Resolution of invalid CSS data by Data Owners

Date of latest update
Type
Change
ID
R0061
Change Category
Change Path
Priority
Urgent
No
Latest Update
04 March 2024 - Change has been withdrawn following implementation of a solution outside of the REC Change Process. 10WD window to adopt change will close on 18 March 2024.
Summary
Data is sent via the Supplier or MEM to update MPRS, which is then sent to CSS. If the data is considered invalid at CSS, an error is returned to MPRS. MPRS is the conduit of data from the Suppliers & MEMs to CSS, and ERDAs are not responsible for the data, therefore only the supplier/MEM can correct the data. The incidents must be put on hold until the owner of the data corrects the issue, this is to prevent SLA breaches. SLAs does not apply to the Supplier/MEM explicitly, so the incidents remain in the DNOs/IDNOs queue with the need to chase every few days to prevent the incident being closed. The responsibility for the incidents should be on the data owners (Suppliers/MEMs).
Proposer
Elise Handy
Change Plan

Solution Analysis and Development

Completed

Start:

22 Aug 2022

Due:

15 Aug 2023

Completion:

15 Aug 2023

Service Provider Impact Assessment Due

Completed

Start:

15 Aug 2023

Due:

19 Oct 2023

Completion:

19 Oct 2023
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Lydia Bentley
Solution Development
Proposed solution summary
  1. As a Consumer, I want data relating to my energy supply to be accurate, so that I can have a consistent and faultless switching experience. As a Consumer, I want any data issues related to my switch to be resolved quickly and by the party responsible, to ensure a fast and efficient switching experience.
  2. As a DNO, I want my service level requirements to be reflective of my data ownership responsibilities, so that data queries can be resolved more efficiently. As the CSS Service Desk provider, I want my tickets to be allocated to the most appropriate party able to resolve them.
Proposed Solution Document
Document title
R0061 Solution - Service Desk Guidance Article
Archive
Off
Problem Statement
DNO/iDNOs are obligated to resolve data mismatches identified by the CSS during the switch process. However, they are unable to do so in cases where the Supplier/MEM owns data required to resolve the mismatch. Tickets assigned to the DNO (via MPRS) are therefore not going to the party best placed to resolve them, resulting in DNOs chasing the incident resolution every few days to prevent them being closed incorrectly.
Stages Selection
SME
SME Role
Lead Technical Analyst
R0061 - Change Proposal Form
R0061 - Initial Assessment Report v1.0 (Approved) - 18.07.2023
R0061 - Change Proposal Plan v1.0 (Approved) - 18.07.2023
R0061 Change Proposal Re-Plan (Approved) v1.0 - 19.10.23
Company Name
St Clements Services
Review status
Review required

ERDS Service Definition timezone correction

Date of latest update
Type
Change
ID
R0060
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
This change seeks to specify timezones within the ERDS Service Definition. For example: Data received by the ERDA shall be included within the ERDS Total Daily Processing on the basis that all data received prior to 23:00hrs is made available to the SMRA, EES Provider or CSS Provider (as applicable) by 06:00hrs the following Working Day. Data received after 23:00hrs will be made available to the SMRA, EES Provider or CSS Provider (as applicable) by the second Working Day
Proposer
Daniel Tadecicco
Change Plan

Change Proposal Plan and Impact Assessment Report Published

Completed

Start:

22 Aug 2022

Due:

18 Jun 2024

Completion:

18 Jun 2024

Change report and Consultation issued

Completed

Start:

18 Jun 2024

Due:

28 Jun 2024

Completion:

27 Jun 2024

Consultation closed

Completed

Start:

28 Jun 2024

Due:

19 Jul 2024

Completion:

19 Jul 2024

Responsible Committee decision

Completed

Start:

19 Jul 2024

Due:

28 Aug 2024

Completion:

28 Aug 2024

Appeal Window Closure

Not Started

Start:

28 Aug 2024

Due:

12 Sep 2024

Completion:

Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 4.1.0_Superseded
Included changes Affected REC Items
R0152 Revision to the Consolidated Metering Code of Practice (CoMCoP)
  • MOCoPA (since removed)
  • ASPCoP (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Smart Meter Installation Schedule (since removed)
  • Gas Metering Code of Practice (since removed)
R0157 Removal of Facsimile as a Method of Code Communication
  • Schedule 14 - Metering Operations
  • Schedule 18 - Green Deal Arrangements
  • Standards Definition Document
  • Data Item Catalogue
R0191 Introduction of SLA for Supplier De-Registration on Disconnected Meters
  • Schedule 27 - RMP Lifecycle
R0205 Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches
R0212 Protecting Crimestoppers and their Contacts
R0215 Schedule 30 Switch Meter Reading Problems - Rejections and Timings
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
R0060 ERDS Service Definition timezone correction
  • Schedule 1 - Interpretations and Definitions
R0232 Non-Domestic Change of Occupier SDEP Screens (R0155 Solution)
R0243 Transfer of Standard Settlement Configuration and Time Pattern Regime Data Item Ownership
  • Data Item Catalogue
R0248 REC Changes to tie in with DCP451 - Suspending Registrations
  • Schedule 24 - Switching Data Management
R0254 Non-Domestic Change of Occupier Reporting (R0155 Solution)
R0255 Terms of Reference Updates
R0257 Change to REC for Data processing outside of EEA
R0263 Sharing Confirmed Energy Theft Data with the BSCCo
  • Schedule 7 - Energy Theft Reduction
R0269 Schedule 5 – Change Management: Clarity and Typographical Review
  • Schedule 1 - Interpretations and Definitions
  • Schedule 5 - Change Management
R0279 Housekeeping November 2025
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 7 - Energy Theft Reduction
  • Schedule 27 - RMP Lifecycle
  • Schedule 18 - Green Deal Arrangements
  • Schedule 24 - Switching Data Management
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Market Message Catalogue
R0227 Domestic Elective HH Switching
  • Schedule 23 - Registration Services
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Supplier, I want to have confidence that the data in the systems is aligned and accurate.
  2. As ERDS Provider, I want to be able to provide accurate and appropriately labelled data that can be aligned with data from other systems.
Proposed Solution Document
Document title
R0060 Proposed legal text for decision 15.08.24.zip
Upload document
R0060 Proposed legal text for decision 15.08.24.zip
Archive
Off
Document title
R0060 Proposed legal text 27.06.24
Upload document
R0060 Proposed legal text 27.06.24.zip
Archive
Off
Document title
R0060 Legal Text ERDS Service Definition v1.0 06.06.2024
Upload document
R0060 Legal Text ERDS Service Definition v1.0 06.06.2024.pdf
Archive
Off
Document title
R0060 Approved legal text 28.08.24
Upload document
R0060 Approved legal text 28.08.24.zip
Archive
Off
Problem Statement
The ERDS Service Definition does not specify the time with a specified time zone. This has led to some instances of MPRS close of day running at 22:00GMT instead of 23:00GMT. A confirmation of time zone is required within the ERDS Service Definition to negate any confusion or delays in flow processing and systems becoming misaligned.
SME
SME Role
Lead Assurance Analyst
SME User
beth.brown@capgemini.com
SME Role
Lead Assurance Analyst
R0060 - Change Proposal Form
R0060 Consolidated RFI Responses v1.0 (05.03.2024)
R0060 Change Proposal Plan (Approved) v1.0 18.06.2024
R0060 - Initial Assessment Report v1.0 (Approved) 18.06.2024
R0060 Preliminary Change Report v1.0 (For Consultation) 27.06.2024
R0060 Consolidated Consultation Responses v1.0 (15.08.24)
R0060 Change Report (Final Recommendation - Approved) v2.0
Company Name
St Clements Services
Review status
Review required

Maintenance of Qualification Schedule Change

Date of latest update
Type
Change
ID
R0059
Change Category
Change Path
Priority
Urgent
No
Latest Update
03/11/23 - This change was implemented on 03 November 2023 as part of the November 2023 REC Release
Summary
This change seeks to clarify, strengthen and simplify a number of requirements within REC Schedule 9 – Qualification and Maintenance.
Proposer
Georgina Scott-Picton
Change Plan

Solution Development

Completed

Start:

05 Aug 2022

Due:

01 Mar 2023

Completion:

01 Mar 2023

Impact Assessment Start

Completed

Start:

01 Mar 2023

Due:

10 Mar 2023

Completion:

10 Mar 2023

Impact Assessment End

Completed

Start:

10 Mar 2023

Due:

24 Mar 2023

Completion:

24 Mar 2023

Preliminary Change Report Issued

Completed

Start:

24 Mar 2023

Due:

14 Apr 2023

Completion:

14 Apr 2023

Responsible Committee Review

Completed

Start:

14 Apr 2023

Due:

25 Apr 2023

Completion:

25 Apr 2023

Consultation Start

Completed

Start:

25 Apr 2023

Due:

28 Apr 2023

Completion:

28 Apr 2023

Consultation End

Completed

Start:

28 Apr 2023

Due:

22 May 2023

Completion:

22 May 2023

Final Change Report Issued

Completed

Start:

22 May 2023

Due:

16 Jun 2023

Completion:

15 Jun 2023

Responsible Committee Decision

Completed

Start:

16 Jun 2023

Due:

27 Jun 2023

Completion:

27 Jun 2023

Appeal Window Closure

Not Started

Start:

27 Jun 2023

Due:

11 Jul 2023

Completion:

Status
Implementation Date
Status Superseded
EMAR Version 3.6.0_Superseded
Included changes Affected REC Items
R0110 A review of Supplier access to data on GES
R0138 Combined progression of Change Proposals R0058, R0104 and R0129
R0140 Housekeeping amendments
R0059 Maintenance of Qualification Schedule Change
  • Schedule 1 - Interpretations and Definitions
  • Schedule 9 - Qualification and Maintenance
R0088 Make Shipper NExA values available on the GES portal
R0017 Invalid Requests for Site Technical Details
  • Schedule 14 - Metering Operations
  • Data Item Catalogue
  • Market Message Catalogue

Documents

Name Version Last updated Actions
222.91 KB
Version 1.0 - 02 Nov 2026 PDF - 222.91 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Jonathan Holland
Solution Development
Proposed solution summary
  1. As an Energy Supplier, DNO, GT, MEM and REC Service User, I want to understand precisely what obligations apply to me under the Schedule 9 – Qualification and Maintenance, so that I can provide the required information to the Code Manager in a timely manner and be compliant.
  2. As the REC Code Manager, I want REC Parties and REC Service Users to have a clear understanding of the information they need to submit relating to the maintenance of their qualification, so that necessary information can be submitted for review and consideration in the most efficient way.
Proposed Solution Document
Document title
R0059 - Draft legal text for IA v1.0 10.03.2023
Upload document
R0059 - Draft legal text for IA v1.0 10.03.2023.zip
Archive
Off
Document title
R0059 - Draft legal text for Consultation v1.0 14.04.2023
Upload document
R0059 - Draft legal text for Consultation v1.0 14.04.2023 (1).zip
Archive
Off
Document title
R0059 - Draft legal text for FCR v1.0 01.06.2023
Upload document
R0059 - Draft legal text for FCR v1.0 01.06.2023.zip
Archive
Off
Document title
R0059 - Final approved draft legal text v1.0 27.06.2023
Upload document
R0059 - Final approved draft legal text v1.0 27.06.2023.zip
Archive
Off
Document title
EMAR Link - R0059 - Draft legal text for FCR v1.0 01.06.2023
Archive
Off
Problem Statement
REC Service Users are required to submit Maintenance of Qualification Annual Statements to the Code Manager, the requirements differ depending on the User category. The lack of clear obligations for REC Service Users surrounding the Maintenance of Qualification reporting, set out in Schedule 9 – Qualification and Maintenance results in missing or partially completed submissions. Considerable time is spent by the Code Manager requesting and following up on individual submissions.
R0059 - Change Proposal Form
R0059 - Change Proposal Plan v1.0 (Approved) 07.02.2023
R0059 - Initial Assessment Report v1.0 (Approved) 07.02.2023
R0059 - Impact Assessment Responses V1.0 14.04.2023
R0059 - Preliminary Change Report v1.0 (approved) 25.04.2023
R0059 - Consolidated Consultation Responses v1.0 23.05.2023
R0059 - Final Change Report v2.0 (post-vote) 27.06.23
Company Name
-
Review status
Review required

Clarification of Supplier of Last Resort Obligations under the REC

Date of latest update
Type
Change
ID
R0057
Change Category
Change Path
Priority
Urgent
No
Latest Update
04/08/2023 - Change Proposal has been withdrawn as agreed with the Proposer. The Problem Statement was addressed through C3-0047 - Updates to PAB Procedures.
Summary
Within Schedule 19 – Market Exit and Supplier of Last Resort there is currently no consideration of circumstances where the Replacement Supplier is unable to fulfil its REC obligations in respect of Consumers transferred to them, due to them having little or no control over the processes of the failed supplier or it’s administrator. This change seeks to define when the Replacement Supplier is responsible for obligations relating to the Consumers gained through a Supplier of Last Resort (SoLR) Process.
Proposer
admin
Impacted Consumers
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer when my Energy Supplier goes out of business and I am transferred to a Replacement Supplier, I want my supply transfer to be handled quickly and have confidence that my new Supplier has all the necessary data to set up my account and bill me correctly from the transfer date, and if the Replacement Supplier fails to provide the expected level of service they will be appropriately held accountable.
  2. As a Replacement Supplier, I want the limitations affecting my ability to meet my REC obligations to be understood by the REC Code Manager and the Performance Assurance Board, so that any breaches of obligations are considered fairly and any limitations are taken into consideration.
  3. As the Code Manager I want to apply appropriate and proportionate Performance Assurance Techniques, taking in to account the ability of a Replacement Supplier to meet their obligations under the REC.
Proposed Solution Document
Document title
R0057 Draft Legal Text
Upload document
R0057 Draft Legal Text.zip
Archive
Off
Problem Statement
Currently, Replacement Suppliers are responsible for all obligations of the failed supplier from the date and time set out in the Last Resort Supply Direction, this includes a period of time prior to Consumer accounts transferring to the Replacement Supplier’s systems, limiting their ability to fulfil these obligations. This means that a Replacement Supplier may experience issues with the Performance Assurance obligations for which they are responsible, but do not have direct control over. Any breaches of obligations by a Replacement Supplier need to be considered fairly and any limitations the Replacement Supplier may face are taken into consideration.
Stages Selection
R0057 - Change Proposal Form
R0057 - Solution Options
R0057 - Consolidated Impact Assessment Responses
R0057 - Change Proposal Plan v1.0
R0057 - Initial Assessment Report v1.0 (Approved)
R0057 - Preliminary Change Report V1.0 (Approved)
Company Name
EDF
Review status
Review required

EES/GES Additional Service Request for Housing Associations to be added to the Data Access Matrix

Date of latest update
Type
Change
ID
R0056
Change Category
Change Path
Priority
Urgent
No
Latest Update
21/11/24 - Change Proposal withdrawn.
Summary
Housing Associations need to validate supply point information to ensure that they have the most up to date and accurate data against each property in their portfolio and also to complement their internal safety inspection processes. This change has been raised to enable Housing Associations to have access to data in EES and GES, to understand and confirm which of their properties contain live supply points, the meter locations, asset data and last inspection checks. This will also enable Housing Associations to update the industry where gas safety information is not accurate against their site data.
Proposer
Fay Morris
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
HA REC Requested Data Items.xlsx
Company Name
Correla Limited
Review status
Review required

Switching Operator Outage Notification Lead time

Date of latest update
Type
Change
ID
R0055
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/11/2022 - The REC Technical Expert Panel voted to approve R0055 for implementation on 24 February 2023.
Summary
Within the Switching Operator Service Definition, the Central Switching Service (CSS) Provider is required to provide 10 Working Days’ (WDs) notice of planned system outages. However, within the CSS Provider’s processes and the Switching Operator Change Management Process Category 3 document, an 8 WD lead time is set out. This change seeks to address this discrepancy.
Proposer
Cordelia Grey
Change Plan

Service Provider Impact Assessment

Completed

Start:

06 Jul 2022

Due:

19 Aug 2022

Completion:

19 Sep 2022

Party Impact Assessment

Completed

Start:

19 Aug 2022

Due:

26 Aug 2022

Completion:

13 Sep 2022

Preliminary Change Report Issued

Completed

Start:

26 Aug 2022

Due:

14 Oct 2022

Completion:

14 Oct 2022

Consultation Issued

Completed

Start:

14 Oct 2022

Due:

14 Oct 2022

Completion:

14 Oct 2022

Final Change Report Issued

Completed

Start:

14 Oct 2022

Due:

18 Nov 2022

Completion:

18 Nov 2022

Responsible Committee Decision

Not Started

Start:

18 Nov 2022

Due:

30 Nov 2022

Completion:

Status
Implementation Date
Status Superseded
EMAR Version 3.3.0_Superseded

Documents

Name Version Last updated Actions
203.39 KB
Version 1.0 - 02 Nov 2026 PDF - 203.39 KB
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As the CSS Provider, I want the service levels to be consistently defined across relevant REC Products. This will ensure that I am clear on the lead time I need to provide for planned outages and can meet the defined service level.
  2. As a CSS User, I want to understand how much notice I will get for planned outages of the CSS, so I am able to appropriately plan my activity reliant on this service.
  3. As a Switching Data Service Provider, I want to understand how much notice I will get for planned outages of the CSS. This will ensure I am able to appropriately plan my Operational Switching Service Changes and associated activities.
Proposed Solution Document
Document title
R0055 - Proposed Legal Text
Upload document
Proposed legal text changes submitted with the CP (2).pdf
Archive
Off
Problem Statement
Across REC products there is an inconsistency in the defined lead time for the CSS Provider to provide notification of scheduled maintenance and system outages. This may result in uncertainty for Switching Data Service Providers around when they should submit an Operational Switching Service Change. This is to ensure there is sufficient lead time for any change to be included within a planned maintenance release, and for CSS Users planning their operational activity around CSS availability.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0055 - Change Proposal Plan v1.0 (Approved)
R0055 - Initial Assessment Report v1.0 (Approved)
R0055 - Consolidated Consultation Responses
R0055 - Preliminary Change Report (Published for Consultation) v1.0
R0055 - Final Change Report v1.0 (Approved)
Company Name
DCC
Review status
Review required

EES Access for Virtual Lead Parties

Date of latest update
Type
Change
ID
R0054
Change Category
Change Path
Priority
Urgent
No
Latest Update
03/04/2023 - The Data Access Matrix changes went live on 04 November 2022, the technical changes to EES were implemented alongside R0022 on 03 April 2023.
Summary
This Change Proposal seeks to allow Virtual Lead Parties (VLP) access to the Electricity Enquiry Service (EES), to allow them to efficiently register their customers for balancing services under the Balancing and Settlement Code (BSC).
Proposer
Ann Perry
Change Plan

Service Provider Impact Assessment

Completed

Start:

17 Jun 2022

Due:

22 Jul 2022

Completion:

22 Aug 2022

Preliminary Change Report Issued

Completed

Start:

22 Jul 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Consultation Issued

Completed

Start:

02 Sep 2022

Due:

02 Sep 2022

Completion:

02 Sep 2022

Consultation Complete

Completed

Start:

02 Sep 2022

Due:

16 Sep 2022

Completion:

16 Sep 2022

Final Change Report Issued

Completed

Start:

16 Sep 2022

Due:

14 Oct 2022

Completion:

14 Oct 2022

Responsible Committee Decision

Completed

Start:

14 Oct 2022

Due:

26 Oct 2022

Completion:

26 Oct 2022
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 3.4.0_Superseded
Included changes Affected REC Items
R0047 Metering Code of Practice Consolidation Review
  • MOCoPA (since removed)
  • ASPCoP (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Smart Meter Installation Schedule (since removed)
  • Gas Metering Code of Practice (since removed)
R0025 Service Provider Performance Charges (DCC)
  • Schedule 6 - Performance Assurance
R0073 Introduction of a Housekeeping Change Proposal Process
  • Schedule 1 - Interpretations and Definitions
  • Schedule 5 - Change Management
R0084 Housekeeping changes to the approved legal text for R0047
  • MOCoPA (since removed)
  • ASPCoP (since removed)
  • REC Change Panel - Terms of Reference
  • Schedule 17 - Secure Data Exchange
R0091 Clarifications to the Theft Detection Incentive Scheme
  • Schedule 1 - Interpretations and Definitions
  • Schedule 7 - Energy Theft Reduction

Documents

Name Version Last updated Actions
1.0 16 Nov 2026
6.08 MB
Version 1.0 - 02 Nov 2026 PPTX - 6.08 MB
1.0 02 Nov 2026
163.13 KB
Version 1.0 - 02 Nov 2026 PDF - 163.13 KB
1.0 02 Nov 2026
140.07 KB
Version 1.0 - 02 Nov 2026 PDF - 140.07 KB
1.0 02 Nov 2026
128.82 KB
Version 1.0 - 02 Nov 2026 PDF - 128.82 KB
1.0 02 Nov 2026
62.46 KB
Version 1.0 - 02 Nov 2026 XLSX - 62.46 KB
1.0 02 Nov 2026
113.76 KB
Version 1.0 - 02 Nov 2026 PDF - 113.76 KB
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As an Energy Consumer, I want my VLP to have access to the data needed to correctly register me in a timely manner, so there aren’t delays in the delivery of my service.
  2. As a VLP, I want to have access to all the data I need to register my customers so I can deliver the service they have requested, without delay.
  3. As a VLP, I want to be able to use the EES to find the MPAN of a customer using their address information, to enable me to reliably gather this data to without delay or further engagement with my customer.
Proposed Solution Document
Document title
R0054 - Draft DAM Change
Upload document
R0054 Draft DAM changes.xlsx
Archive
Off
Document title
R0054 - Draft Legal Text
Upload document
R0054 Draft legal text v2.0.pdf
Archive
Off
Problem Statement
VLPs are required to provide their customer’s MPAN as part of the registration process, as per the Balancing and Settlement Code (BSC). VLPs do not currently have access to the EES to enable an MPAN search and they have no reliable means to acquire the MPAN, other than asking their customer to provide it. This could potentially lead to delays in the registration process and may result in an increased risk of inaccurate data, detrimentally impacting the service VLPs are able to provide to their customers.
R0054 - Initial Assessment Report v1.0 (Approved)
R0054 - Change Proposal Plan v1.0 (Approved)
R0054 - Preliminary Change Report v1.0 (Published for Consultation)
R0054 - Non-Confidential Consultation Responses
R0054 - Final Change Report v2.0
Company Name
-
Review status
Review required

GES Service Definition Document

Date of latest update
Type
Change
ID
R0052
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/11/2022 - The REC Technical Expert Panel voted to APPROVE R0052 for implementation on 24 February 2023.
Summary
The frequency of certain reports detailed in the Gas Enquiry Service (GES) Definition document are not consistent with the frequencies set out during the development of REC v3.0 and consulted on with industry stakeholders. This change seeks to align the reporting defined within the Service Definition with the originally intended timetable.
Proposer
Cristina Alvarez
Change Plan

Party Impact Assessment

Completed

Start:

13 Jun 2022

Due:

09 Sep 2022

Completion:

23 Sep 2022

Preliminary Change Report Issued

Completed

Start:

09 Sep 2022

Due:

21 Oct 2022

Completion:

21 Oct 2022

Consultation Issued

Completed

Start:

21 Oct 2022

Due:

21 Oct 2022

Completion:

21 Oct 2022

Final Change Report Issued

In Progress

Start:

21 Oct 2022

Due:

18 Nov 2022

Completion:

Responsible Committee Decision

Not Started

Start:

18 Nov 2022

Due:

30 Nov 2022

Completion:

Impacted REC Services
Status
Implementation Date
Status Superseded
EMAR Version 3.3.0_Superseded

Documents

Name Version Last updated Actions
203.39 KB
Version 1.0 - 02 Nov 2026 PDF - 203.39 KB
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Meter Asset Provider (MAP), I want it to be clear how and when I will receive reports relating to my portfolio, to ensure that I have the data required to operate efficiently.
  2. As a Meter Equipment Manager (MEM), I want it to be clear how and when I will receive reports relating to my portfolio, to ensure that I have the data required to operate efficiently.
  3. As the GES Service Provider, I want to have clearly and correctly defined requirements and responsibilities, to enable me to efficiently carry out my function as a REC Service Provider.
Proposed Solution Document
Document title
R0052 - Redlined Gas Enquiry Service Definition Document
Upload document
R0052 - Proposed legal text v0.3.docx
Archive
Off
Document title
R0052 - EMAR Change Sets
Archive
Off
Problem Statement
The Frequency of reports set out in the Gas Enquiry Service Definition document does not currently reflect the expected frequency for the ‘Supplier Registration report (MEM)’, ‘Portfolio Data (MEM)’ and ‘Portfolio Data (MAP)’ reports. The Gas Enquiry Service Definition needs to be amended to ensure that Meter Equipment Managers (MEMs) and Meter Asset Providers (MAPs) receive reports in the correct timeframe.
R0052 - Proposed legal text submitted with CP
R0052 - Change Proposal Form v1.0
R0052 - Change Proposal Plan v1.0 (Approved)
R0052 - Initial Assessment Report v1.1 (Approved)
R0052 - Preliminary Change Report v1.0 (Published for Consultation)
R0052 - Consolidated Consultation Responses v1.0
R0052 - Final Change Report v1.0 (Approved)
Company Name
-
Review status
Review required

Switch Request Objections (Change of Occupier)

Date of latest update
Type
Change
ID
R0051
Change Category
Change Path
Priority
Urgent
No
Latest Update
26/01/2024 - Withdrawn following adoption window closure.
Summary
This Change Proposal looks to clarity obligations regarding the losing suppliers' rights to object and the circumstances surrounding registrations by gaining suppliers, following the migration from the MRA to the REC.
Proposer
admin
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Stages Selection
R0051 - Downloadable CP form
Company Name
Business Energy Direct
Review status
Review required

Intellectual Property Rights and Services Data Main Body changes

Date of latest update
Type
Change
ID
R0049
Change Category
Change Path
Priority
Urgent
No
Latest Update
08/11/2024 - This Change Proposal has been implemented as part of the November 2024 REC Release.
Summary
The Central Registration Services (CRS) intellectual property rights (IPR) provisions in the Code were drafted before designation of v1.0 of the Code and primarily seek to deal with the CRS Services IPR as if it were IPR developed and owned by the CRS Provider or its contractors. In reality, much of the solution is built upon third party-owned software or platforms/services that are available to the market. Notwithstanding certain concessions were drafted in Clause 13.5 of the Code at designation, the scope of CRS Service IPR refers to some now obsolete terms and concepts and ought to be amended to clarify what the CRS Provider actually owns or is responsible for, to alleviate the existing ambiguity. Potential to amend Clause 13 of the Code as proposed in the attached mark-up, with consequential amendments to the associated definitions in Schedule 1 (Interpretation and Definitions). The definition “User” should be deleted from the Code and the defined terms “CSS User” or “REC Service User” (as applicable) used in substitution.
Proposer
Cordelia Grey
Change Plan

Party Impact Assessment Published

Completed

Start:

20 May 2022

Due:

04 Jul 2024

Completion:

04 Jul 2024

Preliminary Change Report & Consultation Published

Completed

Start:

04 Jul 2024

Due:

08 Aug 2024

Completion:

08 Aug 2024

Consultation Closes

Completed

Start:

08 Aug 2024

Due:

30 Aug 2024

Completion:

30 Aug 2024

Final Change Report Issued

Completed

Start:

30 Aug 2024

Due:

10 Sep 2024

Completion:

10 Sep 2024

Responsible Committee Decision

Completed

Start:

10 Sep 2024

Due:

17 Sep 2024

Completion:

17 Sep 2024

Appeal Window Closure

Not Started

Start:

17 Sep 2024

Due:

01 Oct 2024

Completion:

Status
Implementation Date
Status Superseded
EMAR Version 3.14.0_Superseded
Included changes Affected REC Items
R0108 Enabling Electricity Enquiry Service searches using a Unique Property Reference Number
R0113 Data Specification updates and clarifications
R0115 Frequency and content of CSS reports on switching via the DCC portal
R0119 Annulment Definition
  • Schedule 1 - Interpretations and Definitions
  • Schedule 23 - Registration Services
R0150 On-site Aggregation as a method to facilitate Third Party Access - BSC P455
  • Schedule 1 - Interpretations and Definitions
  • Schedule 25 - Central Switching Service
R0049 Intellectual Property Rights and Services Data Main Body changes
R0092A DCC Service Level Agreements for the Switching Incentive Regime (Alternative)
R0203 CSS Retry Strategy
  • Schedule 24 - Switching Data Management
R0206 Cross code change to align with BSC CP1598
  • Market Message Catalogue
R0211 November 2024 House Keeping Change
R0069 Amendments to Sample Access Agreement
  • Schedule 9 - Qualification and Maintenance
R0094 Clarify obligations on gas meter exchanges that occur close to CoS
  • Schedule 14 - Metering Operations
  • Market Message Catalogue
R0098 Optional fuzzy searching in EES

Documents

Name Version Last updated Actions
199.57 KB
Version 1.0 - 02 Nov 2026 PDF - 199.57 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Lydia Bentley
Solution Development
Proposed solution summary
  1. N/A – No tangible Consumer impact identified.
  2. As a REC Participant (Service Provider/User), I want the Code to clearly stipulate IPR requirements, so that CRS provisions and arrangements are readily identifiable.
Proposed Solution Document
Document title
R0049-Draft REC Main Body Changes V1.0 04.07.24
Upload document
R0049-Draft REC Main Body Changes V1.0 04.07.docx
Archive
Off
Problem Statement
There is uncertainty as to the scope of the various classes of Intellectual Property Rights (IPR) covered in Clause 13 of the REC Main Body (including the extent to which any IPR may exist in certain data, and the use of obsolete terms and concepts). As a result, there is a risk that the relevant industry stakeholders referred to in Clause 13 are unable to grant the licences and indemnities as described in that Clause. The current wording of Clause 5.3 of the REC Main Body requires amendments to ensure it correctly reflects the relationship between CRS Provider and RECCo, the services being provided and the entitlement to input VAT as a recipient of the CRS.
SME
SME Role
Lead Technical Analyst
SME User
caroline.milner@capgemini.com
SME Role
Lead Assurance Analyst
R0049 - Change Proposal Form
R0049 - Main Body amendments proposed by DCC
R0049 Change Proposal Plan (Approved) V1.0 03.07.24
R0049 Initial Assessment Report (Approved) V1.0 03.07.24
R0049 - Consolidated IA Responses V1.0 08.08.24
R0049 Change Report (Published for Consultation) V1.0 08.08.24
R0049 Consolidated Consultation Responses V1.0 02.09.24
R0049 Final Change Report (Approved) V2.0 17.09.24
Company Name
-
Review status
Review required