Shared Sites in Electricity Enquiry Service (EES)

Date of latest update
Type
Issue
ID
I0231
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/03/2026 The Proposer has withdrawn this Issue following discussions with industry, where impacted Parties advised waiting for the completion of MHHS migration before progressing this Issue and solution development. The window to adopt this Issue has now closed.
Summary
There is a concern regarding shared sites (as defined by BSCP550) that have multiple suppliers linked to them. The investigation revealed a lack of visibility of these sites, and it appears that the industry is similarly uninformed. Elexon, the REC, and the wider industry do not have a consistent way of identifying these shared sites. Therefore, there is a good chance that agents are holding shared sites within their portfolio without knowing it. We would like to explore whether the EES Online Portal has any flags or mechanisms that could help identify these shared sites.
Proposer
Ardin Klimenti
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. A flag on EES that can help everyone clearly identify the shared site, the primary MPAN and all of the pseudo MPANs attached to it.
Problem Statement
There is a concern regarding shared sites (as defined by BSCP550) that have multiple suppliers linked to them. The investigation revealed a lack of visibility of these sites, and it appears that the industry is similarly uninformed. Elexon, the REC, and the wider industry do not have a consistent way of identifying these shared sites. Therefore, there is a good chance that agents are holding shared sites within their portfolio without knowing it. We would like to explore whether the EES Online Portal has any flags or mechanisms that could help identify these shared sites. If not, could these be added?
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
Issue Proposal Form
Company Name
Elexon
Review status
Review required

Proposal to Enable Broader Use of Retail Energy Location (REL) Data for Non-Switching Applications

Date of latest update
Type
Issue
ID
I0218
Change Category
Change Path
Priority
Urgent
No
Latest Update
05/11/2026 - Service Provider Impact Assessments are in progress and will close on 06 November 2026. A refreshed Code Manager Initial Assessment will be carried out given the change of scope since the original assessment.
Summary
The problem being addressed is the current restriction within the Retail Energy Code (REC) that limits the use of Retail Energy Location (REL) data solely to switching purposes. This restriction prevents the full utilisation of REL data, which could be valuable for a broader range of operational, regulatory, and industry applications. Key Issues: - Currently, REL data, enriched with Unique Property Reference Numbers (UPRNs), is available via the Electricity and Gas Enquiry Services. However, Schedule 29 (Address Management) of the REC restricts its use to switching purposes only, preventing its use in other important industry initiatives. - Various industry stakeholders, including REC and non-REC data requestors as well as Ofgem (the regulator), have expressed a strong interest in utilising REL data for non-switching purposes. The restriction is seen as a limitation, especially for initiatives that require accurate property data to support wider operational and regulatory functions. - By restricting the use of REL data to switching, stakeholders are unable to fully leverage it for improving operational efficiency, regulatory compliance, and overall service delivery. Lifting this restriction would enable the wider use of REL data, allowing stakeholders to benefit from its full potential across various non-switching applications.
Proposer
Elise Handy
Change Plan

Proposal plan approved at Change Panel

Completed

Start:

Due:

Completion:

21 Jan 2025

Extension to Proposal Plan approved by REC Change Panel

Completed

Start:

Due:

Completion:

06 May 2025

Update to Plan approved at Change Panel

Completed

Start:

Due:

Completion:

18 Nov 2025

Extension to Plan approved at Change Panel

Completed

Start:

Due:

Completion:

04 Aug 2026
Impacted REC Documents
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
James Hardy
Solution Development
Proposed solution summary
  1. RECCo would acquire a AddressBase Core license from Ordinance Survey and the REC would be updated to allow parties to take full advantage of this data. In order for parties to use the REL data, they would need to acquire an AddressBase Premium license from Ordinance Survey or other relevant license.
Problem Statement
Retail Energy Location (REL) data currently is not permitted for uses such as improving customer service and streamlining internal processes. This means that stakeholders, such as Ofgem and data requestors, have been unable to benefit from this data and Consumers are therefore unable to benefit from the full potential use of their data.
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
Issue proposal form
I0218 - Change Report (Proposal Plan) V2.0 (07.05.2025)
I0218 - Extension to Plan V1.0 (06.05.2025) (Approved)
I0218 - Update to Plan V2.0 (09.09.2025) (Approved)
I0218 - Update to Plan V3.0 (18.11.2025) Approved
I0218 Extension to Plan V1.0 Pre-Approval
I0218 - Extension to Plan V2.0 (04.08.2026) Approved
Company Name
RECCo
Review status
Review required

Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches

Date of latest update
Type
Change
ID
R0205
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
As part of the MHHS REC code change activity, a change has been made to REC Schedule 30 to remove the half hourly meter exemption from the Erroneous Transfer provisions. Whilst this is necessary from an MHHS perspective with all sites becoming half hourly settled, the application of ET obligations in the Advanced Meter segment creates some additional challenges. To be able to accurately bill an Advanced Meter site, following repatriation of that customer to their correct supplier after an ET has been raised / agreed, the supplier needs to have access to half hourly consumption data for the ET period when they were not the registered supplier. With ETs potentially taking up to 2 years to be identified and resolved, the only place that the supplier could reliably source that HH consumption data would be from the other (losing) supplier.
Proposer
Ben Atkinson
Change Report - Draft Change Report
Change report - Final Change Report
Change Plan

Change Proposal Plan to REC Change Panel

Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches > Change Plan

Start:

22 Aug 2024

Due:

01 Apr 2025

Completion:

01 Apr 2025

Discussion at REC Change Issues Group

Not Started

Start:

01 Apr 2025

Due:

05 Jun 2025

Completion:

Status
Implementation Date
Status Superseded
EMAR Version 4.1.0_Superseded
Included changes Affected REC Items
R0152 Revision to the Consolidated Metering Code of Practice (CoMCoP)
  • MOCoPA (since removed)
  • ASPCoP (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Smart Meter Installation Schedule (since removed)
  • Gas Metering Code of Practice (since removed)
R0157 Removal of Facsimile as a Method of Code Communication
  • Schedule 14 - Metering Operations
  • Schedule 18 - Green Deal Arrangements
  • Standards Definition Document
  • Data Item Catalogue
R0191 Introduction of SLA for Supplier De-Registration on Disconnected Meters
  • Schedule 27 - RMP Lifecycle
R0205 Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches
R0212 Protecting Crimestoppers and their Contacts
R0215 Schedule 30 Switch Meter Reading Problems - Rejections and Timings
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
R0060 ERDS Service Definition timezone correction
  • Schedule 1 - Interpretations and Definitions
R0232 Non-Domestic Change of Occupier SDEP Screens (R0155 Solution)
R0243 Transfer of Standard Settlement Configuration and Time Pattern Regime Data Item Ownership
  • Data Item Catalogue
R0248 REC Changes to tie in with DCP451 - Suspending Registrations
  • Schedule 24 - Switching Data Management
R0254 Non-Domestic Change of Occupier Reporting (R0155 Solution)
R0255 Terms of Reference Updates
R0257 Change to REC for Data processing outside of EEA
R0263 Sharing Confirmed Energy Theft Data with the BSCCo
  • Schedule 7 - Energy Theft Reduction
R0269 Schedule 5 – Change Management: Clarity and Typographical Review
  • Schedule 1 - Interpretations and Definitions
  • Schedule 5 - Change Management
R0279 Housekeeping November 2025
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 7 - Energy Theft Reduction
  • Schedule 27 - RMP Lifecycle
  • Schedule 18 - Green Deal Arrangements
  • Schedule 24 - Switching Data Management
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Market Message Catalogue
R0227 Domestic Elective HH Switching
  • Schedule 23 - Registration Services
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
James Hardy
Solution Development
Proposed solution summary
  1. An approval of this Issue/Change Proposal would see an obligation placed upon the Losing Supplier, following a successful Erroneous Switch repatriation, to provide the Gaining Supplier with the Half-Hourly consumption data for the period in which they were erroneously supplying the meter.
  2. Half-Hourly consumption data would be providing to the Gaining Supplier, from the Losing Supplier, via SDEP using an Excel template within 5 Working Days of the Erroneous Switch repatriation switch date. The Gaining Supplier would be required to provide 48 Half-Hourly consumption intervals for each that the the Consumer was supplied by the erroneously Gaining Supplier.
Proposed Solution Document
Document title
I0205 - Draft Legal Text (Schedule 30) - for Party Impact Assessment 10.06.2025
Upload document
I0205 - Draft Legal Text (Schedule 30) - for Party Impact Assessment 10.06.2025.docx
Archive
Off
Document title
I0205 - Draft Reporting Templates
Upload document
I0205 - Draft Reporting Templates.xlsx
Archive
Off
Document title
I0205 - Impact Assessment
Archive
Off
Document title
R0205 - Schedule 30 Legal Drafting 15.08.2025
Upload document
R0205 - Schedule 30 Legal Drafting (For Consultation) 15.08.2025.docx
Archive
Off
Document title
R0205 - Advanced Meter Half-Hourly Consumption Data Sharing Template
Upload document
R0205 - Advanced Meter Half-Hourly Consumption Data Sharing Template.xlsx
Archive
Off
Problem Statement
In the absence of having Half-Hourly consumption data for Erroneously Switched Consumers, Energy Suppliers are currently required to estimate consumption for billing purposes that can lead to inaccurate billing.
I01205 - Change Proposal Form
I0205 - Change Report (Proposal Plan) V1.0 Approved (01.04.2025)
I0205 Consolidated Impact Assessment Responses V1.0 (Non-Confidential) 30.07.2025
R0205 - Consolidated Consultation Responses (09.09.2025)
R0205 Change Report (Final Recommendation) V2.0 (Approved) 16.09.2025
Company Name
Centrica
Review status
Review required

Amendment Proposal: RECCo Access Provision to RECCo Services

Date of latest update
Type
Change
ID
R0185
Change Path
Priority
Urgent
No
Latest Update
08/08/2024 - the Proposer has withdrawn this Change Proposal.
Summary
RECCo is tasked with fulfilling several obligations. This proposal has been raised to amend some of the wording within the REC, which would benefit from reassessment. When the REC was originally drafted, references to RECCo in the code were originally intended to refer to the activities directly managed and overseen by the REC Board, and were considered separately to activities managed by the Code Manager.
Proposer
Andres Alvarez
Impacted REC Documents
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
R0185- CP Form Amendment Proposal RECCo Access Provision to RECCo Services.docx
Company Name
RECCo
Review status
Review required

Proposal for Limiting Queries in EES API Calls (Single Query per API Call)

Date of latest update
Type
Change
ID
R0179
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
This issue has been raised proposing to establish a limit on the number of queries permitted within a single Application Programming Interface (API) call. As there is potential for performance degradation and system instability that can occur when a large number of queries are made in a single API call to the Electricity Enquiry Services (EES) API. The aim would be to prevent overwhelming the system and ensure consistent response times and reliability. Therefore, this proposes implementing a limit of 1000 queries per single API call.
Proposer
Andres Alvarez
Change report - Final Change Report

Comments deadline
Change Plan

Request for Information

Completed

Start:

03 Jun 2024

Due:

05 Jul 2024

Completion:

05 Jul 2024

Change Issue Group

Completed

Start:

05 Jul 2024

Due:

01 Aug 2024

Completion:

01 Aug 2024
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 4.2.0_Superseded
Included changes Affected REC Items
R0179 Proposal for Limiting Queries in EES API Calls (Single Query per API Call)
R0190 Related Meter Point RMP status rules
  • Schedule 28 - Related Metering Points
R0198 Metering Asset Manager (MAM) Communication Method Register
R0242 Missing Scenario Variant from R0043
  • Market Message Catalogue
R0244 C21 to be introduced into STIRG Document
  • Data Item Catalogue
R0235A Missing Scenario Variants in D0179 Alternate Solution
R0256 MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101
  • Market Message Catalogue
R0270 Clarification of SIP Qualification Requirements
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 15 - Metering Accreditation
R0271 Clarification of ASP, AMI, and EMO Accession Requirements
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
R0272 Enabling transparency of the CRS Provider’s REC service level performance
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 26 - Switching Service Management
  • Schedule 24 - Switching Data Management
R0277 Data Latency SLA Alignment for Gas Enquiry Service
  • Schedule 1 - Interpretations and Definitions
R0280 CSS Certificate Authority audit clarification
  • Schedule 1 - Interpretations and Definitions
R0283 Annual Address Management Plan Updates
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 29 - Address Management
R0287 Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 23 - Registration Services
R0293 Housekeeping February 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
holly.law
Solution Development
Proposed Solution Document
Document title
Request For Information (RFI)
Archive
Off
Problem Statement
The absence of a limit on the number of queries (batch processing) within a single API call could cause performance issues and system instability. As a result, system responsiveness may degrade when a large number of queries are made in a single call, impacting user experience and hindering the ability of the EES API to consistently meet user demands.
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
Issue Form
EES API Interface Specification REDLINE DRAFT for R0179
R0179 - Change Report - Final Recommendation Approved
R0179 Change Report (Consultation)
R0179 Consolidated consultation responses (non- confidential)
Re-baseline Change Plan 15.07.25
Consolidated IA responses (non-confidential)
I0179 Change Report (Impact Assessment)
Service Provider - Impacts Data
I0179 - Consolidated RFI Responses
Change Report (Proposal Plan)
Consultation on implementation date response
Change Report - Final Recommendation (new implementation date)
Company Name
RECCo
Review status
Review required

Removal of Facsimile as a Method of Code Communication

Date of latest update
Type
Change
ID
R0157
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
The Public Switched Telephone Networks (PSTN) will be switched off in December 2025 by all telecom companies and will be replaced with an Internet Protocol (IP) digital network. Existing fax machines that are incompatible with new all IP digital networks will become obsolete and no longer capable of meeting Code Communications as prescribed in the REC. All communication methods referencing fax or facsimile will need to be removed and replaced with email (where this is not an existing option), unless an alternative form of communication is needed. Please note: The government have published preparatory guidance which includes migrating to IP-supported technology in advance of the planned decommissioning. UK transition from analogue to digital landlines - GOV.UK (www.gov.uk) Critical National Infrastructure (CNI) (“assets, facilities, systems, networks or processes and the essential workers that operate and facilitate them”) which is subdivided into 13 sectors including Energy, are advised to consider how they move to digital alternatives smoothly to avoid unnecessary interruption following the PSTN switch-off. Openreach's Energy Guidance Factsheet can be found in the CPs Accompanied Documents.
Proposer
Colette Baldwin
Change Plan

Preliminary Change Report and Consultation Issued

Completed

Start:

03 Jan 2024

Due:

09 Feb 2024

Completion:

09 Feb 2024

Final Change Report Issued

Completed

Start:

23 Feb 2024

Due:

12 Mar 2024

Completion:

12 Mar 2024

Responsible Committee Decision

Completed

Start:

12 Mar 2024

Due:

19 Mar 2024

Completion:

19 Mar 2024

Appeal Window Closure

Not Started

Start:

19 Mar 2024

Due:

02 Apr 2024

Completion:

Consultation Close

Completed

Start:

09 Feb 2024

Due:

23 Feb 2024

Completion:

23 Feb 2024
Impacted Consumers
Impacted REC Services
Status
Implementation Date
Status Superseded
EMAR Version 4.1.0_Superseded
Included changes Affected REC Items
R0152 Revision to the Consolidated Metering Code of Practice (CoMCoP)
  • MOCoPA (since removed)
  • ASPCoP (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Smart Meter Installation Schedule (since removed)
  • Gas Metering Code of Practice (since removed)
R0157 Removal of Facsimile as a Method of Code Communication
  • Schedule 14 - Metering Operations
  • Schedule 18 - Green Deal Arrangements
  • Standards Definition Document
  • Data Item Catalogue
R0191 Introduction of SLA for Supplier De-Registration on Disconnected Meters
  • Schedule 27 - RMP Lifecycle
R0205 Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches
R0212 Protecting Crimestoppers and their Contacts
R0215 Schedule 30 Switch Meter Reading Problems - Rejections and Timings
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
R0060 ERDS Service Definition timezone correction
  • Schedule 1 - Interpretations and Definitions
R0232 Non-Domestic Change of Occupier SDEP Screens (R0155 Solution)
R0243 Transfer of Standard Settlement Configuration and Time Pattern Regime Data Item Ownership
  • Data Item Catalogue
R0248 REC Changes to tie in with DCP451 - Suspending Registrations
  • Schedule 24 - Switching Data Management
R0254 Non-Domestic Change of Occupier Reporting (R0155 Solution)
R0255 Terms of Reference Updates
R0257 Change to REC for Data processing outside of EEA
R0263 Sharing Confirmed Energy Theft Data with the BSCCo
  • Schedule 7 - Energy Theft Reduction
R0269 Schedule 5 – Change Management: Clarity and Typographical Review
  • Schedule 1 - Interpretations and Definitions
  • Schedule 5 - Change Management
R0279 Housekeeping November 2025
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 7 - Energy Theft Reduction
  • Schedule 27 - RMP Lifecycle
  • Schedule 18 - Green Deal Arrangements
  • Schedule 24 - Switching Data Management
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Market Message Catalogue
R0227 Domestic Elective HH Switching
  • Schedule 23 - Registration Services
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
James Hardy
Solution Development
Proposed solution summary
  1. All communication methods referencing fax or facsimile will need to be removed and replaced with email
Proposed Solution Document
Document title
Existing References to Fax and "e-mail" in the REC (January 2024)
Upload document
Existing Fax References in the REC.pdf
Archive
Off
Document title
R00157 - Legal Text Changes (All Affected REC Products and Documents)
Upload document
R00157 - Draft Legal Text Changes.zip
Archive
Off
Problem Statement
Existing fax machines that are incompatible with new all IP digital networks will become obsolete and no longer capable of meeting Code Communications as prescribed in the REC
CP Form - Removal of a Fax as a Code Communication method
R0157 - Change Proposal Plan V1.0 (Approved) 30.01.2024
R0157 - Initial Assessment Report V1.0 (Approved) 30.01.2024
R0157 - Consolidated Consultation Responses
R0157 - Preliminary Change Report V1.0 (For Consultation) 09.02.2024
R0157 - Final Change Report V2.0 (Post-Vote) 19.03.2024
Open Reach Energy Industry Factsheet
Company Name
REC Code Manager
Review status
Review required

Allowing different Metering Equipment Managers (MEMs) to be appointed to Import and Export Metering Points

Date of latest update
Type
Change
ID
R0144
Change Category
Priority
Urgent
No
Latest Update
17/02/2025 - R0144 has been withdrawn by the Proposer, alongside it's joint BSC Change P459, as they cannot be progressed prior to MHHS. The Proposer will look to re-raise both changes in the future. The adoption window for this withdrawal has closed.
Summary
The Export Supplier needs to be able to appoint different MEMs to that of the Import Supplier
Proposer
Kit Dixon
Impacted Consumers
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I want a competitive Export market so I can get the best rates for the energy I generate. I want clear metering equipment ownership so I can be confident my meter is functional and safe. I want accurate billing from my Export Supplier.
  2. As an Export Supplier, I want to be able to appoint the MEM that ties in with my commercial strategy.
  3. As a MEM, I want clear guidance on the responsibilities I have for any metering equipment I am appointed to.
Problem Statement
Export Suppliers may become non-compliant with industry regulations if they are unable to appoint the same MEM as the Import Supplier, for example when the Consumer switches Import Supplier or when the Import Supplier changes the appointed MEM.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
Change Proposal Form
R0144 Change Proposal Plan Withdrawal v1.0 (Pre Approval)
R0144 Change Proposal Plan v1.0 (16.04.2024) Approved
R0144 Initial Assessment Report v1.0 (16.04.2024) Approved
Company Name
REC Code Manager
Review status
Review required

Add DESNZ to Schedule 12

Date of latest update
Type
Change
ID
R0135
Change Category
Change Path
Priority
Urgent
No
Latest Update
22/03/2024 - Withdrawn.
Summary
Empty
Proposer
Elise Handy
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Stages Selection
R0135 - Change Proposal Form
Company Name
BEIS (Department for Business, Energy and Industrial Strategy)
Review status
Review required

New EES User Category for the Department for Education

Date of latest update
Type
Change
ID
R0127
Change Category
Change Path
Priority
Urgent
No
Latest Update
05/04/2024 - Following the implementation of R0118, this change has followed the new data access process and has been withdrawn.
Summary
The Department for Education (DfE) wants to be in a position to support schools in making the best use of the energy commodity use within the educational estate. To do this they need the ability to identify the energy meters in use across the educational estate, so that they support schools and colleges with analogue meters with their upgrade to Smart Meters and understand their energy data usage. Currently the DfE does not have access to the Electricity Enquiry Service data to enable it to understand what electricity meters are installed in schools.
Proposer
Kathryn Swanson
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
R0127 - Change Proposal form (downloadable version) 13.06.2023
R0127 - Draft Electricity DAM (pre-IAR) v0.1 13.06.2023
Company Name
-
Review status
Review required

Review of Schedule 12 and processes to manage access to data

Date of latest update
Type
Change
ID
R0118
Change Category
Change Path
Priority
Urgent
No
Latest Update
06/12/2023- This Change was implemented as part of the 6 December 2023 Extraordinary Release
Summary
Since REC go-live in September 2021, Enquiry Service Providers have operated the Enquiry Services processes as effectively as possible, however, overtime gaps have emerged and opportunities to improve have been identified. There have been an increasing number of access requests for market roles that are not reflected in Schedule 12 or the Data Access Matrix (DAM). As a result, it has become apparent there are restrictions on the access to data, and the granting of access to such users can be slow and time consuming. Given the market roles are too narrow at present, this will become increasingly problematic as they do not reflect market roles that could exist in 10 year’s time for example. There is a need to therefore limit ambiguity and reduce number of use cases where judgement is required. This CP will take forward the review of Schedule 12 and any identified changes.
Proposer
Katie Taaffe
Change Plan

Preliminary Change Report issued

Completed

Start:

12 May 2023

Due:

08 Sep 2023

Completion:

08 Sep 2023

Consultation triggered

Completed

Start:

08 Sep 2023

Due:

08 Sep 2023

Completion:

08 Sep 2023

Consultation close

Completed

Start:

08 Sep 2023

Due:

22 Sep 2023

Completion:

22 Sep 2023

Final Change Report issued

Completed

Start:

22 Sep 2023

Due:

06 Oct 2023

Completion:

06 Oct 2023

Responsible Committee decision

Completed

Start:

06 Oct 2023

Due:

17 Oct 2023

Completion:

17 Oct 2023
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 3.7.0_Live

Documents

Name Version Last updated Actions
160.82 KB
Version 1.0 - 02 Nov 2026 PDF - 160.82 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I want Market Participants to have the appropriate data access so any issues affecting my energy account can be addressed easily.
  2. As a Consumer, I want Market Participants to have appropriate data access so that I can benefit from improved product and service offerings.
  3. As a Market Participant, I want the processes that grant data access to be simplified and adaptable so that valid data use cases are addressed quickly.
Proposed Solution Document
Document title
R0118 - Draft Legal Text at PCR 08.09.2023
Upload document
R0118 - Draft Legal Text at PCR.zip
Archive
Off
Document title
R0118 - Draft Legal Text at FCR 06.10.2023
Upload document
R0118 - Draft Legal Text at FCR 06.10.2023.zip
Archive
Off
Problem Statement
Organisations with valid use cases for REC data access must raise a Change Proposal as they are not listed within Schedule 12 or the Data Access Matrix. This is a time-consuming process which delays the implementation of the required access and does not promote innovation, competition, and positive Consumer outcomes.
R0118 - Change Proposal Form 12.05.2023
R0118 - Change Proposal Plan (Approved) 05.09.2023
R0118 - Initial Assessment Report (Approved) 05.09.2023
R0118 - Consolidated Consultation Responses_NON-CONFIDENTIAL 06.10.2023
R0118 - Preliminary Change Report v1.0 (Published for Consultation) 08.09.2023
R0118 - Final Change Report (Approved) 17.10.2023
Company Name
-
Review status