Commissioning of Works by the Crowded Meter Room Coordinator (CMRC) to Resolve Issues In Crowded Meter Rooms

Date of latest update
Type
Change
ID
R0043
Change Category
Priority
Urgent
No
Latest Update
28/06/2024 - Change implemented as part of the June 2024 REC Release
Summary
This Change Proposal is to introduce new processes which will allow a Crowded Meter Room Co-ordinator (CMRC) to contract with a REC accredited Metering Equipment Manager (MEM) to act on behalf of the CMRC, so that they may resolve issues in a Crowded Meter Room (CMR) on behalf of all Registered Suppliers within that meter room. The MEMs undertaking this work on behalf of the CMRC will be referred to as the Crowded Meter Room MEM (CMRM).
Proposer
David Jones
Change Plan

Sandbox Decision

Completed

Start:

22 Apr 2022

Due:

29 Nov 2022

Completion:

29 Nov 2022

Sandbox Trial Commences

In Progress

Start:

29 Nov 2022

Due:

01 Feb 2023

Completion:

Impact Assessment Window

Completed

Start:

06 Jun 2023

Due:

09 Jun 2023

Completion:

09 Jun 2023

Present Extended Plan to Responsible Committee

Completed

Start:

01 Feb 2023

Due:

06 Jun 2023

Completion:

06 Jun 2023

Preliminary Change Report Published

Completed

Start:

09 Jun 2023

Due:

04 Aug 2023

Completion:

02 Aug 2023

Consultation Issued

Completed

Start:

04 Aug 2023

Due:

18 Aug 2023

Completion:

18 Aug 2023

Final Change Report Published

Completed

Start:

18 Aug 2023

Due:

08 Dec 2023

Completion:

10 Nov 2023

Responsible Committee Decision

Completed

Start:

08 Dec 2023

Due:

19 Dec 2023

Completion:

19 Dec 2023
Impacted Consumers
Impacted REC Services
Status
Implementation Date
Status Superseded
EMAR Version 3.11.0_Superseded
Included changes Affected REC Items
R0043 Commissioning of Works by the Crowded Meter Room Coordinator (CMRC) to Resolve Issues In Crowded Meter Rooms
  • MOCoPA (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 12 - Data Access
  • Data Access Matrix (Electricity)
  • Data Item Catalogue
  • Market Message Catalogue
R0158 Amendment to the ‘Supplier Registration Report (MAP)’ report methodology
R0160 Electricity Supply to Hydrogen Electrolysers
  • Schedule 1 - Interpretations and Definitions
R0064 Creating a Meter Operator Agent and MOCoP Installer
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 9 - Qualification and Maintenance
R0070 Provision of Enduring Test Environments
  • Schedule 1 - Interpretations and Definitions
  • Schedule 5 - Change Management
  • Schedule 26 - Switching Service Management
  • Schedule 25 - Central Switching Service

Documents

Name Version Last updated Actions
159.49 KB
Version 1.0 - 16 Nov 2026 PDF - 159.49 KB
1.0 16 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer I want to be able to have a working Smart Meter that can communicate with my Energy Supplier so that I can receive the benefits of smart metering
  2. As a property owner I want to be able to have Smart Meters installed in my properties where there are currently issues with meter room space or other technical constraints preventing installation so that my tenants can access the benefits of having a Smart Meter. As a property owner I want a co-ordinated and managed process for resolving crowded meter room issues so that I am not contacted by or dealing with multiple Suppliers or metering agents for a single property.
  3. As an Energy Supplier, I need to be able to send and receive data, from the CMRC related to interference, faults, or damage to my equipment so that I can fulfil my obligations. As an Energy Supplier I need a coordinated approach to resolving the crowded meter room to enable me to meet my regulatory obligations related to Smart Meter installations and Communications. As an Energy Supplier, I want to know of CMR works being carried out so that I am informed of relevant updates regarding RMPs that I supply. In addition, I wish to be informed if the CMRM identifies any metering issues during their initial assessment or rectification works
  4. As a Distribution Network Operator, I need to be able to send and receive data, from the CMRC related to danger, interference, or damage to my equipment so that I can fulfil my obligations.
  5. As a MEM I need a co-ordinated approach to resolving the CMR issues, to enable me to install working Smart Meters on site.
Proposed Solution Document
Document title
R0043 - Solution Overview (10.11.2023)
Upload document
R0043 - Solution Overview v1.2 (1).docx
Archive
Off
Document title
R0043 Legal Text (10.11.2023)
Upload document
Final Legal Text (1).zip
Archive
Off
Document title
R0043 Data Specification (22.03.2024)
Upload document
Data Spec v2.1 220324.zip
Archive
Off
Problem Statement
For many Multiple Dwelling Units (MDU), Alt HAN Co equipment is required. This needs to be installed near to the electricity Smart Meter, connected to the tails of that Smart Meter, and requires at least one further device in the Consumer premises. However, the installation of HAN equipment can be inhibited by Crowded Meter Room (CMR) for the installation of alternative HAN and smart equipment. The objective of the CMR work is to leave a meter room ready for Energy Suppliers to proceed with their installations to meet their smart metering rollout obligations. Without the ability to install the alternative HAN wired bridge device in a CMR, Energy Suppliers will ultimately be unable to establish a HAN with the associated premises in the MDU
SME
SME Role
Lead Technical Analyst
DCP400 Crowded Meter Room Data Flows.pptx
DCP 400 Introduction to CMR.pptx
R0043 - Change Proposal Plan v5.0 (Approved)
R0043 - Initial Assessment Report v1.0 (Approved)
Alt HAN Co - Target Operating Model
R0043 FAQs v1.1 (08.11.2023)
Crowded Meter Room Pilot overview 14.07.2023
Non Confidential Consolidated Party Impact Assessment Responses
Preliminary Change Report (Approved) 15.08.2023
Crowded Meter Room Webinar 10.08.2023
R0043 - Non Confidential Consultation Response
R0043 Authority Decision
R0043 Final Change Report V2.1 (Approved)
Company Name
-
Review status
Review required

REC V3.0

Date of latest update
Type
Change
ID
R0041
Change Category
Urgent
Yes
Latest Update
-
Summary
-
Proposer
Alasdair MacMillan
Change Plan

Legal text baselined

Completed

Start:

10 Apr 2022

Due:

13 May 2022

Completion:

13 May 2022

Final Change Report Issued

Completed

Start:

13 May 2022

Due:

20 May 2022

Completion:

20 May 2022

Responsible Committee Decision

Completed

Start:

20 May 2022

Due:

07 Jun 2022

Completion:

07 Jun 2022

Authority Determination (Original)

Completed

Start:

07 Jun 2022

Due:

20 Jun 2022

Completion:

17 Jun 2022

Authority Determination (revoked and re-issued)

Completed

Start:

20 Jun 2022

Due:

29 Jun 2022

Completion:

29 Jun 2022
Impacted Consumers
Status
Implementation Date
Status Superseded
EMAR Version 3.0.0_Superseded
Included changes Affected REC Items
R0038 Performance Assurance Report Catalogue Changes as a consequence of REC V3.0
R0041 REC V3.0
  • REC Main Body
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 19 - Market Exit and Supplier of Last Resort
  • Schedule 5 - Change Management
  • Schedule 27 - RMP Lifecycle
  • ASPCoP (since removed)
  • Schedule 28 - Related Metering Points
  • Schedule 29 - Address Management
  • Schedule 9 - Qualification and Maintenance
  • Schedule 2 - REC Transition Schedule
  • Schedule 26 - Switching Service Management
  • Schedule 12 - Data Access
  • Schedule 10 - Charging Methodology
  • Schedule 23 - Registration Services
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Schedule 25 - Central Switching Service
  • Standards Definition Document
  • Data Access Matrix (Electricity)
  • Data Access Matrix (Gas)
  • Data Item Catalogue
  • Market Message Catalogue
R0042 Performance Assurance Board Terms of Reference
  • Performance Assurance Board - Terms of Reference
R0045 Changes to SDEP Messages and Schedule numbering for REC V3.0
  • Market Message Catalogue

Documents

Name Version Last updated Actions
258.97 KB
Version 1.0 - 02 Nov 2026 PDF - 258.97 KB
1.0 02 Nov 2026
257.76 KB
Version 1.0 - 02 Nov 2026 DOCX - 257.76 KB
1.0 02 Nov 2026
219.4 KB
Version 1.0 - 16 Nov 2026 PDF - 219.4 KB
1.0 16 Nov 2026
1.65 MB
Version 1.0 - 02 Nov 2026 PPTX - 1.65 MB
1.0 02 Nov 2026
6.74 MB
Version 1.0 - 02 Nov 2026 PPTX - 6.74 MB
1.0 02 Nov 2026
9.01 MB
Version 1.0 - 02 Nov 2026 PPTX - 9.01 MB
1.0 02 Nov 2026
3.89 MB
Version 1.0 - 02 Nov 2026 PPTX - 3.89 MB
1.0 02 Nov 2026
1.0 02 Nov 2026
16.78 KB
Version 1.0 - 02 Nov 2026 XLSX - 16.78 KB
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I want to be able to successfully switch my Energy Supplier with minimal delay or hassle, so that I can start to receive the service and tariff from my chosen Energy Supplier at the earliest opportunity.
  2. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the obligations, processes and provisions for the new switching arrangements, to enable the successful transition to enduring governance and operational arrangements.
  3. As a REC Party, I want to be clear on the obligations I need to meet and the processes I need to follow post CSS go live, to ensure my organisation is ready for the introduction of the new switching arrangements.
  4. As a REC Service Provider, I want to be clear on the obligations, processes and service standards that I need to meet, to ensure my organisation is ready for the introduction of the new switching arrangements.
Proposed Solution Document
Document title
REC V3.0 Baselined documents
Upload document
R0041 Legal Text.zip
Archive
Off
Document title
REC v3.0 Baselined documents (REC Portal)
Archive
Off
Problem Statement
Changes are required to the REC, to ensure the appropriate obligations, processes and provisions are defined within the REC at CSS go-live, enabling successful transition to enduring governance and operational arrangements developed as part of Ofgem’s Switching Programme.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0041 - Change Proposal Form
Letter from the Authority to the REC Code Manager - REC V3.0 Authority Change Proposal
R0041 - Change Proposal Plan v1.0 (Approved)
R0041 - Initial Assessment Report v2.0 (Approved)
R0041 - Final Change Report v3.0 (Post-Vote)
R0041 Authority Decision
Company Name
Ofgem
Review status
Review required

CSS Switch Synchronisation to ERDA at SecuredActive

Date of latest update
Type
Change
ID
R0040
Change Category
Change Path
Priority
Urgent
No
Latest Update
-
Summary
-
Proposer
Daniel Tadecicco
Change Plan

Solution analysis and development

Completed

Start:

17 Oct 2022

Due:

31 Oct 2022

Completion:

31 Oct 2022

Change Proposal Plan presented to Change Panel for re-baselining

Completed

Start:

31 Oct 2022

Due:

01 Nov 2022

Completion:

26 Oct 2022

Service Provider Impact Assessment period started

Completed

Start:

04 Apr 2022

Due:

17 Oct 2022

Completion:

17 Oct 2022

Service Provider Impact Assessment period ended

Completed

Start:

16 Nov 2022

Due:

18 Jan 2023

Completion:

08 Nov 2022

Change Proposal Withdrawn

Completed

Start:

01 Nov 2022

Due:

16 Nov 2022

Completion:

16 Nov 2022
Impacted Consumers
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Harriet Truss
Solution Development
Proposed solution summary
  1. As a Consumer I want the Switch process to work effectively so that I can switch Electricity Supplier without delay or issues As a Consumer I want the Switch process to work effectively so that if my Switch needs to be cancelled it is done so without delay or issues
  2. As an Energy Supplier I want the Switch systems and process to operate effectively so that appointment Market Messages will be sent to my agents at the appropriate time so that there is no disruption to the Consumer switching experience
  3. As the ERDS Provider I only want to receive the first Pending message and then the Secured Active confirmation message, in order that there is no risk of processing CSS messages out of sequence which could impact a timely Switch for electricity Consumers As the CSS Provider I want the messages I send to MPRS to be processed effectively so that there is no disruption to the Switch process and Consumers’ Switches can be confirmed or cancelled as required
Problem Statement
Due to the high volume and timing of Registration messages being sent by the CSS, some messages are at risk of being received by REC Parties and Service Providers out of sequence. When messages have been received out of sequence, there is a risk that the information maintained in MPRS, including Registration Status, will be incorrect and will not match that held in the Registration Service. This in turn means MPRS updates to Parties could be triggered in error.
Stages Selection
SME
SME Role
Lead Technical Analyst
R0040 - CSS Switch Synchronisation to ERDA Proposer solution
R0040 - Change Proposal Plan v2.0 (Approved)
R0040 - Initial Assessment Report v1.0 (Approved)
Company Name
St Clements Services
Review status
Review required

Prepayment Credit Balance Transfer Process

Date of latest update
Type
Change
ID
R0037
Change Category
Priority
Urgent
No
Latest Update
04/08/2026 - On 04 August 2026, the REC Change Panel approved this Proposal Plan.
Summary
This Change Proposal seeks to develop an agile, efficient, Consumer-centric solution for the transfer of credit balance as part of a smart prepayment Switch.
Proposer
Simon Bevis
Change Plan

Initial Analysis

Completed

Start:

10 Mar 2022

Due:

30 Jun 2022

Completion:

Present updated Change Proposal Plan to Change Panel

Completed

Start:

30 Jun 2022

Due:

19 Jul 2022

Completion:

Solution Development Complete

Completed

Start:

30 Jan 2023

Due:

29 Feb 2024

Completion:

29 Feb 2024

Present Updated Change Proposal Plan to Change Panel

Completed

Start:

19 Jul 2022

Due:

08 Nov 2022

Completion:

Present Updated Plan to Change Panel

Completed

Start:

08 Nov 2022

Due:

17 Jan 2023

Completion:

17 Jan 2023

Service Provider Impact Assessment

Completed

Start:

17 Jan 2023

Due:

30 Jan 2023

Completion:

30 Jan 2023
Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
florentina.monea
Solution Development
Proposed Solution Document
Document title
R0037 - Draft Legal Text v1.0
Upload document
R0037 Party IA Legal Drafts.zip
Archive
Off
Document title
R0037 - Solution Document v2.0
Upload document
R0037 - Solution Document v2.0.pdf
Archive
Off
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
R0037 - CP Form (Downloadable version)
R0037 Consolidated Party IA Responses PUBLIC v1.0
R0037 - Change Proposal Plan V6.0 (Approved) 05.03.24
R0037 - Initial Assessment Report v1.0 (Approved) 06.04.22
R0037 Consolidated RFI Responses PUBLIC v1.0
R0037 Change Report (Proposal Plan) Approved
Company Name
Utilita Energy Limited
Review status
Review required

Extensive Housekeeping Amendments

Date of latest update
Type
Change
ID
R0036
Change Category
Change Path
Priority
Urgent
No
Latest Update
-
Summary
-
Proposer
Ann Perry
Change Plan

Legal review of draft legal text

Completed

Start:

04 Mar 2022

Due:

19 Aug 2022

Completion:

19 Aug 2022

Creation of legal text in the EMAR

Completed

Start:

19 Aug 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Deadline for alternative change proposal submission

Completed

Start:

02 Sep 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Preliminary Change Report issued

Completed

Start:

02 Sep 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Consultation Start

Completed

Start:

02 Sep 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Consultation Ends

Completed

Start:

02 Sep 2022

Due:

26 Sep 2022

Completion:

26 Sep 2022

Final Change Report issued

Completed

Start:

26 Sep 2022

Due:

07 Oct 2022

Completion:

07 Oct 2022

Appeal window closure

Not Started

Start:

18 Oct 2022

Due:

01 Nov 2022

Completion:

Responsible Committee Decision

Completed

Start:

07 Oct 2022

Due:

18 Oct 2022

Completion:

18 Oct 2022
Impacted Consumers
Status
Implementation Date
Status Superseded
EMAR Version 3.2.0_Superseded
Included changes Affected REC Items
R0018 Complex Sites process improvements
  • Schedule 14 - Metering Operations
R0022 Amendment to REC Data Access Matrix
  • Schedule 12 - Data Access
  • Data Access Matrix (Electricity)
R0054 EES Access for Virtual Lead Parties
  • Schedule 1 - Interpretations and Definitions
R0031 Altering the Trigger Points for CT Commissioning
  • Schedule 14 - Metering Operations
  • Data Item Catalogue
  • Market Message Catalogue
R0033 Micro-business Smart Meter Installation Reports
  • Smart Meter Installation Schedule (since removed)
R0036 Extensive Housekeeping Amendments
  • MOCoPA (since removed)
  • Schedule 15 - Metering Accreditation
  • REC Main Body
  • ASPCoP (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 11 - Prepayment Arrangements
  • Schedule 6 - Performance Assurance
  • Schedule 19 - Market Exit and Supplier of Last Resort
  • Schedule 7 - Energy Theft Reduction
  • Schedule 5 - Change Management
  • Schedule 8 - Unbilled Energy Code of Practice
  • Schedule 4 - Company Governance
  • Schedule 17 - Secure Data Exchange
  • Schedule 28 - Related Metering Points
  • Schedule 3 - Accession Agreement
  • Schedule 18 - Green Deal Arrangements
  • Schedule 29 - Address Management
  • Schedule 13 - Transfer of Consumer Data
  • Smart Meter Installation Schedule (since removed)
  • Gas Metering Code of Practice (since removed)
  • Schedule 9 - Qualification and Maintenance
  • Schedule 2 - REC Transition Schedule
  • Schedule 26 - Switching Service Management
  • Schedule 12 - Data Access
  • Schedule 24 - Switching Data Management
  • Schedule 10 - Charging Methodology
  • Schedule 23 - Registration Services
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Schedule 25 - Central Switching Service
  • Data Access Matrix (Electricity)
  • Data Access Matrix (Gas)
  • Data Item Catalogue
  • Market Message Catalogue

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Jonathan Holland
Solution Development
Proposed solution summary
  1. As a REC Party, I need the REC drafting to be accurate, so I can rely on it to ensure my processes and procedures correctly reflect my obligations. If there are mistakes or omissions, then it could cause issues with the effective operation and assurance of the retail energy market.
Proposed Solution Document
Document title
R0036 - proposed changes v2.0
Upload document
R0036 - proposed changes v2.0 (2).xlsx
Archive
Off
Document title
Variants ONJOB Flows - Market Participant Mandatory v1.0
Upload document
Variants ONJOB Flows - Market Participant Mandatory v1.0.xlsx
Archive
Off
Document title
EMAR Link 1
Archive
Off
Document title
EMAR Link 2
Archive
Off
Problem Statement
REC Parties and Service Providers rely on the REC to provide a consistent baseline to ensure the industry operates effectively and to give certainty to Parties obligations. There are currently inconsistencies between the drafting of the REC, and the processes operated by REC Parties and Service Providers. This could cause issues in the effective operation and assurance of the retail energy market.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0036 - proposed changes v1.0
R0036 - Change Proposal Plan v2.0 (Approved)
R0036 - Initial Assessment Report v1.0 (Approved)
R0036 - CP Form (Downloadable version)
R0036 - Consolidated consultation responses
Re-Baselined Change Proposal Plan for R0036
R0036 - Preliminary Change Report v1.0
R0036 - Final Change Report v2.0 (Post-Vote)
Company Name
-
Review status
Review required

Market Stabilisation Charge – Administration

Date of latest update
Type
Change
ID
R0035
Change Category
Priority
Urgent
Yes
Latest Update
-
Summary
-
Proposer
Jon Dixon
Change Plan

Party Impact Assessment initiated

Completed

Start:

22 Feb 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Party Impact Assessment completed

Completed

Start:

08 Apr 2022

Due:

29 Apr 2022

Completion:

29 Apr 2022

Preliminary Change Report issued

Completed

Start:

29 Apr 2022

Due:

06 May 2022

Completion:

06 May 2022

Issued to Responsible Committee for review (ex-Committee)

Completed

Start:

06 May 2022

Due:

10 May 2022

Completion:

10 May 2022

Consultation initiated

Completed

Start:

10 May 2022

Due:

13 May 2022

Completion:

13 May 2022

Consultation completed

Completed

Start:

13 May 2022

Due:

01 Jun 2022

Completion:

01 Jun 2022

Final Change Report issued

Completed

Start:

01 Jun 2022

Due:

10 Jun 2022

Completion:

10 Jun 2022

Responsible Committee Decision (ex-Committee)

Completed

Start:

10 Jun 2022

Due:

14 Jun 2022

Completion:

14 Jun 2022

Authority Determination

Completed

Start:

14 Jun 2022

Due:

24 Jun 2022

Completion:

27 Jun 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 2.3.0_Live
Included changes Affected REC Items
R0014 Cable Colour Identification
  • MOCoPA (since removed)
R0019 Consequential REC changes for BSC CP1532
  • Schedule 14 - Metering Operations
R0008 Consequential New and Amended Market Messages for BSC Modification P375
  • Standards Definition Document
  • Data Item Catalogue
  • Market Message Catalogue
R0023 Prepayment Unallocatable Transactions
  • Schedule 11 - Prepayment Arrangements
R0035 Market Stabilisation Charge – Administration
  • Schedule 1 - Interpretations and Definitions

Documents

Name Version Last updated Actions
156.64 KB
Version 1.0 - 02 Nov 2026 PDF - 156.64 KB
1.0 02 Nov 2026
256.28 KB
Version 1.0 - 02 Nov 2026 DOCX - 256.28 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Domestic Consumer, I want to be able to choose my Energy Supplier and a tariff from a range of competitive options, so that I can take advantage of cheaper deals as they become available.
  2. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the MSC obligations, so that the new MSC licence obligations on Energy Suppliers can be effectively discharged by RECCo.
  3. As RECCo, I want the Retail Energy Code to specify my obligations, governance and charging mechanisms, so that I can effectively discharge obligations imposed by the Authority through the Licence Condition modification.
  4. As a Domestic Supplier, I want to understand how RECCo will calculate my credits and liabilities and when they will send my invoices/credit notes, so that I can plan to review my invoices/credit notes prior to the receipt of monies owed or payments I make to RECCo or at an appropriate time for my organisation. As a Domestic Supplier, I want to understand how I could dispute an invoice which I do not believe is accurate, so that I am able to raise a dispute/challenge compliantly
Proposed Solution Document
Document title
Legal Text (tracked changes)
Upload document
R0035 Legal Text - Post Consultation.zip
Archive
Off
Document title
EMAR Change Set
Archive
Off
Problem Statement
Following the publication of Ofgem’s decision on potential short-term interventions to address risks to consumers from market volatility, the Market Stabilisation Charge will be introduced via the modified Standard Licence Condition 24A and introduced into the REC by Change Proposal R0034. A change is needed to the REC to set out the charging and payment mechanism, and to introduce the necessary governance arrangements to allow these MSC payments to be administered by RECCo.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0035 - CP Form (Downloadable version)
Ofgem Decision document - Short Term Interventions
MSC calculation guidance
Gas SLC Modified Decision Notice
Elec SLC Modified Decision Notice
R0035 - High level Solution Overview v1.0
R0035 - Change Proposal Plan v2.0 (Approved)
R0035 - Initial Assessment Report v2.0 (Approved)
R0035 - Consolidated IA responses v1.0
R0035 - Proposed Solution v2.0
R0035 - Preliminary Change Report v2.0 (Approved)
R0035 - Consolidated consultation responses v1.0
R0035 - Final Change Report v2.0 (Post-Vote)
Authority Decision for R0035
Company Name
RECCo
Review status
Review required

Market Stabilisation Charge

Date of latest update
Type
Change
ID
R0034
Change Category
Priority
Urgent
Yes
Latest Update
-
Summary
-
Proposer
Henry Kemp
Change Plan

Preliminary Change Report issued

Completed

Start:

21 Feb 2022

Due:

04 Mar 2022

Completion:

04 Mar 2022

Consultation issued (5 WD)

Completed

Start:

04 Mar 2022

Due:

04 Mar 2022

Completion:

04 Mar 2022

Final Change Report issued

Completed

Start:

04 Mar 2022

Due:

18 Mar 2022

Completion:

18 Mar 2022

Responsible Committee decision (ex-Committee)

Completed

Start:

18 Mar 2022

Due:

23 Mar 2022

Completion:

23 Mar 2022

Authority determination

Completed

Start:

23 Mar 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version REC V2.2.2_SUPERSEDED
Included changes Affected REC Items
R0028 Review of Category 3 documents in the REC Baseline Statement
  • Schedule 1 - Interpretations and Definitions
  • Schedule 5 - Change Management
  • Standards Definition Document
R0034 Market Stabilisation Charge
  • Schedule 1 - Interpretations and Definitions

Documents

Name Version Last updated Actions
170.51 KB
Version 1.0 - 02 Nov 2026 PDF - 170.51 KB
1.0 02 Nov 2026
4.09 MB
Version 1.0 - 02 Nov 2026 PPTX - 4.09 MB
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the MSC obligations, so that the new MSC licence obligations on Energy Suppliers can be effectively discharged by RECCo.
Proposed Solution Document
Document title
Legal Text
Upload document
R0034 legal text - Market Stabilisation Charge v2.0 Post Consultation.zip
Archive
Off
Document title
EMAR Change Set
Archive
Off
Problem Statement
Following the publication of Ofgem’s decision on potential short-term interventions to address risks to consumers from market volatility, the Market Stabilisation Charge will be introduced via the modified Standard Licence Condition 24A. A change is needed to the REC to give effect to the Market Stabilisation Charge from 14 April 2022.
Ofgem Decision Document - Short Term Interventions
R0034 - CP Form (Downloadable version)
R0034 - Change Proposal Plan v1.0 (Approved)
R0034 - Initial Assessment Report v1.0 (Approved)
R0034 - Preliminary Change Report v1.0 (Published for Consultation)
R0034 - Consolidated consultation responses v1.0
R0034 - Final Change Report v2.0 (Post-Vote)
Authority Decision for R0034 - Market Stabilisation Charge
Company Name
-
Review status
Review required

Micro-business Smart Meter Installation Reports

Date of latest update
Type
Change
ID
R0033
Change Category
Change Path
Priority
Urgent
No
Latest Update
-
Summary
-
Proposer
Kelly Austin
Change Plan

Legal text drafting initiated

Completed

Start:

07 Feb 2022

Due:

02 May 2022

Completion:

02 May 2022

Legal text drafting completed

Completed

Start:

02 May 2022

Due:

16 May 2022

Completion:

16 May 2022

Service Provider IA completed

Completed

Start:

16 May 2022

Due:

14 Jun 2022

Completion:

14 Jun 2022

Preliminary Change Report issued

Completed

Start:

14 Jun 2022

Due:

01 Jul 2022

Completion:

01 Jul 2022

Consultation completed

Completed

Start:

01 Jul 2022

Due:

22 Jul 2022

Completion:

22 Jul 2022

Final Change Report issued

Completed

Start:

22 Jul 2022

Due:

05 Aug 2022

Completion:

05 Aug 2022

Responsible Committee Decision

Completed

Start:

05 Aug 2022

Due:

16 Aug 2022

Completion:

16 Aug 2022
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 3.2.0_Superseded
Included changes Affected REC Items
R0018 Complex Sites process improvements
  • Schedule 14 - Metering Operations
R0022 Amendment to REC Data Access Matrix
  • Schedule 12 - Data Access
  • Data Access Matrix (Electricity)
R0054 EES Access for Virtual Lead Parties
  • Schedule 1 - Interpretations and Definitions
R0031 Altering the Trigger Points for CT Commissioning
  • Schedule 14 - Metering Operations
  • Data Item Catalogue
  • Market Message Catalogue
R0033 Micro-business Smart Meter Installation Reports
  • Smart Meter Installation Schedule (since removed)
R0036 Extensive Housekeeping Amendments
  • MOCoPA (since removed)
  • Schedule 15 - Metering Accreditation
  • REC Main Body
  • ASPCoP (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 11 - Prepayment Arrangements
  • Schedule 6 - Performance Assurance
  • Schedule 19 - Market Exit and Supplier of Last Resort
  • Schedule 7 - Energy Theft Reduction
  • Schedule 5 - Change Management
  • Schedule 8 - Unbilled Energy Code of Practice
  • Schedule 4 - Company Governance
  • Schedule 17 - Secure Data Exchange
  • Schedule 28 - Related Metering Points
  • Schedule 3 - Accession Agreement
  • Schedule 18 - Green Deal Arrangements
  • Schedule 29 - Address Management
  • Schedule 13 - Transfer of Consumer Data
  • Smart Meter Installation Schedule (since removed)
  • Gas Metering Code of Practice (since removed)
  • Schedule 9 - Qualification and Maintenance
  • Schedule 2 - REC Transition Schedule
  • Schedule 26 - Switching Service Management
  • Schedule 12 - Data Access
  • Schedule 24 - Switching Data Management
  • Schedule 10 - Charging Methodology
  • Schedule 23 - Registration Services
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Schedule 25 - Central Switching Service
  • Data Access Matrix (Electricity)
  • Data Access Matrix (Gas)
  • Data Item Catalogue
  • Market Message Catalogue

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
colette.baldwin
Solution Development
Proposed solution summary
  1. As a Micro-Business Consumer, I want my Energy Supplier to complete my Smart Meter installation in line with, or above, the standards of service provided by other Energy Suppliers, so that the installation of the Smart Meter has minimal disruption to my business.
  2. As an Energy Supplier to Micro-Business Consumers, I want access to Consumer feedback from across the industry, to enable me to assess my performance relative to other Micro-Business Energy Suppliers and identify areas of under or over performance, enabling me to take appropriate actions to increase or maintain my performance.
Proposed Solution Document
Document title
Proposed Draft Legal Text
Upload document
Legal Text R0033 - Solution and Housekeeping Differentiated v2.0.docx
Archive
Off
Document title
Final Change Report (Approved)
Upload document
R0033 -. Final Change Report v2.0.pdf
Archive
Off
Problem Statement
Energy Suppliers do not currently have the ability to assess their Micro-Business Smart Meter installation performance relative to other Energy Suppliers through Consumer Survey Reports, therefore may not take any appropriate action to address any areas of underperformance or respond to trends in Consumer feedback, wider than their own Consumer base. This could affect the Smart Meter installation service received by Micro-Business Consumers.
Micro Business Customer Survey Report Q2 2021
R0033 - CP Form (Downloadable version)
R0033 - Change Proposal Plan v1.0 (Approved)
R0033 - Initial Assessment Report v1.0 (Approved)
Consolidated Impact Assessment Responses
R0033 - Preliminary Change Report v1.0 (Published for Consultation)
R0033 -. Final Change Report (Post Vote)
Company Name
EDF
Review status
Review required

New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS)

Date of latest update
Type
Change
ID
R0032
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/06/2023 - This change was implemented on 30 June 2023 as part of the June 2023 REC Release
Summary
This change seeks to deliver a recommendation from the Market-Wide Half Hourly Settlement Programme’s (MHHSP’s) Code Change and Development Group (CCDG), to introduce Registration Service Data Items that will be needed for MHHS, into the existing Supplier Meter Registration Service (SMRS) systems, before MHHS migration commences in October 2024.
Proposer
Colette Baldwin
Change Plan

Solution Analysis and Development

Completed

Start:

03 Feb 2022

Due:

09 May 2022

Completion:

09 May 2022

Service Provider Impact Assessment Issued

Completed

Start:

09 May 2022

Due:

13 May 2022

Completion:

13 May 2022

Party Impact Assessment Issued

Completed

Start:

13 May 2022

Due:

13 May 2022

Completion:

13 May 2022

Preliminary Change Report Issued

Completed

Start:

29 Jun 2022

Due:

29 Jul 2022

Completion:

29 Jul 2022

Consultation Issued

Completed

Start:

29 Jul 2022

Due:

05 Aug 2022

Completion:

05 Aug 2022

Final Change Report Issued

Completed

Start:

05 Aug 2022

Due:

08 Nov 2022

Completion:

08 Nov 2022

Additional Impact Assessment Issued

Completed

Start:

13 May 2022

Due:

29 Jun 2022

Completion:

29 Jun 2022

Responsible Committee Decision (Deferred from 20/09/22)

Completed

Start:

08 Nov 2022

Due:

15 Nov 2022

Completion:

15 Nov 2022
Status
Implementation Date
Status Superseded
EMAR Version 3.5.0_Superseded
Included changes Affected REC Items
R0101 Revision of the Implementation Date and approved solution for R0021
  • MOCoPA (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
R0102 Revision of the approved solution for R0032
  • Data Item Catalogue
  • Market Message Catalogue
R0114 Housekeeping amendments
  • REC Main Body
  • Schedule 1 - Interpretations and Definitions
  • Schedule 2 - REC Transition Schedule
  • Data Access Matrix (Electricity)
  • Data Access Matrix (Gas)
R0015 Remote communication obligations for electricity Advanced Meters
  • Schedule 14 - Metering Operations
R0010 New Meter Types for Auxiliary Proportional Controllers (APCs)
  • Data Item Catalogue
  • Market Message Catalogue
R0011 Reporting of Additional EMR Backing Data to Suppliers
  • Data Item Catalogue
  • Market Message Catalogue
R0021 Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier
  • MOCoPA (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
R0030 Erroneous Transfer Cancellations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Data Item Catalogue
  • Market Message Catalogue
R0066 Inclusion of SMRS Data Items in EES (BSC CP1568 Consequential Change)
R0032 New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS)
  • Data Item Catalogue
  • Market Message Catalogue
R0090 Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
4.64 MB
Version 1.0 - 02 Nov 2026 PPTX - 4.64 MB
1.0 02 Nov 2026
199.58 KB
Version 1.0 - 02 Nov 2026 PDF - 199.58 KB
1.0 02 Nov 2026
124.69 KB
Version 1.0 - 02 Nov 2026 PDF - 124.69 KB
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As an impacted Market Participant, I want to ensure good quality underlying data is available to support the transition to HH Settlements to avoid additional time and effort being spent fixing data quality issues during the migration period.
  2. As the MHHS Programme, I want Registration Data Items to be available ahead of the MHHS migration to enable data cleanse activity to be completed to address data quality issues.
Proposed Solution Document
Document title
R0032 Final Solution Documents
Upload document
Final Solution.zip
Archive
Off
Problem Statement
There are Registration Service Data Items that are critical to the MHHS rules and processes. The MHHS Programme is concerned that starting migration in October 2024 with poor underlying data quality would lead to avoidable time and effort being spent fixing issues during the 12-month migration period. To facilitate MHHS Programme data cleanse activity, prior to the transition to Half Hourly Settlement, Registration Service Data Items need to be introduced into the existing Supplier Meter Registration Service (SMRS) system and displayed in EES.
SME
SME Role
Lead Technical Analyst
CCDG_Transition_Consultation_v1.0-1.pdf
Proposed D0312 data flow with new data items.pdf (03.02.2022)
R0032 - CP form (Downloadable version)
R0032 - Change Proposal Plan v2.0 (Approved)
R0032 Initial Assessment Report v1.0 (Approved)
R0032 Consolidated First Impact Assessment Responses
R0032 Consolidated Second Impact Assessment Responses
R0032 - Preliminary Change Report V1.0 (Approved)
R0032 - Consolidated Consultation Responses
R0032 - Final Change Report v3.0 (Post-Vote)
Company Name
-
Review status
Review required

Altering the Trigger Points for CT Commissioning

Date of latest update
Type
Change
ID
R0031
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
-
Summary
-
Proposer
colette.baldwin
Change Plan

Preliminary Change Report Published

Completed

Start:

01 Feb 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Consultation Issued

Completed

Start:

08 Apr 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Consultation Period End

Completed

Start:

08 Apr 2022

Due:

04 May 2022

Completion:

04 May 2022

Final Change Report Published

Completed

Start:

04 May 2022

Due:

27 May 2022

Completion:

27 May 2022

Responsible Committee Decision

Completed

Start:

27 May 2022

Due:

10 Aug 2022

Completion:

10 Aug 2022
Impacted Consumers
Status
Implementation Date
Status Superseded
EMAR Version 3.2.0_Superseded
Included changes Affected REC Items
R0018 Complex Sites process improvements
  • Schedule 14 - Metering Operations
R0022 Amendment to REC Data Access Matrix
  • Schedule 12 - Data Access
  • Data Access Matrix (Electricity)
R0054 EES Access for Virtual Lead Parties
  • Schedule 1 - Interpretations and Definitions
R0031 Altering the Trigger Points for CT Commissioning
  • Schedule 14 - Metering Operations
  • Data Item Catalogue
  • Market Message Catalogue
R0033 Micro-business Smart Meter Installation Reports
  • Smart Meter Installation Schedule (since removed)
R0036 Extensive Housekeeping Amendments
  • MOCoPA (since removed)
  • Schedule 15 - Metering Accreditation
  • REC Main Body
  • ASPCoP (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 11 - Prepayment Arrangements
  • Schedule 6 - Performance Assurance
  • Schedule 19 - Market Exit and Supplier of Last Resort
  • Schedule 7 - Energy Theft Reduction
  • Schedule 5 - Change Management
  • Schedule 8 - Unbilled Energy Code of Practice
  • Schedule 4 - Company Governance
  • Schedule 17 - Secure Data Exchange
  • Schedule 28 - Related Metering Points
  • Schedule 3 - Accession Agreement
  • Schedule 18 - Green Deal Arrangements
  • Schedule 29 - Address Management
  • Schedule 13 - Transfer of Consumer Data
  • Smart Meter Installation Schedule (since removed)
  • Gas Metering Code of Practice (since removed)
  • Schedule 9 - Qualification and Maintenance
  • Schedule 2 - REC Transition Schedule
  • Schedule 26 - Switching Service Management
  • Schedule 12 - Data Access
  • Schedule 24 - Switching Data Management
  • Schedule 10 - Charging Methodology
  • Schedule 23 - Registration Services
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Schedule 25 - Central Switching Service
  • Data Access Matrix (Electricity)
  • Data Access Matrix (Gas)
  • Data Item Catalogue
  • Market Message Catalogue

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
colette.baldwin
Solution Development
Proposed solution summary
  1. As the DNO, I only want to send the commissioning information using the D0383 (MM00370) when I am made aware that the site has now been energised by the Registered Supplier’s MEM for a CT Pre-commissioned meter, so that I can meet my regulatory obligations under the BSC
  2. As a MEM I want to receive the information from the DNO in a timely manner to ensure my records are accurate and up to date, and that I can provide the Registered Supplier with information to ensure the metering point is accurately settled.
Proposed Solution Document
Document title
R0031 Proposed Draft Legal Text
Upload document
R0031 - Legal Text Altering the Trigger Point for CT Commisioning v1.0.docx
Archive
Off
Problem Statement
The Balancing & Settlement Code Procedure (BSCP) 515 and the Retail Energy Code (REC) Metering Operations Schedule set out the obligations and timescales imposed on the DNO to send commissioning information to the MEM (using the D0383 (MM00370) data flow), where the DNO has installed metering equipment, with Measurement Transformers. When the DNO installs Low Voltage Current Transformer (LV CT) metering units, that have been pre-commissioned off-site, the commissioning of the units is done before installation and separately to the Energisation of the Supply. When the Energisation status change is the responsibility of the Registered Supplier and is requested of the MEM using the D0134 data flow, notification of the change in energisation status is then sent to the Registered Supplier and the DNO by the MEM, using the D0139 (MM00036) For an LV fused supply, the DNO may not be aware of who the MEM is to send the commissioning information to via a D0383 (MM00370) until a D0139 (MM00036) is received. This is often the point at which the DNO first becomes aware that a fused supply is now Energised. This may be several days/weeks/months after DNO commissioning, and it is proving difficult for the DNO to meet their BSC obligations.
R0031 - CP form (Downloadable version)
R0031 - PCR Altering the Trigger Point for CT Commissioning
R0031 - Final Change Report (Post Vote - Approved)
R0031 - IAR Altering the Trigger Point for CT Commissioning V1.0 (Approved)
R0031 - CPP Altering the Trigger Point for CT Commissioning v1.0 (Approved)
R0031 - Consolidated Consultation Responses v1.0
Company Name
-
Review status
Review required