Introducing a Process to Provide Updates During Fault Resolutions

Date of latest update
Type
Issue
ID
I0197
Change Category
Priority
Urgent
No
Latest Update
10/06/2026 - The Code Manager, following an approval to an Update to Plan by the REC Metering Expert Panel, has placed I0197 on hold.
Summary
Some customers have had faulty meters for a prolonged period, which impacts billing and settlement, and can prevent customers accessing specific tariffs. Currently the REC only has obligations relating to electricity meter faults, and these do not actually require work to be done to address faults. This issues proposes the introduction a maximum timeframe Fault Resolution deadline to resolve issues around faulty meters.
Proposer
Amy Crowe-Lamont
Change Report - Initial Assessment and Change Plan Report
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
James Hardy
Solution Development
Problem Statement
Consumers have had faulty meters for a prolonged period, which impacts billing and settlement, and can prevent customers accessing specific tariffs.
SME
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
I0197 - Change Proposal Form
I0197 - Change Report (Proposal Plan) V1.0 (Approved) 03.06.2025
I0197 - Update to Plan V3.0 (On Hold) 03.06.2026
Company Name
-
Review status
Review required

Metering Asset Manager (MAM) Communication Method Register

Date of latest update
Type
Change
ID
R0198
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
Studies conducted by the REC Performance Assurance (RPA) function of the REC Code Manager have concluded that gas market data fidelity may be improved by reducing the frequency of missed messages between Metering Asset Managers and other REC Parties. This Issue seeks to explore mechanisms by which a reduction in the number of permissible communication methods used by MAMs could support the data quality improvement objective.
Proposer
Amy Crowe-Lamont
Status
Implementation Date
Status Superseded
EMAR Version 4.2.0_Superseded
Included changes Affected REC Items
R0179 Proposal for Limiting Queries in EES API Calls (Single Query per API Call)
R0190 Related Meter Point RMP status rules
  • Schedule 28 - Related Metering Points
R0198 Metering Asset Manager (MAM) Communication Method Register
R0242 Missing Scenario Variant from R0043
  • Market Message Catalogue
R0244 C21 to be introduced into STIRG Document
  • Data Item Catalogue
R0235A Missing Scenario Variants in D0179 Alternate Solution
R0256 MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101
  • Market Message Catalogue
R0270 Clarification of SIP Qualification Requirements
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 15 - Metering Accreditation
R0271 Clarification of ASP, AMI, and EMO Accession Requirements
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
R0272 Enabling transparency of the CRS Provider’s REC service level performance
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 26 - Switching Service Management
  • Schedule 24 - Switching Data Management
R0277 Data Latency SLA Alignment for Gas Enquiry Service
  • Schedule 1 - Interpretations and Definitions
R0280 CSS Certificate Authority audit clarification
  • Schedule 1 - Interpretations and Definitions
R0283 Annual Address Management Plan Updates
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 29 - Address Management
R0287 Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 23 - Registration Services
R0293 Housekeeping February 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
Lydia Bentley
Solution Development
Proposed Solution Document
Document title
I0198 - Draft Schedule 14 - Metering Operations & Draft Communications Method Register
Upload document
I0198 Proposed Solution V1.0.zip
Archive
Off
Document title
R0198 - Draft Schedule 14 - Metering Operations & Draft Communications Method Register V2.0
Upload document
R0198 Proposed Solution V2.0.zip
Archive
Off
Problem Statement
MAMs communicate with each other, and with other parties, using up to three possible methods as they send Market Messages in line with their obligations in the REC. It has been suggested that moving to a single communication method might help mitigate gas data quality issues. This Issue seeks to explore an interim solution to facilitate this.
SME
SME Role
Lead Assurance Analyst
SME User
beth.brown@capgemini.com
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
I0198 Change Proposal (pdf)
I0198 Change Report (Plan) (Approved) V2.0 03.04.2
I0198 Change Proposal Re-Plan V1.0 28.03.25
I0198 Change Report (IA) V1.0 03.04.25
R0198 Consolidated IA Responses V1.0 Non-Confidential
R0198 Change Report (Consultation) V1.0 11.06.25
R0198 Change Proposal Re-Plan V2.0 02.07.25
Change Report (Consultation) V2.0 11.07.25
R0198 Consolidated Consultation Responses V1.0 06.08.25
R0198 Change Report (Final Recommendation: Pre-Vote) V1.1 13.08.25
R0198 Change Report (Final Reccomendation - Post-Vote) V1.0 13.08.25
Company Name
-
Review status
Review required
Schedule 14 - Metering Operations 5.0 – Implemented on
Market Participant Applicability
Market participant All Sections
Domestic Suppliers Mandatory
Non-Domestic Suppliers Mandatory
Gas Transporters Mandatory
Distribution Network Operators Mandatory
DCC N/A
Metering Equipment Managers Mandatory
Non-Party REC Service Users N/A
Loading...

Gas Meter Type Code - Thermal Mass Measurement

Date of latest update
Type
Issue
ID
I0184
Urgent
No
Latest Update
16/10/2024 - This Change Issue has been withdrawn at the request of the proposer.
Summary
Empty
Proposer
Joey Manners
Status
Implementation Status
Date Raised
Lead Analyst
Lydia Bentley
Solution Development
Stages Selection
Stages Selection
I0184 - Change Proposal Form (PDF)
Company Name
Octopus Energy Ltd
Review status
Review required

Schedule 14 - Metering Operations Footnote Review

Date of latest update
Type
Change
ID
R0181
Change Category
Change Path
Priority
Urgent
No
Latest Update
23/08/2024 - This change was successfully implemented as part of the August 2024 Extraordinary REC Release on 23 August 2024.
Summary
The footnotes within Schedule 14 - Metering Operations are not in the correct place, are missing or no longer relevant. This Change Proposal looks to correct issues within the footnotes and move them into the legal text to prevent this from happening when future Change Proposals impacting this schedule are implemented.
Proposer
Holly Law
Change Plan

Change Proposal Plan and Impact Assessment Report issued

Completed

Start:

06 Jun 2024

Due:

18 Jun 2024

Completion:

18 Jun 2024

Preliminary Change Report issued

Completed

Start:

18 Jun 2024

Due:

19 Jun 2024

Completion:

19 Jun 2024

Consultation issued

Completed

Start:

19 Jun 2024

Due:

19 Jun 2024

Completion:

19 Jun 2024

Consultation Close

Completed

Start:

19 Jun 2024

Due:

10 Jul 2024

Completion:

10 Jul 2024

Final Change Report Issued

Completed

Start:

10 Jul 2024

Due:

11 Jul 2024

Completion:

11 Jul 2024

Responsible Committee Decision

Completed

Start:

11 Jul 2024

Due:

19 Jul 2024

Completion:

19 Jul 2024

Appeal Window Closure

Not Started

Start:

19 Jul 2024

Due:

02 Aug 2024

Completion:

Status
Implementation Date
Status Superseded
EMAR Version 3.12.0_Superseded

Documents

Name Version Last updated Actions
159.49 KB
Version 1.0 - 02 Nov 2026 PDF - 159.49 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
holly.law
Solution Development
Proposed Solution Document
Document title
Metering Operations v4.1 footnote review legal drafting for PCR
Upload document
Metering Operations v4.1 footnote review - PCR.docx
Archive
Off
Document title
Metering Operations v4.1 footnote review legal drafting for FCR
Upload document
Metering Operations v4.1 footnote review - FCR (2).docx
Archive
Off
Problem Statement
REC parties are unable to ensure their processes and procedures correctly reflect their obligations as the footnotes within Schedule 14 - Metering Operations are not in the correct place, are missing or no longer relevant.
R0181 Change Proposal Plan (Approved) 18.06.2024
R0181 Initial Assessment Report (Approved) 18.06.2024
R0181 Preliminary Change Report
Consolidated Consultation Responses
R0181 Final Change Report - approved 22.07.24
Company Name
Code Manager
Review status
Review required

Removal of Facsimile as a Method of Code Communication

Date of latest update
Type
Change
ID
R0157
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
The Public Switched Telephone Networks (PSTN) will be switched off in December 2025 by all telecom companies and will be replaced with an Internet Protocol (IP) digital network. Existing fax machines that are incompatible with new all IP digital networks will become obsolete and no longer capable of meeting Code Communications as prescribed in the REC. All communication methods referencing fax or facsimile will need to be removed and replaced with email (where this is not an existing option), unless an alternative form of communication is needed. Please note: The government have published preparatory guidance which includes migrating to IP-supported technology in advance of the planned decommissioning. UK transition from analogue to digital landlines - GOV.UK (www.gov.uk) Critical National Infrastructure (CNI) (“assets, facilities, systems, networks or processes and the essential workers that operate and facilitate them”) which is subdivided into 13 sectors including Energy, are advised to consider how they move to digital alternatives smoothly to avoid unnecessary interruption following the PSTN switch-off. Openreach's Energy Guidance Factsheet can be found in the CPs Accompanied Documents.
Proposer
Colette Baldwin
Change Plan

Preliminary Change Report and Consultation Issued

Completed

Start:

03 Jan 2024

Due:

09 Feb 2024

Completion:

09 Feb 2024

Final Change Report Issued

Completed

Start:

23 Feb 2024

Due:

12 Mar 2024

Completion:

12 Mar 2024

Responsible Committee Decision

Completed

Start:

12 Mar 2024

Due:

19 Mar 2024

Completion:

19 Mar 2024

Appeal Window Closure

Not Started

Start:

19 Mar 2024

Due:

02 Apr 2024

Completion:

Consultation Close

Completed

Start:

09 Feb 2024

Due:

23 Feb 2024

Completion:

23 Feb 2024
Impacted Consumers
Impacted REC Services
Status
Implementation Date
Status Superseded
EMAR Version 4.1.0_Superseded
Included changes Affected REC Items
R0152 Revision to the Consolidated Metering Code of Practice (CoMCoP)
  • MOCoPA (since removed)
  • ASPCoP (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Smart Meter Installation Schedule (since removed)
  • Gas Metering Code of Practice (since removed)
R0157 Removal of Facsimile as a Method of Code Communication
  • Schedule 14 - Metering Operations
  • Schedule 18 - Green Deal Arrangements
  • Standards Definition Document
  • Data Item Catalogue
R0191 Introduction of SLA for Supplier De-Registration on Disconnected Meters
  • Schedule 27 - RMP Lifecycle
R0205 Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches
R0212 Protecting Crimestoppers and their Contacts
R0215 Schedule 30 Switch Meter Reading Problems - Rejections and Timings
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
R0060 ERDS Service Definition timezone correction
  • Schedule 1 - Interpretations and Definitions
R0232 Non-Domestic Change of Occupier SDEP Screens (R0155 Solution)
R0243 Transfer of Standard Settlement Configuration and Time Pattern Regime Data Item Ownership
  • Data Item Catalogue
R0248 REC Changes to tie in with DCP451 - Suspending Registrations
  • Schedule 24 - Switching Data Management
R0254 Non-Domestic Change of Occupier Reporting (R0155 Solution)
R0255 Terms of Reference Updates
R0257 Change to REC for Data processing outside of EEA
R0263 Sharing Confirmed Energy Theft Data with the BSCCo
  • Schedule 7 - Energy Theft Reduction
R0269 Schedule 5 – Change Management: Clarity and Typographical Review
  • Schedule 1 - Interpretations and Definitions
  • Schedule 5 - Change Management
R0279 Housekeeping November 2025
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 7 - Energy Theft Reduction
  • Schedule 27 - RMP Lifecycle
  • Schedule 18 - Green Deal Arrangements
  • Schedule 24 - Switching Data Management
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Market Message Catalogue
R0227 Domestic Elective HH Switching
  • Schedule 23 - Registration Services
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
James Hardy
Solution Development
Proposed solution summary
  1. All communication methods referencing fax or facsimile will need to be removed and replaced with email
Proposed Solution Document
Document title
Existing References to Fax and "e-mail" in the REC (January 2024)
Upload document
Existing Fax References in the REC.pdf
Archive
Off
Document title
R00157 - Legal Text Changes (All Affected REC Products and Documents)
Upload document
R00157 - Draft Legal Text Changes.zip
Archive
Off
Problem Statement
Existing fax machines that are incompatible with new all IP digital networks will become obsolete and no longer capable of meeting Code Communications as prescribed in the REC
CP Form - Removal of a Fax as a Code Communication method
R0157 - Change Proposal Plan V1.0 (Approved) 30.01.2024
R0157 - Initial Assessment Report V1.0 (Approved) 30.01.2024
R0157 - Consolidated Consultation Responses
R0157 - Preliminary Change Report V1.0 (For Consultation) 09.02.2024
R0157 - Final Change Report V2.0 (Post-Vote) 19.03.2024
Open Reach Energy Industry Factsheet
Company Name
REC Code Manager
Review status
Review required

Allowing different Metering Equipment Managers (MEMs) to be appointed to Import and Export Metering Points

Date of latest update
Type
Change
ID
R0144
Change Category
Priority
Urgent
No
Latest Update
17/02/2025 - R0144 has been withdrawn by the Proposer, alongside it's joint BSC Change P459, as they cannot be progressed prior to MHHS. The Proposer will look to re-raise both changes in the future. The adoption window for this withdrawal has closed.
Summary
The Export Supplier needs to be able to appoint different MEMs to that of the Import Supplier
Proposer
Kit Dixon
Impacted Consumers
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I want a competitive Export market so I can get the best rates for the energy I generate. I want clear metering equipment ownership so I can be confident my meter is functional and safe. I want accurate billing from my Export Supplier.
  2. As an Export Supplier, I want to be able to appoint the MEM that ties in with my commercial strategy.
  3. As a MEM, I want clear guidance on the responsibilities I have for any metering equipment I am appointed to.
Problem Statement
Export Suppliers may become non-compliant with industry regulations if they are unable to appoint the same MEM as the Import Supplier, for example when the Consumer switches Import Supplier or when the Import Supplier changes the appointed MEM.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
Change Proposal Form
R0144 Change Proposal Plan Withdrawal v1.0 (Pre Approval)
R0144 Change Proposal Plan v1.0 (16.04.2024) Approved
R0144 Initial Assessment Report v1.0 (16.04.2024) Approved
Company Name
REC Code Manager
Review status
Review required
Schedule 14 - Metering Operations 4.0 – Implemented on
Market Participant Applicability
Market participant All Sections
Domestic Suppliers Mandatory
Non-Domestic Suppliers Mandatory
Gas Transporters Mandatory
Distribution Network Operators Mandatory
DCC N/A
Metering Equipment Managers Mandatory
Non-Party REC Service Users N/A
Loading...

Aligning electricity and gas timescale requirements for sharing Meter Technical Detail information

Date of latest update
Type
Change
ID
R0109
Change Category
Change Path
Priority
Urgent
No
Latest Update
22/03/2024 - Withdrawn.
Summary
Empty
Proposer
Elise Handy
Impacted Consumers
Impacted REC Documents
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
R0109 - Change Proposal Form
Company Name
Utility Warehouse
Review status
Review required