assessment Due
Start:
25 Sep 2022Due:
21 Sep 2023Completion:
Preliminary Change Report Issued
Start:
21 Sep 2023Due:
06 Oct 2023Completion:
Responsible Committee Review
Start:
06 Oct 2023Due:
17 Oct 2023Completion:
17 Oct 2023Consultation Issued
Start:
17 Oct 2023Due:
20 Oct 2023Completion:
20 Oct 2023Final Change Report Issued
Start:
20 Oct 2023Due:
10 Nov 2023Completion:
10 Nov 2023Responsible Committee Decision
Start:
10 Nov 2023Due:
21 Nov 2023Completion:
21 Nov 202323 February 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0103 | Central provision of DCC Technical Contacts for requesting test certificates |
|
| R0156 | Updates to the CSS Message Business Data Validation Rules and Physical Interface Design Specification | |
| R0071 | DCC access to EES and GES |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Consumer, I want data relating to my energy supply to be handled appropriately, so that I can have a consistent and faultless switching experience.
- As the Switching Service Desk, I want to be able to access market data that lets me resolve tickets first time, so that I can provide a more efficient service to users. As the GES Provider, I want my users to be able to access information that helps them fulfil their objectives, so that the service is used as efficiently as possible. As the EES Provider, I want my users to be able to access information that helps them fulfil their objectives, so that the service is used as efficiently as possible.
Introduction of CSS refresh functionality
Solution Analysis and Development
Start:
29 Aug 2022Due:
19 Oct 2022Completion:
19 Oct 2022Service Provider Impact Assessment
Start:
19 Oct 2022Due:
29 Mar 2023Completion:
29 Mar 2023Consultation
Start:
11 Apr 2023Due:
09 May 2023Completion:
28 Apr 2023Preliminary Change Report Issued
Start:
29 Mar 2023Due:
11 Apr 2023Completion:
05 Apr 2023Final Change Report Issued
Start:
Due:
Completion:
21 Jun 2023Responsible Committee Decision
Start:
09 May 2023Due:
28 Jun 2023Completion:
28 Jul 202306 December 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0118 | Review of Schedule 12 and processes to manage access to data |
|
| R0128 | Removal of CSS Business Rule 1177 to reflect OFAF optionality | |
| R0136 | Change to REC Schedule 22 Market Stabilisation Charge (MSC) | |
| R0149 | Updates to the EES API Interface Specification | |
| R0067 | Introduction of CSS refresh functionality |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Consumer, I want the Switching process to work successfully, so that I can switch Energy Supplier without delays or issues.
- As the CSS Provider I want the messages I send to SDSPs to be received and processed successfully, so that there is no interruption to the Switching process or the Consumers’ Switching experience. As the CSS Provider, I want the functionality to be available for SDSPs to automatically resolve issues when messages are not received in the correct order or are received after Gate Closure, so that this work does not have to be done manually.
- As an SDSP, I want to be able to detect when I have not received the expected CSS messages, so that I am able to request that the missing messages are sent to me to process. As an SDSP I want to be able to request a refresh of CSS messages when they are not received in the correct order or they are received after Gate Closure, so that I am able to maintain an accurate reflection of the current Switch status and minimise impacts on CSS Users and Consumers.
EES Access for Virtual Lead Parties
Service Provider Impact Assessment
Start:
17 Jun 2022Due:
22 Jul 2022Completion:
22 Aug 2022Preliminary Change Report Issued
Start:
22 Jul 2022Due:
02 Sep 2022Completion:
02 Sep 2022Consultation Issued
Start:
02 Sep 2022Due:
02 Sep 2022Completion:
02 Sep 2022Consultation Complete
Start:
02 Sep 2022Due:
16 Sep 2022Completion:
16 Sep 2022Final Change Report Issued
Start:
16 Sep 2022Due:
14 Oct 2022Completion:
14 Oct 2022Responsible Committee Decision
Start:
14 Oct 2022Due:
26 Oct 2022Completion:
26 Oct 202201 April 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0047 | Metering Code of Practice Consolidation Review |
|
| R0025 | Service Provider Performance Charges (DCC) |
|
| R0073 | Introduction of a Housekeeping Change Proposal Process |
|
| R0084 | Housekeeping changes to the approved legal text for R0047 |
|
| R0091 | Clarifications to the Theft Detection Incentive Scheme |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 16 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As an Energy Consumer, I want my VLP to have access to the data needed to correctly register me in a timely manner, so there aren’t delays in the delivery of my service.
- As a VLP, I want to have access to all the data I need to register my customers so I can deliver the service they have requested, without delay.
- As a VLP, I want to be able to use the EES to find the MPAN of a customer using their address information, to enable me to reliably gather this data to without delay or further engagement with my customer.
REC V3.0
Legal text baselined
Start:
10 Apr 2022Due:
13 May 2022Completion:
13 May 2022Final Change Report Issued
Start:
13 May 2022Due:
20 May 2022Completion:
20 May 2022Responsible Committee Decision
Start:
20 May 2022Due:
07 Jun 2022Completion:
07 Jun 2022Authority Determination (Original)
Start:
07 Jun 2022Due:
20 Jun 2022Completion:
17 Jun 2022Authority Determination (revoked and re-issued)
Start:
20 Jun 2022Due:
29 Jun 2022Completion:
29 Jun 202218 July 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0038 | Performance Assurance Report Catalogue Changes as a consequence of REC V3.0 | |
| R0041 | REC V3.0 |
|
| R0042 | Performance Assurance Board Terms of Reference |
|
| R0045 | Changes to SDEP Messages and Schedule numbering for REC V3.0 |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 16 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Consumer, I want to be able to successfully switch my Energy Supplier with minimal delay or hassle, so that I can start to receive the service and tariff from my chosen Energy Supplier at the earliest opportunity.
- As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the obligations, processes and provisions for the new switching arrangements, to enable the successful transition to enduring governance and operational arrangements.
- As a REC Party, I want to be clear on the obligations I need to meet and the processes I need to follow post CSS go live, to ensure my organisation is ready for the introduction of the new switching arrangements.
- As a REC Service Provider, I want to be clear on the obligations, processes and service standards that I need to meet, to ensure my organisation is ready for the introduction of the new switching arrangements.