Missing Scenario Variants in D0179

Date of latest update
Type
Change
ID
R0235
Change Category
Change Path
Priority
Urgent
No
Latest Update
01/07/2025 - On 01 July 2025, the REC Change Panel voted to reject R0235 and approve R0235A, in line with the Code Manager's recommendation. The appeal window has closed.
Summary
Within MHHS SIT there is a scenario where the LDSO generates a D0139 to the MS for a PPM but the requirement is for the MS to generate a D0179. There is a gap in the D0179 data required and that provided on the D0139. 21.5.1 & 21.5.6 under Schedule 14 states that where the DNO changes the energisation status, within 3 WD of changing the energisation status the DNO will send the D0139 or the D0179(21.5.6) to the MS and then the MS will generate the D0179 to the Supplier(21.5.6). Currently, the LDSO only generates the D0179 to the Supplier but not to the MOP and the only change under MHHS is to add the new variant MSS.
Proposer
Patricia Parker
Change Plan

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

04 Mar 2025

Presented at Change Issues Group

Completed

Start:

Due:

Completion:

06 Mar 2025

Presented at Change Issues Group

Completed

Start:

Due:

Completion:

01 May 2025

Presented at REC Change Panel

Completed

Start:

Due:

Completion:

20 May 2025
Impacted Consumers
Impacted REC Documents
Status
Implementation Date
Status Superseded
EMAR Version 4.2.0_Superseded
Included changes Affected REC Items
R0179 Proposal for Limiting Queries in EES API Calls (Single Query per API Call)
R0190 Related Meter Point RMP status rules
  • Schedule 28 - Related Metering Points
R0198 Metering Asset Manager (MAM) Communication Method Register
R0242 Missing Scenario Variant from R0043
  • Market Message Catalogue
R0244 C21 to be introduced into STIRG Document
  • Data Item Catalogue
R0235A Missing Scenario Variants in D0179 Alternate Solution
R0256 MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101
  • Market Message Catalogue
R0270 Clarification of SIP Qualification Requirements
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 15 - Metering Accreditation
R0271 Clarification of ASP, AMI, and EMO Accession Requirements
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
R0272 Enabling transparency of the CRS Provider’s REC service level performance
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 26 - Switching Service Management
  • Schedule 24 - Switching Data Management
R0277 Data Latency SLA Alignment for Gas Enquiry Service
  • Schedule 1 - Interpretations and Definitions
R0280 CSS Certificate Authority audit clarification
  • Schedule 1 - Interpretations and Definitions
R0283 Annual Address Management Plan Updates
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 29 - Address Management
R0287 Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 23 - Registration Services
R0293 Housekeeping February 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0235 D0179 Missing Scenario Variants
Upload document
I0235 D0179 Missing Scenario Variants.pdf
Archive
Off
Document title
R0235 Data Specification V0.2
Upload document
I0235 D0179 Missing Scenario Variants V0.2.pdf
Archive
Off
Problem Statement
DNOs and MOAs cannot fulfil their full obligations listed in Schedule 14 Metering Operations as there missing Scenario Variants in the Data Specification preventing them from sending the D0179 to all required Parties.
Stages Selection
I0235 Change Proposal Form
I0235 Change Report (Proposal Plan) V1.0 Approved 04.03.25
I0235 Consolidated Impact Assessment Responses V1.0
R0235 and R0235A Change Report (For Consultation) V1.1
R0235 and R0235A Consolidated Consultation Responses PUBLIC V1.0
R0235 and R0235A Change Report (Final Recommendation) V2.0 (Approved) 01.07.2025
Company Name
ESG Global
Review status
Review required

Adding the DIP Rules to the Cross Code Steering Group Terms of Reference

Date of latest update
Type
Change
ID
R0208
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented on 28 February 2025.
Summary
The Data Integration Platform (DIP) will take on a key role within the electricity industry so the DIP Manager, as the Code Manager equivalent organisation responsible for the DIP and associated DIP Rules, needs to be recognised as a Cross Code Steering Group (CCSG) member.
Proposer
Lorna Mallon
Change Plan

Proposal Plan approved

Completed

Start:

29 Aug 2024

Due:

01 Oct 2024

Completion:

01 Oct 2024

Consultation published

Completed

Start:

01 Oct 2024

Due:

04 Oct 2024

Completion:

01 Oct 2024

Change Report - Final Recommendation

Completed

Start:

04 Oct 2024

Due:

21 Nov 2024

Completion:

22 Nov 2024
Status
Implementation Date
Status Superseded
EMAR Version 3.16.0_Superseded

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Draft CCSG - Terms of Reference
Upload document
Draft CCSG - Terms of Reference v1.1.pdf
Archive
Off
Problem Statement
The current CCSG Terms of Reference (ToR) do not recognise the role of the DIP Manager introduced as part of the MHHS Programme.
Change Proposal Form
R0208 - Change Report 1.0 (Consultation) 01.10.2024
R0208 Consolidated Consultation Responses
R0208 - Change Report 1.0 (Post Vote)
Company Name
Gemserv
Review status
Review required

Performance Assurance Report Catalogue Updates (MHHS)

Date of latest update
Type
Change
ID
R0202
Change Category
Change Path
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the REC Release on 27 June 2025.
Summary
This change seeks to update the Performance Assurance Reporting Catalogue (PARC) to capture data items required to continue to appropriately monitor Retail Risks under Market-wide Half Hourly Settlement (MHHS) industry arrangements. Some housekeeping changes, for the PARC, have also been included in this change.
Proposer
Andrew Waghorn
Change Plan

Proposal Plan approved

Completed

Start:

08 Aug 2024

Due:

03 Sep 2024

Completion:

03 Sep 2024

Party impact assessment completed

Completed

Start:

03 Sep 2024

Due:

04 Oct 2024

Completion:

04 Oct 2024

Change Report approved for Consultation

Completed

Start:

04 Oct 2024

Due:

25 Mar 2025

Completion:

25 Mar 2025

Consultation completed

Completed

Start:

25 Mar 2025

Due:

15 Apr 2025

Completion:

15 Apr 2025

RECPAB Voting

In Progress

Start:

15 Apr 2025

Due:

29 Apr 2025

Completion:

Status
Implementation Date
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Harriet Truss
Solution Development
Proposed Solution Document
Document title
03 RECPAB_24_0827_04E Draft changes to the PARC for MHHS (27.08.2024)
Upload document
03 RECPAB_24_0827_04E Draft changes to the PARC for MHHS.xlsx
Archive
Off
Document title
R0202 RECPAB_23_PARC V5.2 - REDLINE MHHS - MEM only (18.03.2025)
Upload document
R0202 RECPAB_23_PARC V5.2 - REDLINE MHHS - MEM only 18.03.2025.xlsx
Archive
Off
Document title
R0202 RECPAB_23_PARC V5.2 - REDLINE MHHS - MEM only APPROVED 29.04.2025
Upload document
R0202 RECPAB_23_PARC V5.2 - REDLINE MHHS - MEM only APPROVED 29.04.2025.xlsx
Archive
Off
Problem Statement
The PARC currently does not capture all the data items required to support the monitoring of Retail Risks following Market-wide Half Hourly Settlement go-live. An update to the PARC is required to include the data items that will ensure the Code Manager can provide the assurance the industry requires during transition and under the new MHHS arrangements.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
SME Role
Lead Assurance Analyst
SME User
awaghorn@deloitte.co.uk
RECPAB_23_Performance Assurance Report Catalogue V5.2 - REDLINE.xlsx
R0202 - PARC Updates (MHHS) (CP Form)
R0202 Change Proposal Re-Plan v1.0 31.10.24
R0202 Change Report (Proposal Plan) v2.0 (Approved) 03.09.2024
R0202 Change Proposal Re-Plan V2.0 (Approved) 20.03.2025
R0202 Change Report (Consultation) v1.0 (Approved) 25.03.2025
R0202 Consolidated Consultation Responses V1.1 (22.04.2025)
R0202 Change Report (Final Recommendation) (Post-Vote) v2.0
Company Name
Code Manager
Review status
Review required

Metering Asset Manager (MAM) Communication Method Register

Date of latest update
Type
Change
ID
R0198
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
Studies conducted by the REC Performance Assurance (RPA) function of the REC Code Manager have concluded that gas market data fidelity may be improved by reducing the frequency of missed messages between Metering Asset Managers and other REC Parties. This Issue seeks to explore mechanisms by which a reduction in the number of permissible communication methods used by MAMs could support the data quality improvement objective.
Proposer
Amy Crowe-Lamont
Status
Implementation Date
Status Superseded
EMAR Version 4.2.0_Superseded
Included changes Affected REC Items
R0179 Proposal for Limiting Queries in EES API Calls (Single Query per API Call)
R0190 Related Meter Point RMP status rules
  • Schedule 28 - Related Metering Points
R0198 Metering Asset Manager (MAM) Communication Method Register
R0242 Missing Scenario Variant from R0043
  • Market Message Catalogue
R0244 C21 to be introduced into STIRG Document
  • Data Item Catalogue
R0235A Missing Scenario Variants in D0179 Alternate Solution
R0256 MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101
  • Market Message Catalogue
R0270 Clarification of SIP Qualification Requirements
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 15 - Metering Accreditation
R0271 Clarification of ASP, AMI, and EMO Accession Requirements
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
R0272 Enabling transparency of the CRS Provider’s REC service level performance
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 26 - Switching Service Management
  • Schedule 24 - Switching Data Management
R0277 Data Latency SLA Alignment for Gas Enquiry Service
  • Schedule 1 - Interpretations and Definitions
R0280 CSS Certificate Authority audit clarification
  • Schedule 1 - Interpretations and Definitions
R0283 Annual Address Management Plan Updates
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 29 - Address Management
R0287 Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 23 - Registration Services
R0293 Housekeeping February 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
Lydia Bentley
Solution Development
Proposed Solution Document
Document title
I0198 - Draft Schedule 14 - Metering Operations & Draft Communications Method Register
Upload document
I0198 Proposed Solution V1.0.zip
Archive
Off
Document title
R0198 - Draft Schedule 14 - Metering Operations & Draft Communications Method Register V2.0
Upload document
R0198 Proposed Solution V2.0.zip
Archive
Off
Problem Statement
MAMs communicate with each other, and with other parties, using up to three possible methods as they send Market Messages in line with their obligations in the REC. It has been suggested that moving to a single communication method might help mitigate gas data quality issues. This Issue seeks to explore an interim solution to facilitate this.
SME
SME Role
Lead Assurance Analyst
SME User
beth.brown@capgemini.com
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
I0198 Change Proposal (pdf)
I0198 Change Report (Plan) (Approved) V2.0 03.04.2
I0198 Change Proposal Re-Plan V1.0 28.03.25
I0198 Change Report (IA) V1.0 03.04.25
R0198 Consolidated IA Responses V1.0 Non-Confidential
R0198 Change Report (Consultation) V1.0 11.06.25
R0198 Change Proposal Re-Plan V2.0 02.07.25
Change Report (Consultation) V2.0 11.07.25
R0198 Consolidated Consultation Responses V1.0 06.08.25
R0198 Change Report (Final Recommendation: Pre-Vote) V1.1 13.08.25
R0198 Change Report (Final Reccomendation - Post-Vote) V1.0 13.08.25
Company Name
-
Review status
Review required

CSS Change to Allow Prevent of Registration by Market Segment

Date of latest update
Type
Issue
ID
I0194
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
06/05/2025 - Code Manager presented solution development outcomes to Technical Change Panel on 30/04/2025 and confirmed that the issue has been resolved and will not be progressed further. An operational process will be put in place for the monitoring of Registrations by Market Segment.
Summary
To prevent a Supplier with exemptions in place that were approved, in BSC and REC PAB for Smart and Unmetered, from registering meter points other than those that they are Qualified in.
Proposer
Matt Cogram
Change Plan

Change Proposal Plan approved

Completed

Start:

25 Jul 2024

Due:

03 Dec 2024

Completion:

03 Dec 2024

Definition

In Progress

Start:

03 Dec 2024

Due:

28 Feb 2025

Completion:

Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Harriet Truss
Solution Development
Proposed Solution Document
Document title
I0194 - Solution Report v1.0 23.04.2025
Upload document
I0194 - Solution Report v1.0 23.04.2025.pdf
Archive
Off
Problem Statement
Suppliers who do not operate, or intend to operate, in the Smart or Unmetered Market Segments, will be seeking exemptions from the relevant MHHS Qualification requirements. At present, there is no mechanism in CSS to prevent Suppliers from registering Metering Points for which an exemption has been granted and for which they are therefore not qualified.
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
PAB281_01A_Modification Proposal Form.docx
I0194 - CSS Change to Allow Prevent of Registration by Market Segment.docx
PAB281_01_Request for Exemption from Suppliers v2.0.docx
352_04_Initial Written Assessment - v1.0.docx
I0194 Proposal Plan Change Report V2.0 (Approved) 03.12.2024.pdf
I0194 - Change Proposal Re-Plan v1.0 (Approved) 27.02.2025
Company Name
Elexon
Review status
Review required

Clarity on use of on hold for switching issues, including the obligations of CSS Users

Date of latest update
Type
Change
ID
R0180
Change Category
Change Path
Priority
Urgent
No
Latest Update
06/11/26 - This Change Proposal has been implemented as part of the 6 November 2026 REC Release.
Summary
Many Switching Incidents are on hold waiting for resolution. The Switching Operator puts these tickets on hold, which is an approved business process from the Switching Programme. This is not reflected in the obligations on SDSPs or other REC Service Providers, where there is no on hold concept. Further there are no obligations on CSS Users to respond in a timely basis. This means that the REC obligations do not reflect current practice, and many tickets remain open much longer than necessary.
Proposer
anton.moden
Change Plan

Change Issue Group

Completed

Start:

03 Jun 2024

Due:

01 Aug 2024

Completion:

01 Aug 2024
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 4.4.0
Included changes Affected REC Items
R0180 Clarity on use of on hold for switching issues, including the obligations of CSS Users
  • Schedule 26 - Switching Service Management
R0207 Import / Export MOA Charging Clarification
  • Schedule 14 - Metering Operations
R0253 Theft - DNO/Networks not providing photos
  • Schedule 8 - Unbilled Energy Code of Practice
R0261 Addition of Export flag in D0303 flows
R0266 REC Data Specification Clarifications
  • Schedule 14 - Metering Operations
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Data Item Catalogue
  • Market Message Catalogue
R0317 Number of Displayed Register Digits Data Item linkage
R0328 Removal of D0383 & D0384 requirements from Sharing MTDs process
  • Schedule 14 - Metering Operations
R0336 Legal text to support REC Change R0180
  • Schedule 26 - Switching Service Management
R0343 MSC - Amending Statement Production Timescales
R0345 Housekeeping November 2026

Documents

Name Version Last updated Actions
331.85 KB
Version 1.0 - 11 Nov 2026 PDF - 331.85 KB
1.0 11 Nov 2026
1.0 11 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Option 1
Upload document
Option 1.zip
Archive
Off
Document title
Solution Development Report
Upload document
Solution Development Report.pdf
Archive
Off
Document title
Option 2
Upload document
Option 2.zip
Archive
Off
Document title
Option 3
Upload document
Option 3.zip
Archive
Off
Problem Statement
A lack of obligations is causing issues with open tickets relating to missing messages. Tickets placed on hold also require significant additional work for the Switching Operator, which could either be released as a cost saving or it could result in time freed up for improvement activities.
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
Issue Form
Change Report - Proposal Plan V1.0
I0180 Extension to Plan V1.0 approved 09.07.25
I0180 Consolidated Party Impact Assessment Responses v1.0
I0180 Update to Plan V1.0 approved 10.12.25
R0180 Change Report (For Consultation) V1.0
R0180 Consolidated consultation responses V1.0
R0180 Change Report (Final Recommendation) V1.0 approved 25.03.26
Company Name
REC Code Manager
Review status
Review required

Change Smart Meter Installation Consumer Survey Specification survey questions to a REC Category 2 document

Date of latest update
Type
Change
ID
R0177
Change Category
Change Path
Priority
Urgent
No
Latest Update
This change was implemented on 06 September 2024.
Summary
Adding the Smart Meter Installation Consumer Survey Specification questions to the REC list of documents will allow any amendments to follow the REC change process and allow anyone to propose such amendments.
Proposer
Lorna Mallon
Change Plan

Preliminary Change Report published

Completed

Start:

22 May 2024

Due:

05 Jul 2024

Completion:

04 Jul 2024

Consultation opened

Completed

Start:

05 Jul 2024

Due:

05 Jul 2024

Completion:

04 Jul 2024

Consultation closes

Completed

Start:

05 Jul 2024

Due:

26 Jul 2024

Completion:

26 Jul 2024

Final Change Report published

Completed

Start:

26 Jul 2024

Due:

09 Aug 2024

Completion:

08 Aug 2024

Change Panel decision

Completed

Start:

09 Aug 2024

Due:

20 Aug 2024

Completion:

20 Aug 2024
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 3.13.0_Superseded

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Domestic or Micro-Business Consumer, I want the Smart Meter Installation survey questions to have robust governance, so I have confidence the right KPIs are being monitored.
  2. As an Energy Supplier, I want the Smart Meter Installation survey questions to be governed by the REC Change Process, so I can suggest and provide feedback on changes to them.
Proposed Solution Document
Document title
REC Baseline Statement DRAFT
Upload document
REC Baseline Statement DRAFT.xlsx
Archive
Off
Problem Statement
The Smart Meter Installation Consumer Survey Specification questions are mandatory for Energy Suppliers to use, but there is no mechanism for Energy Suppliers to raise changes or issues against the questions as they are not held in the REC Baseline Statement.
R0177 Change Proposal Form
R0177 Change Proposal Plan v1.0 Approved
R0177 Initial Assessment Report v1.0 Approved
R0177 Preliminary Change Report v1.0
R0177 Consolidated Consultation Responses v1.0
R0177 Change Report (Final Recommendation) V1.1
Company Name
Gemserv
Review status
Review required

Change Process Improvements following Code Manager review

Date of latest update
Type
Change
ID
R0167
Change Category
Change Path
Priority
Urgent
No
Latest Update
19/07/24 - This change was implemented on the 19 July 2024.
Summary
This Change Proposal has been raised to make the required changes to Schedule1 and Schedule 5, to enable process enhancements to be made to support Change Process Improvements project.
Proposer
Helen Fosberry
Change Plan

Preliminary Change Reports Published

Completed

Start:

25 Apr 2024

Due:

17 May 2024

Completion:

17 May 2024

Consultation Published

Completed

Start:

17 May 2024

Due:

17 May 2024

Completion:

17 May 2024

Final Change Report Published

Completed

Start:

17 May 2024

Due:

07 Jun 2024

Completion:

25 Jun 2024

Responsible Committee Decison

Completed

Start:

07 Jun 2024

Due:

18 Jun 2024

Completion:

02 Jul 2024
Status
Implementation Date
Status Superseded
EMAR Version 3.11.1_Superseded
Included changes Affected REC Items
R0167 Change Process Improvements following Code Manager review

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I want REC issues and changes that impact Consumers to be developed with Parties and Market Participants input, with minimal delay or hassle, so that I can benefit from positive Consumer outcomes at the earliest opportunity.
  2. As a REC Party or Market Participant, I want to participate effectively and efficiently in the REC Change Process including the development and progression of industry issues, to shape and develop solutions.
Proposed Solution Document
Document title
R0167 - Final Legal Text
Upload document
R0167 - Final Legal Text.zip
Archive
Off
Problem Statement
Feedback gathered has highlighted issues with the current process including speed of the process, engagement, and inefficiencies. Amendments are required to Schedule 1 and Schedule 5, that will support the provision of a suite of enhancements to the Change Process.
Change Proposal Form
R0167 - Change Proposal Plan (Approved)
R0167 - Initial Assessment Report (Approved)
R0167 - Preliminary Change Report v1.1 (Published for Consultation)
R0167 Consolidated Consultation Responses
R0167 Final Change Report v1.0 (Post Vote)
Company Name
REC Code Manager
Review status
Review required

Removal of the Green Deal Panel

Date of latest update
Type
Change
ID
R0166
Change Category
Change Path
Priority
Urgent
No
Latest Update
23/08/2024 - This change was successfully implemented as part of the August 2024 Extraordinary REC Release on 23 August 2024.
Summary
This Change Proposal seeks to remove the Green Deal Panel Terms of Reference from the REC Baseline Statement and product set, and to amend the Change Panel Terms of Reference to incorporate consideration of Green Deal business.
Proposer
Paul Rocke
Change Plan

Preliminary Change Report Published

Completed

Start:

22 Apr 2024

Due:

09 May 2024

Completion:

09 May 2024

Consultation Issued

Completed

Start:

09 May 2024

Due:

09 May 2024

Completion:

09 May 2024

Final Change Report Issued

Completed

Start:

09 May 2024

Due:

07 Jun 2024

Completion:

07 Jun 2024

Responsible Committee Decision

Completed

Start:

07 Jun 2024

Due:

18 Jun 2024

Completion:

18 Jun 2024
Status
Implementation Date
Status Superseded
EMAR Version 3.12.0_Superseded

Documents

Name Version Last updated Actions
159.49 KB
Version 1.0 - 02 Nov 2026 PDF - 159.49 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a party I want Green Deal matters, should they arise to be dealt with in a timely fashion. This could be difficult under the current arrangements where it is not possible to get a quorate panel to make decisions.
Proposed Solution Document
Document title
REC Change Panel - Terms of Reference - Red-lined
Upload document
REC Change Panel - Terms of Reference - Red-lined. V0.2.pdf
Archive
Off
Problem Statement
Since the REC was established, no business has been raised that would require the Green Deal Panel to meet and therefore the group has not yet convened. As well as being an unnecessary administrative consideration, it is a challenge to keep the Members and Chair abreast of the wider REC Change Process, and the Green Deal Panel may therefore find it more challenging to discharge its functions in the event that it needs to be convened.
Change Proposal Form
R0166 - Change Proposal Plan v1.0 (Approved)
R0166 - Initial Assessment Report (Approved)
R0166 - Preliminary Change Report V1.0
R0166 Final Change Report v1.0
Company Name
REC Code Manager
Review status
Review required

House Keeping Amendment to the PARC

Date of latest update
Type
Change
ID
R0159
Change Category
Change Path
Priority
Urgent
No
Latest Update
This change was implemented as part of the the Extraordinary release on 28 March 2024.
Summary
The Code Manager has identified a typographical error in the approved legal text for the Performance Assurance Report Catalogue (PARC) as part of the implementation of R0149 Prepayment Levelisation. In the PARC drafting, R0147 has specified the Code Manager (RTS) as providing the new data submission report that is part of the R0147 solution. However, RTS will be acting for RECCo in provision of this report and not RTS as the Code Manager.
Proposer
Holly Law
Change Plan

Final Change Report Issued

Not Started

Start:

07 Mar 2024

Due:

14 Mar 2024

Completion:

14 Mar 2024

Responsible Committee Decision

Not Started

Start:

14 Mar 2024

Due:

26 Mar 2024

Completion:

26 Mar 2024
Status
Implementation Date
Status Superseded
EMAR Version 3.9.0
Included changes Affected REC Items
R0147 Prepayment Levelisation
  • Schedule 1 - Interpretations and Definitions

Documents

Name Version Last updated Actions
184.95 KB
Version 1.0 - 16 Nov 2026 PDF - 184.95 KB
1.0 16 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Copy of RECPAB_23_Performance Assurance Report Catalogue V5.1.1 Redline (1).xlsx
Upload document
Copy of RECPAB_23_Performance Assurance Report Catalogue V5.1.1 Redline (1).xlsx
Archive
Off
Problem Statement
This Housekeeping Change Proposal seeks to make typographical corrections that have been identified and improve consistency across the REC.
Workgroup
Workgroup(s)
Performance Assurance Report Catalogue
R0159 - Housekeeping Change Report v1.1- APPROVED
Company Name
Code Manager RPS
Review status
Review required