Updates to Schedule 14 Measurement Transformers Commissioning Timescales

Date of latest update
Type
Change
ID
R0284
Change Category
Change Path
Priority
Urgent
No
Latest Update
12/08/2026 - the Metering Expert Panel approved the Change Report (Final Recommendation) V1.2. This Change Proposal will be implemented on 26 June 2027. If you wish to appeal this decision, this must be received by COB 28 August 2026.
Summary
The current timetables in REC Schedule 14 Metering Operations sections 15.6 and 30.6, where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 and the Measurement Transformers are owned by the DNO, or in 15.7 and 30.7 where the Measurement Transformers are not owned by the DNO, may no longer be fit for purpose post the implementation of MHHS Milestone M16, where the Settlement timetable reduces the RF run to 4 months.
Proposer
Caroline Freimuller
Change Plan

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

03 Feb 2026

Presented at Change Issues Group

Completed

Start:

Due:

Completion:

05 Feb 2026

Change Report (For Consultation) approved by Metering Expert Panel

Completed

Start:

Due:

Completion:

08 Apr 2026
Impacted Consumers
Impacted REC Documents
Status
Implementation Date
Status Scheduled
EMAR Version 4.6.0_Scheduled

Documents

Name Version Last updated Actions
244.73 KB
Version 1.0 - 02 Nov 2026 PDF - 244.73 KB
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0284 Schedule 14 Metering Operations draft V0.2
Upload document
I0284 Schedule 14 Metering Operations draft V0.2.pdf
Archive
Off
Document title
R0284 Schedule 14 Metering Operations draft V0.3
Upload document
I0284 Schedule 14 Metering Operations draft V0.3.pdf
Archive
Off
Document title
R0284 Schedule 14 Metering Operations final version
Upload document
I0284 Schedule 14 Metering Operations final version.pdf
Archive
Off
Problem Statement
The current timetables in REC Schedule 14 Metering Operations sections 15.6 and 30.6, where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 and the Measurement Transformers are owned by the DNO, or in 15.7 and 30.7 where the Measurement Transformers are not owned by the DNO, may no longer be fit for purpose post the implementation of MHHS Milestone M16, where the Settlement timetable reduces the RF run to 4 months.
I0284 submission form
I0284 Change Report (Proposal Plan) V1.0 approved 03.02.26
I0284 Change Issue Group paper v1.0
I0284 Consolidated Impact Assessment Responses PUBLIC v1.0
R0284 Change Report (For Consultation) V1.0 approved 08.04.26
R0284 Consolidated Consultation Responses PUBLIC v1.0
R0284 Change Report (Final Recommendation) V1.2 approved 12.08.26
Company Name
REC Code Manager
Review status
Review required

Annual Address Management Plan Updates

Date of latest update
Type
Change
ID
R0283
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
Address management is the responsibility of DCC, with support from REC Parties. There has been progress resolving address data issues, but there is no mechanism to clearly establish code level targets for address improvement, or overall market performance.
Proposer
anton.moden
Change Plan

Proposal Plan approved at Change Panel

Completed

Start:

Due:

Completion:

21 Oct 2025

Final Recommendation approved at Change Panel

Completed

Start:

Due:

Completion:

16 Dec 2025
Impacted Consumers
Impacted REC Services
Status
Implementation Date
Status Superseded
EMAR Version 4.2.0_Superseded
Included changes Affected REC Items
R0179 Proposal for Limiting Queries in EES API Calls (Single Query per API Call)
R0190 Related Meter Point RMP status rules
  • Schedule 28 - Related Metering Points
R0198 Metering Asset Manager (MAM) Communication Method Register
R0242 Missing Scenario Variant from R0043
  • Market Message Catalogue
R0244 C21 to be introduced into STIRG Document
  • Data Item Catalogue
R0235A Missing Scenario Variants in D0179 Alternate Solution
R0256 MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101
  • Market Message Catalogue
R0270 Clarification of SIP Qualification Requirements
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 15 - Metering Accreditation
R0271 Clarification of ASP, AMI, and EMO Accession Requirements
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
R0272 Enabling transparency of the CRS Provider’s REC service level performance
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 26 - Switching Service Management
  • Schedule 24 - Switching Data Management
R0277 Data Latency SLA Alignment for Gas Enquiry Service
  • Schedule 1 - Interpretations and Definitions
R0280 CSS Certificate Authority audit clarification
  • Schedule 1 - Interpretations and Definitions
R0283 Annual Address Management Plan Updates
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 29 - Address Management
R0287 Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 23 - Registration Services
R0293 Housekeeping February 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0283 Legal Text For Consultation
Upload document
R0283 Legal Text For Consultation.zip
Archive
Off
Problem Statement
The REC Address Management Service is the responsibility of DCC, with support from REC Parties. There has been progress resolving address data issues, but there is no mechanism to clearly establish code level targets for address improvement, or overall market performance.
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
R0283 submission form
R0283 Change Report (Proposal Plan) v1.0 approved 21/10/2025
R0283 Change Report (For Consultation) v1.0
R0283 Consolidated Consultation Responses v1.0
R0283 - Change Report (Final Recommendation) Approved 16.12.25 v1.0
Company Name
REC Code Manager
Review status
Review required

Return of Legacy Meters

Date of latest update
Type
Issue
ID
I0282
Change Path
Priority
Urgent
No
Latest Update
08/04/2026 - The Closure Report was presented to the REC Metering Expert Panel at their meeting on 08 April 2026. The Issue has now been classed as resolved.
Summary
The issue identified is that current arrangements require or assume that legacy Meter Asset Providers (MAPs) take back old, non Smart Meters once they are removed from Consumers’ Premises, even though many of these meters are obsolete, cannot be reused, and ultimately require disposal. This has resulted in large volumes of legacy meters being transported across the country between storage providers and legacy MAPs, creating unnecessary cost, administrative burden, and environmental impact. Storage providers are issuing extensive lists of Meter Serial Numbers (MSN) to try to establish meter ownership, and legacy MAPs must manually verify these details. This process has been made more difficult by historical changes in company names and ownership structures. Once ownership is confirmed, the meters are frequently transported to the legacy MAP only for them to arrange disposal, which provides no net value and simply adds further transportation and handling costs.
Proposer
Bryan Heap
Change Report - Initial Assessment and Change Plan Report
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
The process for handling removed legacy non Smart Meters is inefficient and environmentally costly, with unclear ownership, unnecessary transport, and no established recycling route. A consistent, sustainable disposal solution is needed to reduce waste, simplify operations, and clarify the management of any scrap value.
I0282 submission form
I0282_Closure Report_v1.0 (26 March 2026)
Company Name
SP Electricity North West
Review status
Review required

Extending R0067 Refresh Functionality

Date of latest update
Type
Issue
ID
I0281
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/09/2026 - The update to plan has been approved by the Technical Expert Panel on 30 September 2026.
Summary
CSS Market Messages sent by the Central Switching Service (CSS) to Switching Data Service Providers (SDSPs) are either not being received, being received after Gate Closure, or are being received out of the order that they were originally sent in. This Issue originally aimed to extend the Refresh functionality, implemented for the Gas Retail Data Agent (GRDA).to the Electricity Retail Data Agent (ERDA). Following solution development for I0281, it was agreed that the Refresh functionality would be made available for all Market Participants in receipt of the in-scope messages.
Proposer
Finn Deacon
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
Francine Peyroux-Sissoko
Solution Development
Proposed Solution Document
Document title
I0281_Proposed_Legal text_PIA_V1.0.
Upload document
I0281_Proposed_Legal text_PIA_V1.0.zip
Archive
Off
Problem Statement
CSS messages are not received by the SDSPs in the order in which they were originally sent, or after Gate Closure, so it can be difficult to detect and often requires significant manual effort to resolve. This issue can directly impact Consumer switching experiences, causing disruption and possible delays in a switch.
Workgroup
Workgroup(s)
I0281_Change Report (Update to Plan) v1.0 (Pre-approval)
I0281_Change Report (Update to Plan) v2.0 Approved
I0281_Change Report (Update to Plan) v2.0 (Pre-approval)
I0281_Change Report (Update to Plan) v1.0 Approved 20.05.2026
I0281_Change Report (Proposal Plan) v1.0_Approved 04.11.2025
Company Name
REC Technical Services
Review status
Review required

CSS Certificate Authority audit clarification

Date of latest update
Type
Change
ID
R0280
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
CSS Certificate Authority Service Definition clause 9.1 states that the CSS CA Service will be audited each year by a third party against an approved compliance standard and or methodology. The clause however does not state who initiates the audit (i.e. RECCo, the Code Manager, Switching Operator etc.) and engages with the third party.
Proposer
Bradley Baker
Change Plan

Proposal Plan approved at Change Panel

Completed

Start:

Due:

Completion:

21 Oct 2025

Final Recommendation vote at PAB

Completed

Start:

Due:

Completion:

16 Dec 2025
Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 4.2.0_Superseded
Included changes Affected REC Items
R0179 Proposal for Limiting Queries in EES API Calls (Single Query per API Call)
R0190 Related Meter Point RMP status rules
  • Schedule 28 - Related Metering Points
R0198 Metering Asset Manager (MAM) Communication Method Register
R0242 Missing Scenario Variant from R0043
  • Market Message Catalogue
R0244 C21 to be introduced into STIRG Document
  • Data Item Catalogue
R0235A Missing Scenario Variants in D0179 Alternate Solution
R0256 MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101
  • Market Message Catalogue
R0270 Clarification of SIP Qualification Requirements
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 15 - Metering Accreditation
R0271 Clarification of ASP, AMI, and EMO Accession Requirements
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
R0272 Enabling transparency of the CRS Provider’s REC service level performance
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 26 - Switching Service Management
  • Schedule 24 - Switching Data Management
R0277 Data Latency SLA Alignment for Gas Enquiry Service
  • Schedule 1 - Interpretations and Definitions
R0280 CSS Certificate Authority audit clarification
  • Schedule 1 - Interpretations and Definitions
R0283 Annual Address Management Plan Updates
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 29 - Address Management
R0287 Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 23 - Registration Services
R0293 Housekeeping February 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0280 Legal Text approved 16.12.2025 v1.0
Upload document
R0280 - CSS Certificate Authority Service Definition approved 16.12.2025.docx
Archive
Off
Problem Statement
Section 9 of the CSS Certificate Authority Service Definition document mandates an annual third-party audit of the CSS Certificate Authority Service against an approved compliance standard or methodology. However, it does not specify the audit technique or methodology to be used, nor does it specify who is responsible for initiating the audit and engaging with the third-party.
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
R0280 submission form
R0280 Change Report (Proposal Plan) v1.0 approved 21/10/2025
R0280 Change Report (For Consultation) v1.0
R0280 Consolidated Consultation Responses v1.0
R0280 Change Report (Final Recommendation) Approved 16.12.25 v1.0
Company Name
Smart DCC
Review status
Review required

Housekeeping November 2025

Date of latest update
Type
Change
ID
R0279
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
The Code Manager has identified a number of non-material clarifications, typographical errors and changes needed to REC products.
Proposer
Caroline Freimuller
Change Plan

Approved at Change Panel

Completed

Start:

Due:

Completion:

21 Oct 2025
Status
Implementation Date
Status Superseded
EMAR Version 4.1.0_Superseded
Included changes Affected REC Items
R0152 Revision to the Consolidated Metering Code of Practice (CoMCoP)
  • MOCoPA (since removed)
  • ASPCoP (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Smart Meter Installation Schedule (since removed)
  • Gas Metering Code of Practice (since removed)
R0157 Removal of Facsimile as a Method of Code Communication
  • Schedule 14 - Metering Operations
  • Schedule 18 - Green Deal Arrangements
  • Standards Definition Document
  • Data Item Catalogue
R0191 Introduction of SLA for Supplier De-Registration on Disconnected Meters
  • Schedule 27 - RMP Lifecycle
R0205 Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches
R0212 Protecting Crimestoppers and their Contacts
R0215 Schedule 30 Switch Meter Reading Problems - Rejections and Timings
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
R0060 ERDS Service Definition timezone correction
  • Schedule 1 - Interpretations and Definitions
R0232 Non-Domestic Change of Occupier SDEP Screens (R0155 Solution)
R0243 Transfer of Standard Settlement Configuration and Time Pattern Regime Data Item Ownership
  • Data Item Catalogue
R0248 REC Changes to tie in with DCP451 - Suspending Registrations
  • Schedule 24 - Switching Data Management
R0254 Non-Domestic Change of Occupier Reporting (R0155 Solution)
R0255 Terms of Reference Updates
R0257 Change to REC for Data processing outside of EEA
R0263 Sharing Confirmed Energy Theft Data with the BSCCo
  • Schedule 7 - Energy Theft Reduction
R0269 Schedule 5 – Change Management: Clarity and Typographical Review
  • Schedule 1 - Interpretations and Definitions
  • Schedule 5 - Change Management
R0279 Housekeeping November 2025
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 7 - Energy Theft Reduction
  • Schedule 27 - RMP Lifecycle
  • Schedule 18 - Green Deal Arrangements
  • Schedule 24 - Switching Data Management
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Market Message Catalogue
R0227 Domestic Elective HH Switching
  • Schedule 23 - Registration Services
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
This Housekeeping Change Proposal seeks to make typographical and formatting corrections that have been identified and improve consistency across the REC.
November 2025 Housekeeping summary spreadsheet V1.0
November Housekeeping legal text (zip file) V1.0
R0279 Housekeeping Change Report V1.0 approved 21.10.25
Company Name
Code Manager
Review status
Review required

Establishing the Safe Isolation Provider (SIP) as a Standalone REC Party

Date of latest update
Type
Issue
ID
I0278
Change Category
Change Path
Priority
Urgent
No
Latest Update
21/07/2026 - An Update to Plan has been approved by the Change Panel on 21 July 2026.
Summary
This proposal recommends the formal recognition of the Safe Isolation Provider (SIP) as a standalone Party under the Retail Energy Code (REC). This aligns with the direction set out in Ofgem’s recently published Strategic Direction Statement (SDS), which explicitly calls for the establishment of SIPs as a standalone Party role. The aim is to address the growing scale of unregulated SIP activity, mitigate associated consumer safety risks, and ensure the metering industry is equipped to support the UK’s Net Zero ambitions. By enabling easier access to certified SIPs, this change will enhance consumer protection, accelerate low-carbon technology deployment, and improve operational efficiency across the energy sector.
Proposer
Rebecca Griffiths
Change Report - Initial Assessment and Change Plan Report

Comments deadline
Impacted Consumers
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Problem Statement
The current SIP framework poses several risks: - Consumers, MEMs and unaccredited practitioners’ safety. Unaccredited and unregulated isolation work increases the risk of unsafe installations and potential harm to Consumers. NAPIT highlighted to RECCo and DESNZ that 17 and 13 unregulated practitioners respectively died in 2023 and in 2024 due to unsafe isolation. With the right Party undertaking this work, there would also be less safety issues for the Consumer at their premises; - Inequity. Independent Installers face longer wait times compared to supplier-led installations, creating a two-tier system; - Low competitive market. Currently prospective Parties can be put off from applying to be a SIP as it appears they would need full MEM Accreditation which is often too far outside their current business operating model. Providing SIPs with their own pathway and requirements could result in more Parties becoming SIPs and therefore giving Consumers more choice in their provider; and - Decarbonisation delays. The inability to scale SIP capacity undermines the timely deployment of LZCTs, threatening Net Zero targets.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0278 submission form
I0278 Change Report (Proposal Plan) V1.0 (Pre-Approval) 09.10.2025
I0278_Change Report (Extension to Plan) v1.0 (Pre-Approval) 12.01.2026
I0278_Change Report (Extension to Plan) v2.0 (Pre-Approval) 13.07.2026
I0278_Change Report (Extension to Plan) v2.1 (Approved) 21.07.26
I0278_Consolidated Information Request DNO Responses
I0278_Consolidated Information Request MEM-SIP Responses PUBLIC
I0278_Consolidated Information Request RPA Responses
Company Name
RECCo
Review status
Review required

Data Latency SLA Alignment for Gas Enquiry Service

Date of latest update
Type
Change
ID
R0277
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
The current performance level for the processing of Data from CDSP is no longer fit for purpose and does not reflect the operational capability of the service. The performance level was originally conceived as part of the CSS programme in 2022 and operational reality has shown it is not required by industry. A revision of the performance level will align service performance metrics with system performance and deliver economic benefit.
Proposer
Andres Alvarez
Change Plan

Proposal Plan approved at Change Panel

Completed

Start:

Due:

Completion:

07 Oct 2025

Final Recommendation approved at TEP

Completed

Start:

Due:

Completion:

26 Nov 2025
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 4.2.0_Superseded
Included changes Affected REC Items
R0179 Proposal for Limiting Queries in EES API Calls (Single Query per API Call)
R0190 Related Meter Point RMP status rules
  • Schedule 28 - Related Metering Points
R0198 Metering Asset Manager (MAM) Communication Method Register
R0242 Missing Scenario Variant from R0043
  • Market Message Catalogue
R0244 C21 to be introduced into STIRG Document
  • Data Item Catalogue
R0235A Missing Scenario Variants in D0179 Alternate Solution
R0256 MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101
  • Market Message Catalogue
R0270 Clarification of SIP Qualification Requirements
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 15 - Metering Accreditation
R0271 Clarification of ASP, AMI, and EMO Accession Requirements
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
R0272 Enabling transparency of the CRS Provider’s REC service level performance
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 26 - Switching Service Management
  • Schedule 24 - Switching Data Management
R0277 Data Latency SLA Alignment for Gas Enquiry Service
  • Schedule 1 - Interpretations and Definitions
R0280 CSS Certificate Authority audit clarification
  • Schedule 1 - Interpretations and Definitions
R0283 Annual Address Management Plan Updates
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 29 - Address Management
R0287 Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 23 - Registration Services
R0293 Housekeeping February 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0277 Legal Text For Consultation
Upload document
R0277 Legal Text For Consultation.zip
Archive
Off
Problem Statement
The current performance levels for the processing of data from CDSP is no longer fit for purpose and does not align with system or service performance. The CSDP is also not meeting these performance levels on a monthly basis. While there are no known issues on data latency raised by users, this change to clarify performance levels is needed for the GES reinstated contract and to ensure ongoing service delivery.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0277 submission form
I0277 Change Report (Proposal Plan) approved 07/10/2025
R0277 Change Report (For Consultation) v1.0
R0277 Change Report (Final Recommendation) Approved 26.11.25 v1.0
Company Name
RECCo
Review status
Review required

SFIC to CMRM - missing Scenario Variant in D0126 / MM00016

Date of latest update
Type
Change
ID
R0276
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
It has been raised to the Code Manager by a Party that the Scenario Variant of Supply Fault Information Centre (SFIC) to Crowded Meter Room MEM (CMRM) is missing from the D0126 / MM00016 (Asset Condition Report Response / Clearance) Market Message. This should have been introduced as part of REC Change R0043 which introduced the role of the CMRM.
Proposer
Caroline Freimuller
Change Plan

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

16 Sep 2025
Impacted Consumers
Impacted REC Documents
Status
Implementation Date
Status Superseded
EMAR Version 4.3.0
Included changes Affected REC Items
R0267 Smart Meter Installation Surveys - Microbusiness requirements
  • Smart Meter Installation Schedule (since removed)
R0276 SFIC to CMRM - missing Scenario Variant in D0126 / MM00016
  • Market Message Catalogue
R0286 Clarification on Detailed Impact Assessment Activities
  • Schedule 5 - Change Management
R0291 Review of Schedule 1 Interpretations and Definitions
  • Schedule 1 - Interpretations and Definitions
R0299 Data Latency Targets for the GES Service Definition
R0300 Amendments to D0312 to align with BSC CP1622
  • Data Item Catalogue
R0307 Release and Licensing of the CoMCoP Logo for Accredited Parties
R0308 Update CCSG ToRs to include cross-code prioritisation as per Code Reform
R0310 Addition of value 11 to data item J0418
  • Data Item Catalogue
R0311 CoMCoP 2-year Audit Cycles
  • Schedule 15 - Metering Accreditation
R0316 Clarification of Data Items within the Payment Method Levelisation Supplier Data Reporting Specification
R0319 Clarification of in-year amendments to the CRS budget
R0320 Housekeeping June 2026
  • Schedule 1 - Interpretations and Definitions
  • Schedule 11 - Prepayment Arrangements
  • Schedule 7 - Energy Theft Reduction
  • Schedule 17 - Secure Data Exchange
  • Schedule 12 - Data Access
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
SFIC to CMRM - missing Scenario Variant in D0126 red-lining (IA)
Upload document
SFIC to CMRM - missing Scenario Variant in D0126 MM00016 legal text.docx
Archive
Off
Document title
SFIC to CMRM - missing Scenario Variant in D0126 red-lining (consultation)
Upload document
SFIC to CMRM - missing Scenario Variant in D0126 V2.0.docx
Archive
Off
Problem Statement
CMRMs can send the D0135 / MM00023 Asset Condition Report Market Message to the SFIC, but the SFIC cannot send a response on the D0126 / MM00016 Asset Condition Report Response / Clearance Market Message to confirm the outcome of their investigation.
R0276 submission form
R0276 Change Report (Proposal Plan) V1.0 approved 16.09.25
R0276 Consolidated Impact Assessment Responses PUBLIC v1.0
R0276 Change Report (For Consultation) V1.0
R0276 Consolidated Consultation Responses v1.0
R0276 Change Report (Final Recommendation) V1.0 approved 17.12.25
Company Name
REC Code Manager
Review status
Review required

MHHS Related Metering Points across Market Segments

Date of latest update
Type
Issue
ID
I0275
Change Category
Change Path
Priority
Urgent
No
Latest Update
17/09/2026 - The Code Manager has published a guidance document that acts as the solution for this Issue. A Closure Report has now been published, and this Issue has now been classed as resolved.
Summary
It has been identified by the MHHS Data Cleanse Working Group (DCWG) that around 9,000 existing Metering Point Relationships include Metering Points that would migrate into different Market-wide Half Hourly Settlement (MHHS) Market Segments. The majority of these are where one Metering Point has a Traditional meter installed (Smart Segment) and a Related Metering Point has an Advanced meter (Advanced Segment). This situation is currently valid but in MHHS would cause two problems. - SMRS would not be able to align the agent appointments, leaving secondary MPANs without agents and MHHS Migrations unable to fully complete.
Proposer
jonny.moore_42
Impacted Consumers
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0275 - Related Metering Points Guidance Document_V1.0.pdf
Upload document
I0275 - Related Metering Points Guidance Document_V1.0 (1).pdf
Archive
Off
Document title
I0275 - Closure Report_V1.0
Upload document
I0275_Closure Report_v1.0 (2).pdf
Archive
Off
Problem Statement
Without considering this Issue, there will be a risk to the MHHS migration. Indeed, a Metering Point installed which does not match its Related Metering Point (for example a Relationship between a Traditional meter with an Advanced Meter) will not be able to fully migrate to MHHS arrangements.
I0275 submission form
Company Name
RECCo
Review status
Review required